Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Page 1
Page 1 of the encumbrance certificate. Filed with K-RERA: Encumbrance Certificate.
Approvals
| Power NOC | Filed with the registration | |
|---|---|---|
| Fire NOC | Filed with the registration | |
| Environmental clearance | SEIAA 123 CON 2020 · issued 6 Mar 2021 | Clear |
| Airport height NOC | Filed with the registration | |
| Pollution board (CFE) | Filed with the registration | |
Disputes & cases
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Projects within 4 km, counted | 1 (1 with an approximate location) |
|---|
Location & risks
Construction & progress
Developer
| Estimated cost, at registration | ₹357.50 Cr |
|---|
Loan & collateral
| Escrow bank | CORPORATION BANK · SC Road Ananda Rao circle |
|---|
Data room
65 documents filed with K-RERA for this project
₹99 for this report opens Disputes & cases and Documents for this project, yours to read for good.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | 1 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | 1 | – | – | Red flag |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| 1 Lakh Multi Storey Bengaluru Housing ProgrammeLapsed · completion date passed | Rajiv Gandhi Housing Corporation Limited | Apartment | 323 sqft carpet (as filed) | Mar 2024 |
| A.R RuthviLapsed · completion date passed | G.RAVINDRAKUMAR & M.K.ASHOKA | Plot | ~1,200–1,500 sqft (estimate: filed carpet plus 25%) | Dec 2025 |
| A.R Ruthvi Phase 2Filed as completed · no completion certificate on record | T MANJUNATHA | Plot | ~1,200–1,500 sqft (estimate: filed carpet plus 25%) | Feb 2024 |
| Ag Varaha ValleyApplied for completion 23/01/2026 | ABHISHEK . A | Plot | ~1,230–1,500 sqft (estimate: filed carpet plus 25%) | Aug 2025 |
| Arvind LakeviewActive · 90% built | Arvind Builders | Plot | ~1,200–4,000 sqft (estimate: filed carpet plus 25%) | Dec 2027 |
| Arvind OrchidsApplied for completion 16/02/2024 | Arvind Builders | Plot | ~1,200–1,680 sqft (estimate: filed carpet plus 25%) | Dec 2023 |
| Ashwasurya LegacyRegistered · no quarterly update yet | M/s. Suryakalpa Ventures | Plot | ~1,200–2,220 sqft (estimate: filed carpet plus 25%) | Dec 2029 |
| B.T.G LayoutApplied for completion 11/03/2023 | SHARADAMMA | Plot | ~600–1,200 sqft (estimate: filed carpet plus 25%) | Aug 2021 |
8 of 65 other projects in West Bengaluru, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Housing Scheme in the interactive atlas
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Land area of this registration | 7,38,195 sq m |
|---|
| Water supply NOC |
|---|
| Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 19 Nov 2021 |
₹99 for this report opens Disputes & cases and Documents for this project, yours to read for good.
| Plots in them | 96 |
|---|
| Booked | 42 of 96 (44%) |
|---|
| Unsold | 54 |
|---|
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 15.5 km, Siddeswara Layout |
|---|
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed tank |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 30.1 m
Taluk average; not a reading at the site.
| Groundwater | Nelamangala taluk average, July 2023: 27.9 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2024, 0 of 3 CGWB wells in Nelamangala taluk read in this class | |
| Through the year | January 2024: 5.2 m (3 wells), Pre-monsoon 2024: 5.4 m (3 wells), August 2024: 5.4 m (3 wells), depth below ground of CGWB's monitoring wells in Nelamangala taluk (the median where there are several) | |
| Water supply, as filed | Self development |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km |
| RERA completion date | 19 Nov 2021 | Red flag |
|---|---|---|
| Work began, as filed | 20 Jan 2021 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Fire safety | Filed with the registration | |
|---|---|---|
| Environmental clearance | SEIAA 123 CON 2020 · issued 6 Mar 2021 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Escrow bank | CORPORATION BANK · SC Road Ananda Rao circle |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | None within 3 km | |
|---|---|---|
| Metro, operational | about 14 km, Madavara | |
| Metro, under construction | about 24 km, Yelahanka |
| Kempegowda Airport | 49 | 35.5 |
| MG Road (CBD) | 38 | 30.5 |
| Manyata Tech Park | 36.5 | 28 |
| ITPL, Whitefield | 52.5 | 42.5 |
| Ecospace, Bellandur ORR | 51.5 | 40.5 |
| Electronic City Ph 1 | 63.5 | 47 |
| Quarry | about 2.5 km to the south-east |
|---|
| Crematorium | None within 3 km |
|---|
| Prison | None within 3 km |
|---|
| Electrical substation | None within 3 km |
|---|