Overview
INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92
DLF UTILITIES LIMITED · Gurugram
Units65
Completion2024-11-19Proposed
Registered on2021-08-17
Valid to2024-11-19
Approvals24
Sections
| Property title & search report | |
|---|---|
| Approvals | 24 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 12 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 14 documents · 2 source links |
Registration
Registration
| Promoter | DLF UTILITIES LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/475/207/2021/43 DATED 17.08.2021 | |
| Registered on | 2021-08-17 | |
| Valid to | 2024-11-19 | |
| Status (as filed) | Registered | |
| Proposed completion | 2024-11-19 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | Licence No. 59 of 2011 dt. 28.06.2011 for 101.218 acres, for which Part Completion Certificate has been granted on 02.07.2014. Licence No. 14 of 2012 dt. 27.02.2012 for 62.956 acres. Part Completion Certificate for an area of 60.14 acres has been granted on 18.03.2016. Licence No. 13 of 2019 dt. 06.02.2019 for 16.25 acres. | Town & Country Planning Department | |
| Layout Plan | |||
| Building Plan | |||
| I. LICENSE 59 OF 2011 APPROVAL | 2011-06-26 | ||
| II. LICENSE 14 OF 2012 APPROVAL | 2012-02-27 | ||
| III. LICENSE 13 OF 2019 APPROVAL | 2019-02-06 | ||
| IV. ENVIRONMENT CLEARANCE (SEIAA(126)/HR/2021/192) FOR PLOTTED DEVELOPMENT | 2021-02-18 | ||
| V. SERVICE PLAN ESTIMATES APPROVAL (MEMO NO. LC-2523-K/ASSTT.(AK) /2019/2574) | 2020-01-27 | ||
| VI. FOREST NOC (XRR-CAU-LW82) | 2019-10-18 | ||
| VII. NATURAL CONSERVATION ZONE NOC (22/AM0B0) | 2020-06-23 | ||
| VIII. TREE CUTTING PERMISSION/ NOC (XU5-RRE-V3XX) | 2021-03-10 | ||
| IX. BUILDING PLAN / SITE PLAN APPROVAL (FOR G19-12) | 2021-07-08 | ||
| X. BUILDING PLAN / SITE PLAN APPROVAL (FOR G19-14) | 2021-07-08 | ||
| XI. BUILDING PLAN / SITE PLAN APPROVAL (FOR G21-18) | 2021-07-08 | ||
| XII. BUILDING PLAN / SITE PLAN APPROVAL (FOR G21-19) | 2021-07-08 | ||
| XIII. BUILDING PLAN / SITE PLAN APPROVAL (FOR G21-16) | 2021-07-08 | ||
| XIV. BUILDING PLAN / SITE PLAN APPROVAL (FOR G16-21) | 2021-07-08 | ||
| XV. BUILDING PLAN / SITE PLAN APPROVAL (FOR G8-8) | 2021-07-08 | ||
| XVI. BUILDING PLAN / SITE PLAN APPROVAL (FOR SA-1G) | 2021-07-08 | ||
| XVII. BUILDING PLAN / SITE PLAN APPROVAL (FOR B12-5) | 2021-07-08 | ||
| XVIII. BUILDING PLAN / SITE PLAN APPROVAL (FOR G17-19) | 2021-07-08 | ||
| XIX. BUILDING PLAN / SITE PLAN APPROVAL (FOR NCA-12) | 2021-07-08 | ||
| XX. BUILDING PLAN / SITE PLAN APPROVAL (FOR NCA-14) | 2021-07-08 | ||
| XXI. BUILDING PLAN / SITE PLAN APPROVAL (FOR NCA-15) | 2021-07-08 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹13,26,63,000.00000001 | |
|---|---|---|
| Construction | ₹45,35,14,000.00000006 | |
| Total | ₹74,59,99,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 4,436.9 | |
|---|---|---|
| Units | 65 |
Unit types
| Plot | 1 | |
| Plot | 1 | |
| Plot | 8 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Apartment/Shops/Other Buildings | 154.281 | 4 |
| Apartment/Shops/Other Buildings | 164.398 | 4 |
| Apartment/Shops/Other Buildings | 167.687 | 32 |
| Apartment/Shops/Other Buildings | 175.854 | 4 |
| Apartment/Shops/Other Buildings | 130.137 | 4 |
| Apartment/Shops/Other Buildings | 206.407 | 4 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-12-20 | |
|---|---|---|
| Proposed completion | 2024-11-19 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | DLF UTILITIES LIMITED | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 5 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1664
- Registration Certificate · 2021-08-17
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2021-07-19 · Sign in to download
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2021-07-19
- ZONING PLAN · 2021-07-19
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2021-07-19
- DEMARCATION PLAN · 2021-07-20
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2021-07-20
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2021-07-26
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2021-07-27 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2021-07-27 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2021-07-27 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2021-07-27 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2021-07-27
- OC uploaded · 2024-08-08 · Sign in to download