Overview
Hermitage Centralis
Hermitage Infra Developers · Sahibzada Ajit Singh Nagar (Mohali)
Units586
Completion2023-11-01Proposed
Valid to2023-11-01
Approvals11
Sections
| Property title & search report | |
|---|---|
| Approvals | 11 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 64 unit types |
| Construction & progress | 2 progress details · 30 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 39 documents · 44 source links |
Registration
Registration
| Promoter | Hermitage Infra Developers | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR0408 | |
| Valid to | 2023-11-01 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2023-11-01 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Clearances (Received) | 2018-05-18 |
| CLU Certificate | ||
| Environment Clearance certificate/ NOC | Clearances (Received) | 2018-09-07 |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2018-09-07 |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2018-09-07 |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2018-09-07 |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2022-03-28 |
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2018-03-16 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹2,08,32,86,800 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 29,151.58 | |
|---|---|---|
| Towers | 36 | |
| Maximum floors | 14 | |
| Units | 586 |
Unit types
| 4 BHK | 1,526 | 1 | TOWER A1 |
| 3 BHK | 983 | 14 | TOWER A1 |
| 3BHK | 983 | 14 | TOWER A2 |
| 4 BHK | 1,526 | 1 | TOWER A2 |
| 3BHK | 983 | 14 | TOWER A3 |
| 4 BHK | 1,526 | 1 | TOWER A3 |
| 3BHK | 983 | 14 | TOWER A4 |
| 4 BHK | 1,526 | 1 | TOWER A4 |
| 3BHK | 983 | 14 | TOWER A5 |
| 4 BHK | 1,526 | 1 | TOWER A5 |
| 3BHK | 983 | 14 | TOWER A6 |
| 4 BHK | 1,526 | 1 | TOWER A6 |
| 3BHK | 983 | 14 | TOWER A7 |
| 4 BHK | 1,526 | 1 | TOWER A7 |
| 3BHK | 974 | 14 | TOWER B1 |
| 4 BHK | 1,595 | 1 | TOWER B1 |
| 3BHK | 974 | 14 | TOWER B2 |
| 4 BHK | 1,595 | 1 | TOWER B2 |
| 3BHK | 974 | 14 | TOWER B3 |
| 4 BHK | 1,595 | 1 | TOWER B3 |
| 3BHK | 974 | 14 | TOWER B4 |
| 4 BHK | 1,595 | 1 | TOWER B4 |
| 3BHK | 974 | 14 | TOWER B5 |
| 4 BHK | 1,595 | 1 | TOWER B5 |
| 3BHK | 974 | 14 | TOWER B6 |
| 4 BHK | 1,595 | 1 | TOWER B6 |
| 3BHK | 974 | 14 | TOWER B7 |
| 4 BHK | 1,595 | 1 | TOWER B7 |
| 3BHK | 974 | 14 | TOWER B8 |
| 4 BHK | 1,595 | 1 | TOWER B8 |
| 3BHK | 974 | 14 | TOWER B9 |
| 4 BHK | 1,595 | 1 | TOWER B9 |
| 3BHK | 974 | 14 | TOWER B10 |
| 4 BHK | 1,595 | 1 | TOWER B10 |
| 3BHK | 974 | 14 | TOWER B11 |
| 4 BHK | 974 | 1 | TOWER B11 |
| 3BHK | 974 | 14 | TOWER B12 |
| 4 BHK | 1,595 | 1 | TOWER B12 |
| 3BHK | 974 | 14 | TOWER B13 |
| 4 BHK | 1,595 | 1 | TOWER B13 |
| 4 BHK | 1,595 | 1 | TOWER B14 |
| 3 BHK | 974 | 14 | TOWER B14 |
| 3BHK | 974 | 14 | TOWER B15 |
| 4 BHK | 1,595 | 1 | TOWER B15 |
| 4 BHK | 1,595 | 1 | TOWER B16 |
| 3 BHK | 974 | 14 | TOWER B16 |
| 4 BHK | 1,595 | 1 | TOWER B17 |
| 3 BHK | 974 | 14 | TOWER B17 |
| 4 BHK | 1,595 | 1 | TOWER B18 |
| 3 BHK | 974 | 14 | TOWER B18 |
| 4 BHK | 1,595 | 1 | TOWER B19 |
| 3 BHK | 974 | 14 | TOWER B19 |
| 3BHK | 974 | 14 | TOWER B20 |
| 4 BHK | 1,595 | 1 | TOWER B20 |
| 3BHK | 974 | 14 | TOWER B21 |
| 4 BHK | 1,595 | 1 | TOWER B21 |
| 3BHK | 884 | 13 | TOWER C1 |
| 3 BHK | 884 | 13 | TOWER C2 |
| 3 BHK | 884 | 13 | TOWER C3 |
| 3 BHK | 884 | 13 | TOWER C4 |
| 3BHK+1(Servant Room) | 1,093 | 27 | TOWER D1 |
| 3BHK+1(Servant Room) | 1,093 | 27 | TOWER D2 |
| 3BHK | 1,035 | 30 | TOWER E1 |
| 3BHK | 1,035 | 30 | TOWER E2 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-12-01 | |
|---|---|---|
| Proposed completion | 2023-11-01 |
Quarterly progress
| 2019-Q2 | 2021-09-22 |
| 2020-Q1 | 2021-09-22 |
| 2020-Q4 | 2021-09-22 |
| 2021-Q1 | 2021-09-22 |
| 2021-Q2 | 2021-09-22 |
| 2021-Q3 | 2021-10-19 |
| 2019-Q1 | 2021-10-23 |
| 2019-Q3 | 2021-10-23 |
| 2019-Q4 | 2021-10-23 |
| 2020-Q2 | 2021-10-23 |
| 2020-Q3 | 2021-10-23 |
| 2021-Q4 | 2022-01-09 |
| 2022-Q1 | 2022-04-11 |
| 2022-Q2 | 2022-07-22 |
| 2022-Q3 | 2022-10-09 |
| 2022-Q4 | 2023-01-12 |
| 2023-Q1 | 2023-04-12 |
| 2023-Q2 | 2023-07-15 |
| 2023-Q3 | 2023-11-02 |
| 2023-Q4 | 2024-02-08 |
| 2024-Q1 | 2024-08-23 |
| 2024-Q2 | 2024-10-25 |
| 2024-Q3 | 2024-10-25 |
| 2024-Q4 | 2025-01-27 |
| 2025-Q1 | 2025-04-25 |
| 2025-Q2 | 2025-07-26 |
| 2025-Q3 | 2025-10-14 |
| 2025-Q4 | 2026-01-20 |
| 2026-Q1 | 2026-04-21 |
| 2026-Q2 | 2026-08-01 |
Extensions
| Valid to |
|---|
| 2026-04-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Hermitage Infra Developers | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | State Bank of India | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10565&inPromoter_ID=1468&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2018-05-18
- Building Permit Issue from Municipal Authority · 2018-11-02 · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Environment Clearance certificate/ NOC · 2018-09-07
- Environment Clearance certificate/ NOC · 2018-09-07
- Environment Clearance certificate/ NOC · 2018-09-07
- Environment Clearance certificate/ NOC · 2018-09-07
- Environment Clearance certificate/ NOC · 2022-03-28
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-03-16
- Other Document () · 2022-05-02 · Sign in to download
- Other Document (Certificate Issued by Municipal Committee) · 2018-04-05 · Sign in to download
- Other Document (Form A and D from Registrar of Firms) · 2018-05-30 · Sign in to download
- Consent details of actual owner of Land · Sign in to download
- Advertisement and Brochure/ Prospectus · Sign in to download
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2018-05-18
- CLU Certificate
- Environment Clearance certificate/ NOC · 2018-09-07
- Environment Clearance certificate/ NOC · 2018-09-07
- Environment Clearance certificate/ NOC · 2018-09-07
- Environment Clearance certificate/ NOC · 2018-09-07
- Environment Clearance certificate/ NOC · 2022-03-28
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-03-16
- Extension order · Sign in to download
- 2019-Q2 · 2021-09-22
- 2020-Q1 · 2021-09-22
- 2020-Q4 · 2021-09-22
- 2021-Q1 · 2021-09-22
- 2021-Q2 · 2021-09-22
- 2021-Q3 · 2021-10-19
- 2019-Q1 · 2021-10-23
- 2019-Q3 · 2021-10-23
- 2019-Q4 · 2021-10-23
- 2020-Q2 · 2021-10-23
- 2020-Q3 · 2021-10-23
- 2021-Q4 · 2022-01-09
- 2022-Q1 · 2022-04-11
- 2022-Q2 · 2022-07-22
- 2022-Q3 · 2022-10-09
- 2022-Q4 · 2023-01-12
- 2023-Q1 · 2023-04-12
- 2023-Q2 · 2023-07-15
- 2023-Q3 · 2023-11-02
- 2023-Q4 · 2024-02-08
- 2024-Q1 · 2024-08-23
- 2024-Q2 · 2024-10-25
- 2024-Q3 · 2024-10-25
- 2024-Q4 · 2025-01-27
- 2025-Q1 · 2025-04-25
- 2025-Q2 · 2025-07-26
- 2025-Q3 · 2025-10-14
- 2025-Q4 · 2026-01-20
- 2026-Q1 · 2026-04-21
- 2026-Q2 · 2026-08-01