Overview
I.T. Twin Towers
Janta Land Promoters Pvt. Ltd. · Sahibzada Ajit Singh Nagar (Mohali)
Units164
Completion2019-10-31Proposed
Valid to2019-10-31
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 4 site details · 1 unit type |
| Construction & progress | 2 progress details · 25 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 12 documents · 30 source links |
Registration
Registration
| Promoter | Janta Land Promoters Pvt. Ltd. | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PI0003 | |
| Valid to | 2019-10-31 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2019-10-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Date |
|---|---|
| Defense Clearance | 2017-06-21 |
| Pollution Clearance from Punjab Pollution Control Board | 2018-05-14 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 11,047.92 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 12 | |
| Units | 164 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| Commercial | 0.001 | 164 | IT TWIN TOWER PLOT NO 5101 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2012-04-23 | |
|---|---|---|
| Proposed completion | 2019-10-31 |
Quarterly progress
| 2018-Q1 | 2021-12-21 |
| 2018-Q2 | 2021-12-21 |
| 2018-Q3 | 2021-12-21 |
| 2018-Q4 | 2021-12-21 |
| 2019-Q1 | 2021-12-21 |
| 2019-Q2 | 2021-12-21 |
| 2019-Q4 | 2021-12-21 |
| 2020-Q1 | 2021-12-22 |
| 2020-Q2 | 2021-12-22 |
| 2020-Q3 | 2021-12-22 |
| 2020-Q4 | 2021-12-22 |
| 2021-Q1 | 2021-12-22 |
| 2021-Q2 | 2021-12-22 |
| 2021-Q3 | 2021-12-22 |
| 2021-Q4 | 2022-02-23 |
| 2022-Q1 | 2022-04-18 |
| 2022-Q2 | 2022-07-19 |
| 2022-Q3 | 2022-11-29 |
| 2022-Q4 | 2023-04-26 |
| 2023-Q1 | 2023-04-26 |
| 2023-Q2 | 2023-07-12 |
| 2023-Q3 | 2023-10-09 |
| 2023-Q4 | 2024-01-17 |
| 2024-Q1 | 2024-04-08 |
| 2024-Q2 | 2024-07-16 |
Extensions
| Valid to |
|---|
| 2022-12-17 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Janta Land Promoters Pvt. Ltd. | |
|---|---|---|
| Type | Company | |
| Escrow bank | Oriental Bank of Commerce | |
| Other projects in this city pack | 20 |
Professional firms
| Role | Firm |
|---|---|
| Architect | DHAM CONSULTANTS |
| Engineer | SYAL ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10210&inPromoter_ID=1073&inPromoterType=2
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- Commencement Certificate (Mega Project Category) · Sign in to download
- Defense Clearance · 2017-06-21
- Pollution Clearance from Punjab Pollution Control Board · 2018-05-14
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- Defense Clearance · 2017-06-21
- Pollution Clearance from Punjab Pollution Control Board · 2018-05-14
- Extension order · Sign in to download
- 2018-Q1 · 2021-12-21
- 2018-Q2 · 2021-12-21
- 2018-Q3 · 2021-12-21
- 2018-Q4 · 2021-12-21
- 2019-Q1 · 2021-12-21
- 2019-Q2 · 2021-12-21
- 2019-Q4 · 2021-12-21
- 2020-Q1 · 2021-12-22
- 2020-Q2 · 2021-12-22
- 2020-Q3 · 2021-12-22
- 2020-Q4 · 2021-12-22
- 2021-Q1 · 2021-12-22
- 2021-Q2 · 2021-12-22
- 2021-Q3 · 2021-12-22
- 2021-Q4 · 2022-02-23
- 2022-Q1 · 2022-04-18
- 2022-Q2 · 2022-07-19
- 2022-Q3 · 2022-11-29
- 2022-Q4 · 2023-04-26
- 2023-Q1 · 2023-04-26
- 2023-Q2 · 2023-07-12
- 2023-Q3 · 2023-10-09
- 2023-Q4 · 2024-01-17
- 2024-Q1 · 2024-04-08
- 2024-Q2 · 2024-07-16