DOSLDelhi NCR, Delhi Workspace

Overview

_Iris Tower_ of project Cloud 9 Towers

RISHABH BUILDWELL PVT. LTD. · Ghaziabad
Units162
Completion2019-06-30Revised · Proposed 2018-12-31
Registered on2017-08-01
Valid to2019-06-30
Approvals7
Complaints17As of 2026-10-29

Sections

Property title & search report
Approvals7 approvals
Disputes & cases17 project complaints · 56 promoter complaints
Contract & costs1 cost head
Technical report
Site & area4 site details · 108 unit types
Construction & progress3 progress details · 4 quarters · 1 extension
Developer & finance
Developer4 developer details
The evidence
Sources21 documents · 11 source links

Registration

Registration

PromoterRISHABH BUILDWELL PVT. LTD.
DistrictGhaziabad
RegulatorUP RERA
Registration numberUPRERAPRJ2956
Registered on2017-08-01
Valid to2019-06-30
Project typeResidential
Status (as filed)Registered Projects
Proposed completion2018-12-31
Revised completion2019-06-30