Not verified yet: Recent price, super built-up; Gross yield; North Bengaluru, past year; Price paid per sq ft, super built-up.
•• ••• ••••
Title Title report •• %
•• ••• ••••
•••••
₹ •.•• Cr
Charges •• ••• ••••
•••••
₹ •.•• Cr
•• of ••
Boundaries Schedule in the EC vs KGIS neighbours Encumbrance certificate, Form 15 Survey sketch Sketch, sanction and mutation vs KGIS map Land record Filing vs KGIS map •• ••• ••••
•••••
₹ •.•• Cr
•• of ••
The RTC of each filed survey •••••
₹ •.•• Cr
•• of ••
₹ ••,•••
Ownership Joint development agreement Unlock this full report ₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Sign in to unlock for ₹99 Adjust maadbeda.One minute, read what Hrs Sai Guru Bliss Avenue's developer filed before you say yes.
× Hrs Sai Guru Bliss Avenue
HRS Sai Guru Developers LLP · Vidyaranyapura, North Bengaluru
₹99 for this report
✓ Contract terms read from the filed agreement ✓ Title and land records read from the filings ✓ Every figure cited to its page ✓ Pay once. It stays yours to read Sign in first, then pay ₹99 once for this report. No subscription.
No spam calls. We never ask for your phone number.
Built from 100+ public records and registers, K-RERA filings first · No broker, no listing fees
2028 Pollution board valid until 16 Feb 2028 Pollution board: valid until 16 Feb 2028 As of 19 Nov 2026 2024 2025 2026 2027 2028 Pollution board valid until 16 Feb 2028 Pollution board: valid until 16 Feb 2028 As of 19 Nov 2026
2024 2025 2026 2027 2028 Pollution board valid until 16 Feb 2028 Pollution board: valid until 16 Feb 2028 As of 19 Nov 2026
2024 2025 2026 2027 2028 Pollution board valid until 16 Feb 2028 Pollution board: valid until 16 Feb 2028 As of 19 Nov 2026
Valid as of this report Validity ended
RERA Registration certificates Registration certificate PRM/KA/RERA/1251/472/PR/281024/007185
•••••
Unlock this full report ₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Sign in to unlock for ₹99 Adjust maadbeda.One minute, read what Hrs Sai Guru Bliss Avenue's developer filed before you say yes.
× Hrs Sai Guru Bliss Avenue
HRS Sai Guru Developers LLP · Vidyaranyapura, North Bengaluru
₹99 for this report
✓ Contract terms read from the filed agreement ✓ Title and land records read from the filings ✓ Every figure cited to its page ✓ Pay once. It stays yours to read Sign in first, then pay ₹99 once for this report. No subscription.
No spam calls. We never ask for your phone number.
Built from 100+ public records and registers, K-RERA filings first · No broker, no listing fees
•• %
Payments Agreement for sale
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Fees Agreement for sale
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
•• ••• ••••
Unlock this full report ₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Sign in to unlock for ₹99 Adjust maadbeda.One minute, read what Hrs Sai Guru Bliss Avenue's developer filed before you say yes.
× Hrs Sai Guru Bliss Avenue
HRS Sai Guru Developers LLP · Vidyaranyapura, North Bengaluru
₹99 for this report
✓ Contract terms read from the filed agreement ✓ Title and land records read from the filings ✓ Every figure cited to its page ✓ Pay once. It stays yours to read Sign in first, then pay ₹99 once for this report. No subscription.
No spam calls. We never ask for your phone number.
Built from 100+ public records and registers, K-RERA filings first · No broker, no listing fees
3BHK · avg 115 m² 77.8%
2BHK 22.2%
The area Comparable projects Nearest 12 with filed prices Nearest projects This project vs the nearest with filed prices Rent & yield Median rent, 3 km 1BHK · 15 listings 1BHK: median ₹7,500 /mo over 15 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹7,500 /mo 2BHK · 28 listings 2BHK: median ₹25,000 /mo over 28 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹25,000 /mo 3BHK · 14 listings 3BHK: median ₹36,500 /mo over 14 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹36,500 /mo
1BHK · 15 listings 1BHK: median ₹7,500 /mo over 15 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹7,500 /mo 2BHK · 28 listings 2BHK: median ₹25,000 /mo over 28 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹25,000 /mo 3BHK · 14 listings
Unsold stock nearby Months to sell unsold stock Within 4 km, pooled 1,401 unsold flats ÷ 51 booked a month across 19 projects 28 months Sri Rama Enclave Sri Rama Enclave, about 0.5 km: 25 unsold ÷ 8 booked in 9 months 28 months Sumuk Square-2 Sumuk Square-2, about 2 km: 28 unsold ÷ 26 booked in 9 months 10 months Rubby Castle 1 Rubby Castle 1, about 2 km: 24 unsold ÷ 5 booked in 9 months 43 months Durga Samrudhi Durga Samrudhi, about 2 km: 62 unsold ÷ 18 booked in 9 months 31 months Dhara Nakshthra Dhara Nakshthra, 2.5 km: 71 unsold ÷ 6 booked in 9 months 107 months Casagrand Promenade
Not verified yet: Recent price, super built-up; Recent price, carpet; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Transactions in this project; North Bengaluru, past year; Bengaluru, past year; North Bengaluru since 2022; This project vs North Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Bengaluru median yield.
Metro, operational 5.2 km Goraguntepalya
Around it Water Groundwater, Yelahanka taluk average 0 m 10 m 20 m 30 m 40+ m 10 to 20 20 to 40 Ten-year July mean for Yelahanka: 32.6 m Yelahanka taluk average, July 2023 11.4 m below ground 0 m 10 m 20 m 30 m 40+ m 5 to 10 10 to 20
Not verified yet: Nearest high-tension line, Kitchen handover, Sewage plant.
0% 50% 100% Q3 2025-26: 75% 75% Q3 2025-26 Q4 2025-26: 85% 85% Q4 2025-26 Q1 2026-27: 100% 100% Q1 2026-27 Promised 14 Feb 2027: 100% (needed) Promised 14 Feb 2027 0% 50% 100% Q3 2025-26: 75% 75% Q3 2025-26 Q4 2025-26: 85% 85% Q4 2025-26 Q1 2026-27: 100% 100% Q1 2026-27 Promised 14 Feb 2027: 100% (needed) Promised 14 Feb 2027 0% 50% 100% Q3 2025-26: 75% 75% Q3 2025-26 Q4 2025-26: 85% 85% Q4 2025-26 Q1 2026-27: 100% 100% Q1 2026-27 Promised 14 Feb 2027: 100% (needed) Promised 14 Feb 2027 0% 50% 100% Q3 2025-26: 75% 75% Q3 2025-26 Q4 2025-26: 85% 85% Q4 2025-26 Q1 2026-27: 100% 100% Q1 2026-27 Promised 14 Feb 2027: 100% (needed) Promised 14 Feb 2027 As the promoter reported it Possession date in the agreement
Work left By component, Q1 2026-27 Tower A Tower A: 100% 100% Earth work and other leveling preparation work Earth work and other leveling preparation work: 100% 100% Upto Plinth Level Upto Plinth Level: 100% 100% Main structure Main structure: 100% 100% Plastering inside, outside & Ceiling Plastering inside, outside & Ceiling: 100% 100% Basic work of Water supply, Sanitary and Electrification Basic work of Water supply, Sanitary and Electrification: 100% 100% Railing and Grill fixing Railing and Grill fixing: 100% 100% Electrification, Water supply and Sanitary Finishing Electrification, Water supply and Sanitary Finishing: 100% 100% Fire prevention and fire fighting fitting and fixture with network Fire prevention and fire fighting fitting and fixture with network: 100% 100% Elevation work Elevation work: 100% 100% Electricity Electricity: 100% 100% Community Hall Community Hall: 100% 100% Power Backup Power Backup: 100% 100% Water Supply, external Water Supply, external: 100% 100% Electricity supply transformer and substation Electricity supply transformer and substation: 100% 100% Emergency Evacuation services, external Emergency Evacuation services, external: 100% 100% Water conservation/rain water harvesting/recharg e of ground water, external Water conservation/rain water harvesting/recharge of ground water, external: 100% 100% Sewage Treatment Plant (STP) Sewage Treatment Plant (STP): 100% 100% Water Supply, internal Water Supply, internal: 100% 100% Water conservation/rain water harvesting/recharg e of ground water, internal Water conservation/rain water harvesting/recharge of ground water, internal: 100% 100% Fire protection and fire safety requirements Fire protection and fire safety requirements: 100% 100% Emergency Evacuation services, internal Emergency Evacuation services, internal: 100% 100% Staircases Staircases: 100% 100% Fire escapes Fire escapes: 100% 100% Terrace Terrace: 100% 100% Water conservation and renewable energy Water conservation and renewable energy: 100% 100%
Tower A Tower A: 100% 100% Earth work and other leveling preparation work Earth work and other leveling preparation work: 100% 100% Upto Plinth Level Upto Plinth Level: 100% 100% Main structure Main structure: 100% 100% Plastering inside, outside & Ceiling Plastering inside, outside & Ceiling: 100% 100% Basic work of Water supply, Sanitary and Electrification Basic work of Water supply, Sanitary and Electrification: 100% 100% Railing and Grill fixing Railing and Grill fixing: 100% 100% Electrification, Water supply and Sanitary Finishing
Tower A Tower A: 100% 100% Earth work and other leveling preparation work Earth work and other leveling preparation work: 100% 100% Upto Plinth Level Upto Plinth Level: 100% 100% Main structure Main structure: 100% 100% Plastering inside, outside & Ceiling Plastering inside, outside & Ceiling: 100% 100% Basic work of Water supply, Sanitary and Electrification Basic work of Water supply, Sanitary and Electrification: 100% 100% Railing and Grill fixing Railing and Grill fixing: 100% 100% Electrification, Water supply and Sanitary Finishing
Tower A Tower A: 100% 100% Earth work and other leveling preparation work Earth work and other leveling preparation work: 100% 100% Upto Plinth Level Upto Plinth Level: 100% 100% Main structure Main structure: 100% 100% Plastering inside, outside & Ceiling Plastering inside, outside & Ceiling: 100% 100% Basic work of Water supply, Sanitary and Electrification Basic work of Water supply, Sanitary and Electrification: 100% 100% Railing and Grill fixing Railing and Grill fixing: 100% 100% Electrification, Water supply and Sanitary Finishing
Quarterly return, Q1 2026-27 Dates Dates 2025 2026 2027 Work began 14 Aug 2024 As of 19 Nov 2026 Keys promised 14 Feb 2027 RERA deadline 14 Feb 2027 Builder's schedule ends 14 Feb 2027 Work began: 14 Aug 2024 As of 19 Nov 2026 Keys promised: 14 Feb 2027 RERA deadline: 14 Feb 2027 Builder's schedule ends: 14 Feb 2027
2025 2026 2027 Work began 14 Aug 2024 As of 19 Nov 2026 Keys promised 14 Feb 2027 RERA deadline 14 Feb 2027 Builder's schedule ends 14 Feb 2027 Work began: 14 Aug 2024 As of 19 Nov 2026 Keys promised: 14 Feb 2027 RERA deadline: 14 Feb 2027 Builder's schedule ends: 14 Feb 2027
2025 2026 2027 Work began 14 Aug 2024 As of 19 Nov 2026 Keys promised 14 Feb 2027 RERA deadline 14 Feb 2027 Builder's schedule ends 14 Feb 2027 Work began: 14 Aug 2024 As of 19 Nov 2026 Keys promised: 14 Feb 2027 RERA deadline: 14 Feb 2027 Builder's schedule ends: 14 Feb 2027
2025 2026 2027 Work began 14 Aug 2024 As of 19 Nov 2026 Keys promised 14 Feb 2027 RERA deadline 14 Feb 2027 Builder's schedule ends 14 Feb 2027 Work began: 14 Aug 2024 As of 19 Nov 2026 Keys promised: 14 Feb 2027 RERA deadline: 14 Feb 2027 Builder's schedule ends: 14 Feb 2027
Specified structure What the promoter specified · not an inspection Specified finishes Specification sheet · brands "or equivalent" Certificates Engineer, architect and fire certificates Not verified yet: Structure; Structural safety certificate; Internal roads; Club house; Foundation; Wall material; Wall thickness; Concrete / steel grade; Windows; Flooring; Toilet tiles, spec vs brochure; Wiring; Sanctioned load per flat; Sewage plant; Design consultants (Form 6); Environmental clearance.
Land · ₹7.74 Cr: 28.7% Development · ₹19.24 Cr: 71.3% ₹26.98 Cr estimated cost Land · ₹7.74 Cr 28.7% Development · ₹19.24 Cr 71.3%
Sales Sold vs unsold, Q1 2026-27 Sold (13): 28.9% Unsold (32): 71.1% 29% 45 flats Sold (13) 28.9% Unsold (32) 71.1%
Sold per quarter Q4 2025-26 Q4 2025-26: booked flats went from 6 to 7 1 flat Q1 2026-27 Q1 2026-27: booked flats went from 7 to 13 6 flats
Q4 2025-26 Q4 2025-26: booked flats went from 6 to 7 1 flat Q1 2026-27 Q1 2026-27: booked flats went from 7 to 13 6 flats
Q4 2025-26 Q4 2025-26: booked flats went from 6 to 7 1 flat Q1 2026-27 Q1 2026-27: booked flats went from 7 to 13 6 flats
Q4 2025-26 Q4 2025-26: booked flats went from 6 to 7 1 flat Q1 2026-27 Q1 2026-27: booked flats went from 7 to 13 6 flats
Compliance Escrow, Q1 2026-27 Paid in Paid into the designated account in Q1 2026-27 ₹3.18 Cr Withdrawn Withdrawn by the promoter in Q1 2026-27 ₹2.22 Cr
Paid in Paid into the designated account in Q1 2026-27 ₹3.18 Cr Withdrawn Withdrawn by the promoter in Q1 2026-27 ₹2.22 Cr
Paid in Paid into the designated account in Q1 2026-27 ₹3.18 Cr Withdrawn Withdrawn by the promoter in Q1 2026-27 ₹2.22 Cr
Paid in Paid into the designated account in Q1 2026-27 ₹3.18 Cr Withdrawn Withdrawn by the promoter in Q1 2026-27 ₹2.22 Cr
Not verified yet: Receivable, sold flats; Cost left vs buyer dues; Collected from buyers; Land cost revision; Unregistered agreements, over 10% paid; Average schedule slip; DOSL builder track.
Q3 2025-26 Q3 2025-26: 75% built, as the promoter reported it 75% Q4 2025-26 Q4 2025-26: 85% built, as the promoter reported it 85% Q1 2026-27 Q1 2026-27: 100% built, as the promoter reported it 100%
Q3 2025-26 Q3 2025-26: 75% built, as the promoter reported it 75% Q4 2025-26 Q4 2025-26: 85% built, as the promoter reported it 85% Q1 2026-27 Q1 2026-27: 100% built, as the promoter reported it 100%
Q3 2025-26 Q3 2025-26: 75% built, as the promoter reported it 75% Q4 2025-26 Q4 2025-26: 85% built, as the promoter reported it 85% Q1 2026-27 Q1 2026-27: 100% built, as the promoter reported it 100%
Q3 2025-26 Q3 2025-26: 75% built, as the promoter reported it 75% Q4 2025-26 Q4 2025-26: 85% built, as the promoter reported it 85% Q1 2026-27 Q1 2026-27: 100% built, as the promoter reported it 100%
Not verified yet: Value; Max loan; Borrower margin; Example unit; Calculation; Records searched to; Unregistered agreements, over 10% paid; Sale deed in favour of.
Veerannapalya Veerannapalya drain near Manpho convention center Near Shani mahathma temple beside Hebbal Flyover Kariyannapalya outer ring road, near Varun motors Kariyannapalya Bridge over flowed ORR Upstreams of Devinagar (junction of Ring road and railway track) of Hebbal From Esteem mall beside Dhobi Ghat to Yogesh nagar bridge TATA nagar 8th cross Near Rachanahalli lake inlet Aaimatha layout, Mallasandra Kammagondanahalli near MNTI Polytechnic Shettihalli & Chikkasandra Village Thindlu to Doddabommasandra tank LBSnagar Yelahanka Bhadrappa layout Gurudarshan Layout, Near Doddabommasandra Devi Nagara JRD Tata Nagar Bhadrappa Layout, Nagashettihalli Someshwara Nagar EWS working colony 3rd stage 1 km 3 km 2 km Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
Storm drain, primary Lake or tank Metro lines (dashed: planned) Metro station High-tension line, 765, 400, 220 and 66 kV Its corridor, to scale Buried cable Government-flagged flood location The site3BHK: median ₹36,500 /mo over 14 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹36,500 /mo 1BHK · 15 listings 1BHK: median ₹7,500 /mo over 15 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹7,500 /mo 2BHK · 28 listings 2BHK: median ₹25,000 /mo over 28 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹25,000 /mo 3BHK · 14 listings 3BHK: median ₹36,500 /mo over 14 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹36,500 /mo
1BHK · 15 listings 1BHK: median ₹7,500 /mo over 15 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹7,500 /mo 2BHK · 28 listings 2BHK: median ₹25,000 /mo over 28 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹25,000 /mo 3BHK · 14 listings 3BHK: median ₹36,500 /mo over 14 listings. Rental listings within 3 km, seen 3 Apr 2026 to 2 Oct 2026: asking rents of whole flats, medians by bedroom count ₹36,500 /mo
Casagrand Promenade, 2.6 km: 76 unsold ÷ 40 booked in 9 months 17 months Within 4 km, pooled 1,401 unsold flats ÷ 51 booked a month across 19 projects 28 months Sri Rama Enclave Sri Rama Enclave, about 0.5 km: 25 unsold ÷ 8 booked in 9 months 28 months Sumuk Square-2 Sumuk Square-2, about 2 km: 28 unsold ÷ 26 booked in 9 months 10 months Rubby Castle 1 Rubby Castle 1, about 2 km: 24 unsold ÷ 5 booked in 9 months 43 months Durga Samrudhi Durga Samrudhi, about 2 km: 62 unsold ÷ 18 booked in 9 months 31 months Dhara Nakshthra Dhara Nakshthra, 2.5 km: 71 unsold ÷ 6 booked in 9 months 107 months Casagrand Promenade Casagrand Promenade, 2.6 km: 76 unsold ÷ 40 booked in 9 months 17 months
Within 4 km, pooled 1,401 unsold flats ÷ 51 booked a month across 19 projects 28 months Sri Rama Enclave Sri Rama Enclave, about 0.5 km: 25 unsold ÷ 8 booked in 9 months 28 months Sumuk Square-2 Sumuk Square-2, about 2 km: 28 unsold ÷ 26 booked in 9 months 10 months Rubby Castle 1 Rubby Castle 1, about 2 km: 24 unsold ÷ 5 booked in 9 months 43 months Durga Samrudhi Durga Samrudhi, about 2 km: 62 unsold ÷ 18 booked in 9 months 31 months Dhara Nakshthra Dhara Nakshthra, 2.5 km: 71 unsold ÷ 6 booked in 9 months 107 months Casagrand Promenade Casagrand Promenade, 2.6 km: 76 unsold ÷ 40 booked in 9 months 17 months
Within 4 km, pooled 1,401 unsold flats ÷ 51 booked a month across 19 projects 28 months Sri Rama Enclave Sri Rama Enclave, about 0.5 km: 25 unsold ÷ 8 booked in 9 months 28 months Sumuk Square-2 Sumuk Square-2, about 2 km: 28 unsold ÷ 26 booked in 9 months 10 months Rubby Castle 1 Rubby Castle 1, about 2 km: 24 unsold ÷ 5 booked in 9 months 43 months Durga Samrudhi Durga Samrudhi, about 2 km: 62 unsold ÷ 18 booked in 9 months 31 months Dhara Nakshthra Dhara Nakshthra, 2.5 km: 71 unsold ÷ 6 booked in 9 months 107 months Casagrand Promenade Casagrand Promenade, 2.6 km: 76 unsold ÷ 40 booked in 9 months 17 months
Thindlu to Doddabommasandra tank Gurudarshan Layout, Near Doddabommasandra 500 m Thindlu to Doddabommasandra tank Gurudarshan Layout, Near Doddabommasandra 500 m Basemap: Esri, OpenStreetMap contributors
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Lake or tank Storm drain, smaller Government-flagged flood location The site20 to 40 Ten-year July mean for Yelahanka: 32.6 m Yelahanka taluk average, July 2023 11.4 m below ground 0 m 10 m 20 m 30 m 40+ m 2 to 5 5 to 10 10 to 20 20 to 40 Ten-year July mean for Yelahanka: 32.6 m Yelahanka taluk average, July 2023 11.4 m below ground 0 m 10 m 20 m 30 m 40+ m 2 to 5 5 to 10 10 to 20 20 to 40 Ten-year July mean for Yelahanka: 32.6 m Yelahanka taluk average, July 2023 11.4 m below ground Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
Connectivity Road distance from the site Kempegowda Airport Kempegowda Airport: 27.3 km by road 27.3 km MG Road (CBD) MG Road (CBD): 14.1 km by road 14.1 km Manyata Tech Park Manyata Tech Park: 9.4 km by road 9.4 km ITPL, Whitefield ITPL, Whitefield: 26.4 km by road 26.4 km Ecospace, Bellandur ORR Ecospace, Bellandur ORR: 29.5 km by road 29.5 km Electronic City Ph 1 Electronic City Ph 1: 33.8 km by road 33.8 km
Kempegowda Airport Kempegowda Airport: 27.3 km by road 27.3 km MG Road (CBD) MG Road (CBD): 14.1 km by road 14.1 km Manyata Tech Park Manyata Tech Park: 9.4 km by road 9.4 km ITPL, Whitefield ITPL, Whitefield: 26.4 km by road 26.4 km Ecospace, Bellandur ORR Ecospace, Bellandur ORR: 29.5 km by road 29.5 km Electronic City Ph 1 Electronic City Ph 1: 33.8 km by road 33.8 km
Kempegowda Airport Kempegowda Airport: 27.3 km by road 27.3 km MG Road (CBD) MG Road (CBD): 14.1 km by road 14.1 km Manyata Tech Park Manyata Tech Park: 9.4 km by road 9.4 km ITPL, Whitefield ITPL, Whitefield: 26.4 km by road 26.4 km Ecospace, Bellandur ORR Ecospace, Bellandur ORR: 29.5 km by road 29.5 km Electronic City Ph 1 Electronic City Ph 1: 33.8 km by road 33.8 km
Kempegowda Airport Kempegowda Airport: 27.3 km by road 27.3 km MG Road (CBD) MG Road (CBD): 14.1 km by road 14.1 km Manyata Tech Park Manyata Tech Park: 9.4 km by road 9.4 km ITPL, Whitefield ITPL, Whitefield: 26.4 km by road 26.4 km Ecospace, Bellandur ORR Ecospace, Bellandur ORR: 29.5 km by road 29.5 km Electronic City Ph 1 Electronic City Ph 1: 33.8 km by road 33.8 km
Six city anchors · OSRM, no traffic Nuisances Distance from the site Sewage treatment plant Sewage treatment plant: 590 m, Doddabomasandra STP 590 m Electrical substation Electrical substation: 1.7 km, BEL 1.7 km
Sewage treatment plant Sewage treatment plant: 590 m, Doddabomasandra STP 590 m Electrical substation Electrical substation: 1.7 km, BEL 1.7 km
Sewage treatment plant Sewage treatment plant: 590 m, Doddabomasandra STP 590 m Electrical substation Electrical substation: 1.7 km, BEL 1.7 km
Sewage treatment plant Sewage treatment plant: 590 m, Doddabomasandra STP 590 m Electrical substation Electrical substation: 1.7 km, BEL 1.7 km
Electrification, Water supply and Sanitary Finishing: 100% 100% Fire prevention and fire fighting fitting and fixture with network Fire prevention and fire fighting fitting and fixture with network: 100% 100% Elevation work Elevation work: 100% 100% Electricity Electricity: 100% 100% Community Hall Community Hall: 100% 100% Power Backup Power Backup: 100% 100% Water Supply, external Water Supply, external: 100% 100% Electricity supply transformer and substation Electricity supply transformer and substation: 100% 100% Emergency Evacuation services, external Emergency Evacuation services, external: 100% 100% Water conservation/rain water harvesting/recharge of ground water, external Water conservation/rain water harvesting/recharge of ground water, external: 100% 100% Sewage Treatment Plant (STP) Sewage Treatment Plant (STP): 100% 100% Water Supply, internal Water Supply, internal: 100% 100% Water conservation/rain water harvesting/recharge of ground water, internal Water conservation/rain water harvesting/recharge of ground water, internal: 100% 100% Fire protection and fire safety requirements Fire protection and fire safety requirements: 100% 100% Emergency Evacuation services, internal Emergency Evacuation services, internal: 100% 100% Staircases Staircases: 100% 100% Fire escapes Fire escapes: 100% 100% Terrace Terrace: 100% 100% Water conservation and renewable energy Water conservation and renewable energy: 100% 100% Electrification, Water supply and Sanitary Finishing: 100% 100% Fire prevention and fire fighting fitting and fixture with network Fire prevention and fire fighting fitting and fixture with network: 100% 100% Elevation work Elevation work: 100% 100% Electricity Electricity: 100% 100% Community Hall Community Hall: 100% 100% Power Backup Power Backup: 100% 100% Water Supply, external Water Supply, external: 100% 100% Electricity supply transformer and substation Electricity supply transformer and substation: 100% 100% Emergency Evacuation services, external Emergency Evacuation services, external: 100% 100% Water conservation/rain water harvesting/recharge of ground water, external Water conservation/rain water harvesting/recharge of ground water, external: 100% 100% Sewage Treatment Plant (STP) Sewage Treatment Plant (STP): 100% 100% Water Supply, internal Water Supply, internal: 100% 100% Water conservation/rain water harvesting/recharge of ground water, internal Water conservation/rain water harvesting/recharge of ground water, internal: 100% 100% Fire protection and fire safety requirements Fire protection and fire safety requirements: 100% 100% Emergency Evacuation services, internal Emergency Evacuation services, internal: 100% 100% Staircases Staircases: 100% 100% Fire escapes Fire escapes: 100% 100% Terrace Terrace: 100% 100% Water conservation and renewable energy Water conservation and renewable energy: 100% 100% Electrification, Water supply and Sanitary Finishing: 100% 100% Fire prevention and fire fighting fitting and fixture with network Fire prevention and fire fighting fitting and fixture with network: 100% 100% Elevation work Elevation work: 100% 100% Electricity Electricity: 100% 100% Community Hall Community Hall: 100% 100% Power Backup Power Backup: 100% 100% Water Supply, external Water Supply, external: 100% 100% Electricity supply transformer and substation Electricity supply transformer and substation: 100% 100% Emergency Evacuation services, external Emergency Evacuation services, external: 100% 100% Water conservation/rain water harvesting/recharge of ground water, external Water conservation/rain water harvesting/recharge of ground water, external: 100% 100% Sewage Treatment Plant (STP) Sewage Treatment Plant (STP): 100% 100% Water Supply, internal Water Supply, internal: 100% 100% Water conservation/rain water harvesting/recharge of ground water, internal Water conservation/rain water harvesting/recharge of ground water, internal: 100% 100% Fire protection and fire safety requirements Fire protection and fire safety requirements: 100% 100% Emergency Evacuation services, internal Emergency Evacuation services, internal: 100% 100% Staircases Staircases: 100% 100% Fire escapes Fire escapes: 100% 100% Terrace Terrace: 100% 100% Water conservation and renewable energy Water conservation and renewable energy: 100% 100% Balaji Layout, Near Tata Nagar Kempapura Mariyanna Palya KEMPEGOWDANAGAR Veerannapalya Veerannapalya drain near Manpho convention center Near Shani mahathma temple beside Hebbal Flyover Kariyannapalya outer ring road, near Varun motors Kariyannapalya Bridge over flowed ORR Upstreams of Devinagar (junction of Ring road and railway track) of Hebbal From Esteem mall beside Dhobi Ghat to Yogesh nagar bridge TATA nagar 8th cross Near Rachanahalli lake inlet Aaimatha layout, Mallasandra Kammagondanahalli near MNTI Polytechnic Shettihalli & Chikkasandra Village Thindlu to Doddabommasandra tank LBSnagar Yelahanka Bhadrappa layout Gurudarshan Layout, Near Doddabommasandra Devi Nagara JRD Tata Nagar Bhadrappa Layout, Nagashettihalli Someshwara Nagar EWS working colony 3rd stage Balaji Layout, Near Tata Nagar Kempapura Mariyanna Palya KEMPEGOWDANAGAR 1 km 3 km 2 km