Overview
Runwal Garden City Cluster 6 Tower 6 to 9
HORIZON PROJECTS PVT LTD · Dombivali
Units1,186
Booked83 of 1,186As of 2026-10-29
Completion2029-03-31Revised · Proposed 2027-05-31
Registered on2023-09-11
Cases4
Sold269As of 2026-10-29T22:56:29.398Z
Median ₹/sq ft carpet₹10,416As of 2026-10-29T22:56:29.398Z
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 4 cases |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details |
| Valuation | 7 ledger details · 1 unit type |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 2 developer details · 2 professional firms |
| The evidence | |
| Sources | 53 documents · 12 source links |
Registration
Registration
| Promoter | HORIZON PROJECTS PVT LTD | |
|---|---|---|
| District | Thane | |
| Locality | Dombivali | |
| Regulator | MahaRERA | |
| Registration number | P51700052561 | |
| Registered on | 2023-09-11 | |
| Project type | Residential / Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2027-05-31 | |
| Revised completion | 2029-03-31 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| 3771 | Bombay High Court |
| 1148 | Bombay High Court |
| 9701 | Bombay High Court |
| 534 | Additional Commissioner Konkan Division |
Complaints & cases
| Cases | 4 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹40,39,66,536 | |
|---|---|---|
| Construction | ₹4,05,81,34,000 | |
| Total | ₹5,34,21,00,536 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 1,186 | |
|---|---|---|
| Booked | 83 | |
| Booked as of | 2026-10-29 |
Valuation
What is it worth?
Valuation
Unit ledger
| As of | 2026-10-29T22:56:29.398Z | |
|---|---|---|
| Units | 1,186 | |
| Sold | 269 | |
| Booked | 83 | |
| Unsold | 834 | |
| Median ₹/sq ft carpet | 10,416 | |
| Reckoner ratio, median | 1.632090253838922 |
Ledger by unit type
| Carpet minimum (m²) | Carpet maximum (m²) | Sold | Median ₹/sq ft carpet | Median consideration |
|---|---|---|---|---|
| 32.87 | 71.5 | 269 | 10,416 | ₹43,39,301 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2027-05-31 | |
|---|---|---|
| Revised completion | 2029-03-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | HORIZON PROJECTS PVT LTD | |
|---|---|---|
| Other projects in this city pack | 9 |
Professional firms
| Role | Firm |
|---|---|
| CA | Kshirsagar and Associates |
| CA | M B Agrawal and CO |
Sources
Sources
Source URLs & documents
- https://maharera.maharashtra.gov.in/map-projects-search-result
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getFinaceDesignatedBankDetails
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getFinanceEstimatedActualCost
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectGeneralDetailsByProjectId
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectLitigationDetails
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectMeansOfFinance
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectNaPlotWithStructure
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectNaPlotWithoutStructure
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectProfessionalByType
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectSoldUnsoldInventory
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getUploadedDocuments
- https://maharerait.maharashtra.gov.in/public/project/view/45326
- Other – Technical · 2023-08-05
- Other – Technical · 2023-08-07
- Form 1 Cluster 6 Tower 6 to 9.pdf · 2026-10-19
- Form 3 - Cluster 6.pdf · 2026-10-17
- ENGINEERS CERTIFICATE CLUSTER 6.pdf · 2026-10-19
- Declaration Form B · 2023-08-07
- Ground (Part) Area Calculations- Tower 7- Cluster 6.pdf · 2023-08-03
- Ground floor Area calculations- Tower 8- Cluster 6.pdf · 2023-08-03
- Ground floor line diagram with Shops- Cluster 6.pdf · 2023-08-03
- Ground floor Parking Plan- Cluster 6 parking statment highlighted.pdf · 2023-08-03
- Refuge Floors- Tower 6- Cluster 6.pdf · 2023-08-03
- Refuge Floors- Tower 7- Cluster 6.pdf · 2023-08-03
- Refuge floors- Tower 8- Cluster 6.pdf · 2023-08-03
- Refuge floors- Tower 9- Cluster 6.pdf · 2023-08-03
- Section Elevation- Tower 6- Cluster 6.pdf · 2023-08-03
- Section Elevation- Tower 7- Cluster 6.pdf · 2023-08-03
- Section Elevation- Tower 8- Cluster 6.pdf · 2023-08-03
- Section Elevation- Tower 9- Cluster 6.pdf · 2023-08-03
- Section- Cluster 6.pdf · 2023-08-03
- Sub Plot Area calculation.pdf · 2023-08-03
- Typical except Refuge Floor- Tower 6- Cluster 6.pdf · 2023-08-03
- Typical Floor except Refuge- Tower 7- Cluster 6.pdf · 2023-08-03
- Typical floors except Refuge- Tower 8- Cluster 6.pdf · 2023-08-03
- 1st floor Typical floors except Refuge- Tower 9- Cluster 6.pdf · 2023-08-03
- 2nd 3rd floor Podium Plan- Cluster 6.pdf · 2023-08-03
- 2nd to 4th Podium Floor- Tower 6- Cluster 6.pdf · 2023-08-03
- 4th Podium Plan- Cluster 6.pdf · 2023-08-03
- Area line diagram- 4th Podium- Cluster 6.pdf · 2023-08-03
- Area diagram- Basement- Cluster 6.pdf · 2023-08-03
- Area line diagram- 1st Podium- Cluster 6.pdf · 2023-08-03
- 1st floor- Tower 8- Cluster 6.pdf · 2023-08-03
- 1st Podium floor Plan- Cluster 6.pdf · 2023-08-03
- 1st Podium Floor- Tower 6- Cluster 6.pdf · 2023-08-03
- 1st Podium Floor- Tower 7- Cluster 6.pdf · 2023-08-03
- HIGHLIGHTED PLINTH AREA.pdf · 2023-08-07
- HIGHLIGHTED BUILT UP AND PARKING.pdf · 2023-08-07
- FORM 1 Cluster 6 TOWER 6 to 9 31 dec 24.pdf · 2025-02-06
- CLUSTER 6.pdf · 2024-10-25
- Form 3 Cluster 6 Tower 6 to 9 24 Jan 2025.pdf · 2025-02-03
- Form 3 - Cluster 6.pdf · 2024-10-29
- ENGINEER'S CERTIFICATE _CLUSTER_6_ P1_Dec'2024.pdf · 2025-01-30
- ENGINEER'S CERTIFICATE CLUSTER 6 Tower 6 to 9 Dec 2024.pdf · 2025-02-03
- CLUSTER 6.pdf · 2024-11-07
- CLUSTER 6-rotated.pdf · 2024-11-07
- Form 3 Cluster 6.pdf · 2025-08-13
- CL6 TOWER 6 to 9 31st March 2025.pdf · 2025-04-23
- ENGINEER'S CERTIFICATE CLUSTER 6 P1 31st March 2025.pdf · 2025-04-23
- Form 1 CL 6 TOWER 6 to 9.pdf · 2025-08-13
- Form 2 CL06 T6-9.pdf · 2025-08-13
- Form 3 Cluster 6.pdf · 2025-08-13
- MY CITY- PHASE III -CLUSTER 06.pdf · 2025-08-13
- Declaration HPPL signed.pdf · 2025-08-13
- Document