Overview
HEAVEN CITY
ROOF ENGICON PVT.LTD. · Patna
Units9
Booked7 of 9As of 2025-06-30
Construction progress95%As of 2025-06-30
Completion2022-12-31Proposed
Registered on2019-09-12
Valid to2022-12-31
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 2 unit types |
| Construction & progress | 4 progress details · 22 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 28 documents · 24 source links |
Registration
Registration
| Promoter | ROOF ENGICON PVT.LTD. | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00715-1/928/R-760/2019 | |
| Registered on | 2019-09-12 | |
| Valid to | 2022-12-31 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2022-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Environment Clearance | 2025-07-10 |
| Fire NOC | 2025-07-10 |
| Airport NOC | 2025-07-10 |
| Water Supply Permission | 2025-07-10 |
| Other approval | 2025-07-10 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,35,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,264.88 | |
|---|---|---|
| Built-up (m²) | 849.61 | |
| FAR | 0.92 | |
| Towers | 9 | |
| Units | 9 | |
| Booked | 7 | |
| Booked as of | 2025-06-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| Duplex | 1 | GANGA-1 |
| Duplex | 8 | TRIVENI |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 95% | |
|---|---|---|
| As of | 2025-06-30 | |
| Start | 2019-03-16 | |
| Proposed completion | 2022-12-31 |
Quarterly progress
| 2025-Q2 | 2025-07-10 | 95% | 7 |
| 2025-Q1 | 2025-04-14 | ||
| 2024-Q4 | 2025-01-09 | ||
| 2024-Q3 | 2024-10-08 | ||
| 2024-Q2 | 2024-07-14 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2023-04-07 | ||
| 2022-Q4 | 2023-03-21 | ||
| 2022-Q3 | 2023-03-21 | ||
| 2022-Q2 | 2023-03-21 | ||
| 2022-Q1 | 2022-04-08 | ||
| 2021-Q4 | 2023-01-07 | ||
| 2021-Q3 | 2021-09-30 | ||
| 2021-Q1 | 2023-03-16 | ||
| 2020-Q4 | 2023-03-16 | ||
| 2020-Q3 | 2023-03-16 | ||
| 2020-Q2 | 2023-03-16 | ||
| 2020-Q1 | 2023-03-16 | ||
| 2019-Q4 | 2023-03-16 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ROOF ENGICON PVT.LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP68201800715-1
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP68201800715&ld=pan&pj=RERAP68201800715-1&f=2025-2026&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP68201800715-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Q1 (Apr - Jun) / 2025-2026 · 2025-07-10
- Q4-Jan to Mar / 2024-2025 · 2025-04-14
- Q3-Oct to Dec / 2024-2025 · 2025-01-09
- Q2-Jul to Sep / 2024-2025 · 2024-10-08
- Q1-Apr to Jun / 2024-2025 · 2024-07-14
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-07
- Q3-Oct to Dec / 2022-2023 · 2023-03-21
- Q2-Jul to Sep / 2022-2023 · 2023-03-21
- Q1-Apr to Jun / 2022-2023 · 2023-03-21
- Q4-Jan to Mar / 2021-2022 · 2022-04-08
- Q3-Oct to Dec / 2021-2022 · 2023-01-07
- Q2-Jul to Sep / 2021-2022 · 2021-09-30
- Q4-Jan to Mar / 2020-2021 · 2023-03-16
- Q3-Oct to Dec / 2020-2021 · 2023-03-16
- Q2-Jul to Sep / 2020-2021 · 2023-03-16
- Q1-Apr to Jun / 2020-2021 · 2023-03-16
- Q4-Jan to Mar / 2019-2020 · 2023-03-16
- Q3-Oct to Dec / 2019-2020 · 2023-03-16
- 2025-Q1 · 2025-04-14
- 2024-Q4 · 2025-01-09
- 2024-Q3 · 2024-10-08
- 2024-Q2 · 2024-07-14
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-07
- 2022-Q4 · 2023-03-21
- 2022-Q3 · 2023-03-21
- 2022-Q1 · 2022-04-08
- 2021-Q4 · 2023-01-07
- 2021-Q3 · 2021-09-30
- 2021-Q1 · 2023-03-16
- 2020-Q4 · 2023-03-16
- 2020-Q3 · 2023-03-16
- 2020-Q2 · 2023-03-16
- 2019-Q4 · 2023-03-16