Overview
HLP PALMILLAS
HLP INFRATECH LLP · Sahibzada Ajit Singh Nagar (Mohali)
Units273
Booked5 of 273As of 2026-09-30
Completion2027-03-23Proposed
Registered on2022-05-18
Valid to2027-03-23
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 34 unit types |
| Construction & progress | 2 progress details · 18 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 40 documents · 30 source links |
Registration
Registration
| Promoter | HLP INFRATECH LLP | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PR0791 | |
| Registered on | 2022-05-18 | |
| Valid to | 2027-03-23 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2027-03-23 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Legal Documents (Received) | 2025-10-24 |
| CLU Certificate | ||
| Electric Substation NOC | Revisions (Applied) | 2025-11-04 |
| Electric Substation NOC | 2023-11-15 | |
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| Other Document (Forest NOC ) | 2025-07-10 | |
| Pollution Clearance from Punjab Pollution Control Board | Clearances (To Be Applied) | 2022-03-12 |
| Pollution Clearance from Punjab Pollution Control Board | 2025-09-03 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹43,85,05,871 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 79,396.982 | |
|---|---|---|
| Units | 273 | |
| Booked | 5 | |
| Booked as of | 2026-09-30 |
Unit types
| 167-189, 194-204, 338-345, 350-357, 326-328 | 83.61 | 53 | 0 | ECONOMIC WEAKER SECTION PLOTS |
| SCO 31-32 | 25.78 | 2 | 1 | COMMERCIAL PLOTS |
| Plot No S-01 TO S-05 | 27.86 | 5 | 0 | COMMERCIAL PLOTS |
| Plot S-06 | 21.59 | 1 | 0 | COMMERCIAL PLOTS |
| Plot No S-07 | 16.34 | 1 | 0 | COMMERCIAL PLOTS |
| Plot No S-08 to S-13 | 14.86 | 6 | 0 | COMMERCIAL PLOTS |
| SCO 14 to 27 | 83.61 | 14 | 0 | COMMERCIAL PLOTS |
| SCO 28 TO 30 | 54.34 | 3 | 0 | COMMERCIAL PLOTS |
| Plot No.74-123 , 268-277 | 125.419 | 60 | 0 | PLOTS FOR INDEPENDENT FLOORS |
| Plot No 46A to 46G | 125.419 | 7 | 1 | RESIDENTIAL PLOTS |
| Plot No 293-297 | 123.85 | 5 | 1 | RESIDENTIAL PLOTS |
| Plot No 304-319 | 93.01 | 16 | 1 | RESIDENTIAL PLOTS |
| Plot No 383 - 391 | 119.29 | 9 | 1 | RESIDENTIAL PLOTS |
| Resindetial Plot 372-377 | 113.261 | 6 | 0 | RESIDENTIAL PLOTS |
| Residential Plot No 371 | 113.68 | 1 | 0 | RESIDENTIAL PLOTS |
| Residential Plot 363-370 | 94.072 | 8 | 0 | RESIDENTIAL PLOTS |
| Plot No 382 | 118.38 | 1 | 0 | RESIDENTIAL PLOTS |
| Plot No 324-325 | 112.87 | 2 | 0 | RESIDENTIAL PLOTS |
| Plot No 46 | 122.62 | 1 | 0 | RESIDENTIAL PLOTS |
| Plot No 43-45 | 125.4 | 3 | 0 | RESIDENTIAL PLOTS |
| Plot No 381E | 91.422 | 1 | 0 | RESIDENTIAL PLOTS |
| Plot No 379 - 381D | 93.69 | 7 | 0 | RESIDENTIAL PLOTS |
| Resiential Plot 378 | 95.97 | 1 | 0 | RESIDENTIAL PLOTS |
| Plot No 301-303 | 97.55 | 3 | 0 | RESIDENTIAL PLOTS |
| Plot No 362 | 95.19 | 1 | 0 | RESIDENTIAL PLOTS |
| Plot No 357A, 357B, 358 - 361 | 93.52 | 6 | 0 | RESIDENTIAL PLOTS |
| Plot No 41-42 | 125.18 | 2 | 0 | RESIDENTIAL PLOTS |
| Plot No 346-349 | 125.419 | 4 | 0 | RESIDENTIAL PLOTS |
| Plot No 329-337 | 99.29 | 9 | 0 | RESIDENTIAL PLOTS |
| Plot No 299-300 | 102.191 | 2 | 0 | RESIDENTIAL PLOTS |
| Plot No 288 - 292 | 99.056 | 5 | 0 | RESIDENTIAL PLOTS |
| Plot No 135 -152 | 125.419 | 18 | 0 | RESIDENTIAL PLOTS |
| Plots No 278-285 | 104.516 | 8 | 0 | RESIDENTIAL PLOTS |
| Plot No 286-287 | 116.12 | 2 | 0 | RESIDENTIAL PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-03-24 | |
|---|---|---|
| Proposed completion | 2027-03-23 |
Quarterly progress
| 2022-Q2 | 2022-09-13 | ||
| 2022-Q3 | 2022-11-10 | ||
| 2022-Q4 | 2023-02-09 | ||
| 2023-Q1 | 2023-04-11 | ||
| 2023-Q2 | 2023-09-07 | ||
| 2023-Q3 | 2024-02-09 | ||
| 2023-Q4 | 2024-02-16 | ||
| 2024-Q2 | 2024-07-17 | ||
| 2024-Q1 | 2024-07-17 | ||
| 2024-Q3 | 2025-04-08 | ||
| 2024-Q4 | 2025-04-08 | ||
| 2025-Q1 | 2025-04-08 | ||
| 2025-Q2 | 2025-07-05 | ||
| 2025-Q3 | 2025-10-08 | ||
| 2025-Q4 | 2026-01-10 | ||
| 2026-Q1 | 2026-04-07 | ||
| 2026-Q2 | 2026-07-15 | ||
| 2026-Q3 | 2026-10-04 | 0 | 5 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | HLP INFRATECH LLP | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | IDFC Bank Limited | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectQuarterlyUpdateViewDetails?inProject_ID=11438&inPromoter_ID=2319&inPromoterType=11438&inQUProject_ID=5759&inQUProject_DN=QUP2026T20265759&inQUProjectYear=2026&inQUProjectQTR=ThirdQTR
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11438&inPromoter_ID=2319&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-10-24
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-11-04
- Electric Substation NOC · 2023-11-15
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- Other Document () · 2025-11-03 · Sign in to download
- Other Document (Forest NOC ) · 2025-07-10
- Other Document (Sewerage Clearnce) · 2022-03-11 · Sign in to download
- Other Document (undertaking ) · 2025-10-31 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2022-03-12
- Pollution Clearance from Punjab Pollution Control Board · 2025-09-03
- Consent details of actual owner of Land · Sign in to download
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Annual Report (Form-5 CA Certificate)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-10-24
- CLU Certificate
- Electric Substation NOC · 2025-11-04
- Electric Substation NOC · 2023-11-15
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- Other Document (Forest NOC ) · 2025-07-10
- Pollution Clearance from Punjab Pollution Control Board · 2022-03-12
- Pollution Clearance from Punjab Pollution Control Board · 2025-09-03
- 2022-Q2 · 2022-09-13
- 2022-Q3 · 2022-11-10
- 2022-Q4 · 2023-02-09
- 2023-Q1 · 2023-04-11
- 2023-Q2 · 2023-09-07
- 2023-Q3 · 2024-02-09
- 2023-Q4 · 2024-02-16
- 2024-Q2 · 2024-07-17
- 2024-Q1 · 2024-07-17
- 2024-Q3 · 2025-04-08
- 2024-Q4 · 2025-04-08
- 2025-Q1 · 2025-04-08
- 2025-Q2 · 2025-07-05
- 2025-Q3 · 2025-10-08
- 2025-Q4 · 2026-01-10
- 2026-Q1 · 2026-04-07
- 2026-Q2 · 2026-07-15