Overview
Ireo Waterfront Pocket 4
Ireo Waterfront Pvt Ltd · Ludhiana
Units240
Completion2021-12-31Proposed
Valid to2022-11-30
Approvals7
Cases2
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Disputes & cases | 2 cases |
| Technical report | |
| Site & area | 2 site details · 3 unit types |
| Construction & progress | 2 progress details · 23 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 21 documents · 34 source links |
Registration
Registration
| Promoter | Ireo Waterfront Pvt Ltd | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH45-PR0041 | |
| Valid to | 2022-11-30 | |
| Project type | (1) Residential (Building/Tower Development) (2) Residential (Plotted Development) | |
| Status (as filed) | Completion Certificate | |
| Proposed completion | 2021-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Application for Occupancy/ Completion/ Phase Completion Certificate | 2017-11-29 | |
| Application for renewal of any of the NOCs/ Licenses | 2017-11-29 | |
| Completion/ Phase Completion certificate from Municipal/ Competent Authority | 2017-11-29 | |
| Electric Substation NOC | 2017-05-18 | |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2013-09-18 |
| License as Promoter from competent Authority | 2014-02-25 | |
| NOC from Mining Department | Permissions (Received) | 2011-02-24 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum |
|---|---|
| Not Avaliable | NCDRC, New Delhi |
| 0000 | NCDRC New Delhi |
Complaints & cases
| Cases | 2 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,11,893.4 | |
|---|---|---|
| Units | 240 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| PLOTS | 0.01 | 157 | RESIDENTIAL |
| . | 0.01 | 59 | VILLAS |
| VILLAS | 0.001 | 24 | EXPANDABLE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2014-02-25 | |
|---|---|---|
| Proposed completion | 2021-12-31 |
Quarterly progress
| 2023-Q1 | 2023-05-08 |
| 2022-Q4 | 2023-05-08 |
| 2022-Q3 | 2023-05-08 |
| 2022-Q1 | 2023-05-09 |
| 2022-Q2 | 2023-05-09 |
| 2018-Q1 | 2023-05-20 |
| 2018-Q2 | 2023-05-20 |
| 2018-Q4 | 2023-05-20 |
| 2019-Q4 | 2023-05-21 |
| 2021-Q1 | 2023-05-21 |
| 2021-Q2 | 2023-05-21 |
| 2021-Q4 | 2023-05-21 |
| 2021-Q3 | 2023-05-21 |
| 2020-Q1 | 2023-05-21 |
| 2020-Q2 | 2023-05-21 |
| 2020-Q3 | 2023-05-21 |
| 2020-Q4 | 2023-05-21 |
| 2018-Q3 | 2023-06-02 |
| 2019-Q1 | 2023-06-02 |
| 2019-Q2 | 2023-06-02 |
| 2019-Q3 | 2023-06-02 |
| 2023-Q2 | 2023-07-15 |
| 2023-Q3 | 2023-10-16 |
Extensions
| Valid to |
|---|
| 2022-11-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Ireo Waterfront Pvt Ltd | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 10 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10073&inPromoter_ID=1024&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Sanctioned Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- Amendments or revisions in sanctioned Layout/ Sanction / Building Plan · 2014-02-25
- Application for Occupancy/ Completion/ Phase Completion Certificate · 2017-11-29
- Application for renewal of any of the NOCs/ Licenses · 2017-11-29
- Borewell Registration certificate from Central Ground Water Authority · 2009-04-21
- Commencement Certificate (Mega Project Category) · Sign in to download
- Completion/ Phase Completion certificate from Municipal/ Competent Authority · 2017-11-29
- Electric Substation NOC · 2017-05-18
- Environment Clearance certificate/ NOC · 2013-09-18
- License as Promoter from competent Authority · 2014-02-25
- NOC from Mining Department · 2011-02-24
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- Application for Occupancy/ Completion/ Phase Completion Certificate · 2017-11-29
- Application for renewal of any of the NOCs/ Licenses · 2017-11-29
- Completion/ Phase Completion certificate from Municipal/ Competent Authority · 2017-11-29
- Electric Substation NOC · 2017-05-18
- Environment Clearance certificate/ NOC · 2013-09-18
- License as Promoter from competent Authority · 2014-02-25
- NOC from Mining Department · 2011-02-24
- Extension order · Sign in to download
- 2023-Q1 · 2023-05-08
- 2022-Q4 · 2023-05-08
- 2022-Q3 · 2023-05-08
- 2022-Q1 · 2023-05-09
- 2022-Q2 · 2023-05-09
- 2018-Q1 · 2023-05-20
- 2018-Q2 · 2023-05-20
- 2018-Q4 · 2023-05-20
- 2019-Q4 · 2023-05-21
- 2021-Q1 · 2023-05-21
- 2021-Q2 · 2023-05-21
- 2021-Q4 · 2023-05-21
- 2021-Q3 · 2023-05-21
- 2020-Q1 · 2023-05-21
- 2020-Q2 · 2023-05-21
- 2020-Q3 · 2023-05-21
- 2020-Q4 · 2023-05-21
- 2018-Q3 · 2023-06-02
- 2019-Q1 · 2023-06-02
- 2019-Q2 · 2023-06-02
- 2019-Q3 · 2023-06-02
- 2023-Q2 · 2023-07-15
- 2023-Q3 · 2023-10-16