Overview
Imperial Apartments
HARMONY COLONISERS PRIVATE LIMITED · Sahibzada Ajit Singh Nagar (Mohali)
Units533
Completion2025-08-15Proposed
Valid to2026-08-15
Approvals8
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 36 unit types |
| Construction & progress | 2 progress details · 26 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 25 documents · 37 source links |
Registration
Registration
| Promoter | HARMONY COLONISERS PRIVATE LIMITED | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR0605 | |
| Valid to | 2026-08-15 | |
| Project type | (1) Commercial (Building/Tower Development) (2) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2025-08-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2018-06-17 | |
| CLU Certificate | ||
| Environment Clearance certificate/ NOC | Clearances (Received) | 2018-09-07 |
| License as Promoter from competent Authority | Permissions (Received) | 2019-08-07 |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2018-06-14 | |
| Other Document (Garbage NOC) | 2018-04-17 | |
| Other Document (Payment done after CLU) | Legal Documents (Received) | 2019-05-23 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹83,17,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 28,457.35 | |
|---|---|---|
| Towers | 36 | |
| Maximum floors | 14 | |
| Units | 533 |
Unit types
| 3BHK | 95.225 | 52 | BLOCK A1 |
| 3BHK | 95.225 | 56 | BLOCK A2 |
| 3BHK | 95.225 | 56 | BLOCK A3 |
| 3BHK | 95.225 | 56 | BLOCK A4 |
| 3BHK | 95.225 | 56 | BLOCK A5 |
| 3BHK | 84.876 | 8 | BLOCK B1 |
| 3BHK | 84.876 | 8 | BLOCK B10 |
| 3BHK | 84.876 | 8 | BLOCK B11 |
| 3BHK | 84.876 | 8 | BLOCK B12 |
| 3BHK | 84.876 | 8 | BLOCK B13 |
| 3BHK | 84.876 | 8 | BLOCK B14 |
| 3BHK | 84.876 | 8 | BLOCK B15 |
| 3BHK | 84.876 | 8 | BLOCK B16 |
| 3BHK | 84.876 | 8 | BLOCK B17 |
| 3BHK | 84.876 | 8 | BLOCK B18 |
| 3BHK | 84.876 | 8 | BLOCK B19 |
| 3BHK | 84.876 | 8 | BLOCK B2 |
| 3BHK | 84.876 | 8 | BLOCK B20 |
| 3BHK | 84.876 | 8 | BLOCK B21 |
| 3BHK | 84.876 | 8 | BLOCK B22 |
| 3BHK | 84.876 | 8 | BLOCK B23 |
| 3BHK | 84.876 | 8 | BLOCK B24 |
| 3BHK | 84.876 | 8 | BLOCK B25 |
| 3BHK | 84.876 | 8 | BLOCK B26 |
| 3BHK | 84.876 | 8 | BLOCK B27 |
| 3BHK | 84.876 | 8 | BLOCK B28 |
| 3BHK | 84.876 | 8 | BLOCK B29 |
| 3BHK | 84.876 | 8 | BLOCK B3 |
| 3BHK | 84.876 | 8 | BLOCK B30 |
| 3BHK | 84.876 | 8 | BLOCK B4 |
| 3BHK | 84.876 | 8 | BLOCK B5 |
| 3BHK | 84.876 | 8 | BLOCK B6 |
| 3BHK | 84.876 | 8 | BLOCK B7 |
| 3BHK | 84.876 | 8 | BLOCK B8 |
| 3BHK | 84.876 | 8 | BLOCK B9 |
| SHOP | 29.43 | 17 | BLOCK C |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-06-06 | |
|---|---|---|
| Proposed completion | 2025-08-15 |
Quarterly progress
| 2020-Q2 | 2023-06-01 |
| 2020-Q3 | 2023-06-01 |
| 2020-Q4 | 2023-06-01 |
| 2021-Q1 | 2023-06-01 |
| 2021-Q2 | 2023-06-01 |
| 2021-Q3 | 2023-06-01 |
| 2021-Q4 | 2023-06-01 |
| 2022-Q1 | 2023-06-05 |
| 2022-Q2 | 2023-06-05 |
| 2022-Q3 | 2023-06-05 |
| 2022-Q4 | 2023-06-05 |
| 2023-Q1 | 2023-06-05 |
| 2023-Q2 | 2024-04-02 |
| 2023-Q3 | 2024-04-02 |
| 2023-Q4 | 2024-04-02 |
| 2024-Q1 | 2024-05-31 |
| 2024-Q2 | 2024-10-10 |
| 2024-Q3 | 2024-10-10 |
| 2024-Q4 | 2025-01-14 |
| 2025-Q1 | 2025-04-07 |
| 2025-Q2 | 2025-07-14 |
| 2025-Q3 | 2026-04-07 |
| 2025-Q4 | 2026-04-07 |
| 2026-Q1 | 2026-04-07 |
| 2026-Q2 | 2026-07-07 |
| 2026-Q3 | 2026-10-12 |
Extensions
| Valid to |
|---|
| 2026-08-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | HARMONY COLONISERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Bank of Baroda | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10920&inPromoter_ID=1773&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2018-06-17
- Building Permit Issue from Municipal Authority · 2019-06-06 · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Environment Clearance certificate/ NOC · 2018-09-07
- License as Promoter from competent Authority · 2019-08-07
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-06-14
- Other Document (FEE DETAIL) · 2019-08-04 · Sign in to download
- Other Document (Garbage NOC) · 2018-04-17
- Other Document (Letter of Intent) · 2020-01-20 · Sign in to download
- Other Document (Payment done after CLU) · 2019-05-23
- Other Document (Promoter experience undertaking) · 2019-08-11 · Sign in to download
- Other Document (Sewarage certificate) · 2018-04-17 · Sign in to download
- Other Document (structure design vetting report) · 2019-04-30 · Sign in to download
- Other Document (Structure Stability certificate) · 2019-07-31 · Sign in to download
- Other Document (undertaking) · 2020-01-21 · Sign in to download
- Project Land Khasra Report or Plan
- Extension of Registration Certificate · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2018-06-17
- CLU Certificate
- Environment Clearance certificate/ NOC · 2018-09-07
- License as Promoter from competent Authority · 2019-08-07
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-06-14
- Other Document (Garbage NOC) · 2018-04-17
- Other Document (Payment done after CLU) · 2019-05-23
- Extension order · Sign in to download
- 2020-Q2 · 2023-06-01
- 2020-Q3 · 2023-06-01
- 2020-Q4 · 2023-06-01
- 2021-Q1 · 2023-06-01
- 2021-Q2 · 2023-06-01
- 2021-Q3 · 2023-06-01
- 2021-Q4 · 2023-06-01
- 2022-Q1 · 2023-06-05
- 2022-Q2 · 2023-06-05
- 2022-Q3 · 2023-06-05
- 2022-Q4 · 2023-06-05
- 2023-Q1 · 2023-06-05
- 2023-Q2 · 2024-04-02
- 2023-Q3 · 2024-04-02
- 2023-Q4 · 2024-04-02
- 2024-Q1 · 2024-05-31
- 2024-Q2 · 2024-10-10
- 2024-Q3 · 2024-10-10
- 2024-Q4 · 2025-01-14
- 2025-Q1 · 2025-04-07
- 2025-Q2 · 2025-07-14
- 2025-Q3 · 2026-04-07
- 2025-Q4 · 2026-04-07
- 2026-Q1 · 2026-04-07
- 2026-Q2 · 2026-07-07
- 2026-Q3 · 2026-10-12