Overview
HERO HOMES Mohali Phase 2B
HERO REALTY PRIVATE LIMITED · Sahibzada Ajit Singh Nagar (Mohali)
Units246
Completion2027-07-31Proposed
Valid to2027-07-31
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 15 unit types |
| Construction & progress | 2 progress details · 16 quarters |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 35 documents · 28 source links |
Registration
Registration
| Promoter | HERO REALTY PRIVATE LIMITED | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PR0828 | |
| Valid to | 2027-07-31 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2027-07-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Permissions (Received) | 2016-06-09 |
| CLU Certificate | ||
| Electric Substation NOC | 2021-01-05 | |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2020-10-09 |
| License as Promoter from competent Authority | Permissions (Revised) | 2019-07-25 |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | Clearances (Received) | 2019-07-13 |
| NOC from Mining Department | Clearances (Received) | 2021-12-30 |
| Pollution Clearance from Punjab Pollution Control Board | Clearances (Received) | 2021-12-28 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹88,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 5,360.7 | |
|---|---|---|
| Towers | 3 | |
| Maximum floors | 21 | |
| Units | 246 |
Unit types
| 3BHK + 3T + Store | 101.85 | 6 | TOWER 14 |
| 3BHK + 3T + Utility+ Store | 117.07 | 35 | TOWER 14 |
| 3BHK + 3T + Store | 101.85 | 34 | TOWER 14 |
| 3BHK + 3T + Utility+ Store | 117.07 | 6 | TOWER 14 |
| 3BHK + 3T + Store | 107.58 | 1 | TOWER 14 |
| 3BHK + 3T + Utility+ Store | 117.07 | 29 | TOWER 15 |
| 3BHK + 3T + Utility+ Store | 117.07 | 12 | TOWER 15 |
| 3BHK + 3T + Store | 101.85 | 28 | TOWER 15 |
| 3BHK + 3T + Store | 101.85 | 12 | TOWER 15 |
| 3BHK + 3T + Store | 107.58 | 1 | TOWER 15 |
| 3BHK + 3T + Store | 101.85 | 34 | TOWER 16 |
| 3BHK + 3T + Store | 101.85 | 6 | TOWER 16 |
| 3BHK + 3T + Store | 107.58 | 1 | TOWER 16 |
| 3BHK + 3T + Utility+ Store | 117.07 | 35 | TOWER 16 |
| 3BHK + 3T + Utility+ Store | 117.07 | 6 | TOWER 16 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-08-01 | |
|---|---|---|
| Proposed completion | 2027-07-31 |
Quarterly progress
| 2022-Q4 | 2023-01-10 |
| 2023-Q1 | 2023-04-07 |
| 2023-Q2 | 2023-07-11 |
| 2023-Q3 | 2023-10-12 |
| 2023-Q4 | 2024-01-06 |
| 2024-Q1 | 2024-04-09 |
| 2024-Q2 | 2024-07-11 |
| 2024-Q3 | 2024-10-11 |
| 2024-Q4 | 2025-01-13 |
| 2025-Q1 | 2025-04-14 |
| 2025-Q2 | 2025-07-10 |
| 2025-Q3 | 2025-10-14 |
| 2025-Q4 | 2026-01-09 |
| 2026-Q1 | 2026-04-14 |
| 2026-Q2 | 2026-07-10 |
| 2026-Q3 | 2026-10-12 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | HERO REALTY PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 6 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | TECHNICAL PROJECTS CONSULTANTS PVT LTD |
| Architect | RAJINDER KUMAR AND ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11472&inPromoter_ID=1148&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2016-06-09
- Borewell Registration certificate from Central Ground Water Authority · 2021-05-27
- Building Permit Issue from Municipal Authority · 2019-05-20 · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2021-01-05
- Environment Clearance certificate/ NOC · 2020-10-09
- License as Promoter from competent Authority · 2019-07-25
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2019-07-13
- NOC from Mining Department · 2021-12-30
- Other Document (AAI Representation) · 2022-10-27 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2021-12-28
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2016-06-09
- CLU Certificate
- Electric Substation NOC · 2021-01-05
- Environment Clearance certificate/ NOC · 2020-10-09
- License as Promoter from competent Authority · 2019-07-25
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2019-07-13
- NOC from Mining Department · 2021-12-30
- Pollution Clearance from Punjab Pollution Control Board · 2021-12-28
- 2022-Q4 · 2023-01-10
- 2023-Q1 · 2023-04-07
- 2023-Q2 · 2023-07-11
- 2023-Q3 · 2023-10-12
- 2023-Q4 · 2024-01-06
- 2024-Q1 · 2024-04-09
- 2024-Q2 · 2024-07-11
- 2024-Q3 · 2024-10-11
- 2024-Q4 · 2025-01-13
- 2025-Q1 · 2025-04-14
- 2025-Q2 · 2025-07-10
- 2025-Q3 · 2025-10-14
- 2025-Q4 · 2026-01-09
- 2026-Q1 · 2026-04-14
- 2026-Q2 · 2026-07-10
- 2026-Q3 · 2026-10-12