Overview
Jagdish Villa
MANDVI BUILDCON PVT.LTD · Patna
Units23
Booked2 of 23As of 2026-06-30
Construction progress37%As of 2026-06-30
Completion2029-09-15Proposed
Registered on2025-03-09
Valid to2029-09-15
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 11 unit types |
| Construction & progress | 4 progress details · 6 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 18 documents · 12 source links |
Registration
Registration
| Promoter | MANDVI BUILDCON PVT.LTD | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP181728050325150929E00 | |
| Registered on | 2025-03-09 | |
| Valid to | 2029-09-15 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2029-09-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | NAGAR PARISHAD PHULWARI SHARIF, PATNA |
| Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc. | |
| Notice of Commencement in form X | |
| Fire NOC | Office of the State Fire Officer-Cum-Director, Patna, Bihar |
| Airport NOC | Airports Authority of India |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,13,72,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 960.96 | |
|---|---|---|
| Built-up (m²) | 1,884.82 | |
| FAR | 1.97 | |
| Towers | 1 | |
| Units | 23 | |
| Booked | 2 | |
| Booked as of | 2026-06-30 |
Unit types
| 3 BHK | 3 | Jagdish Villa |
| 3 BHK | 3 | Jagdish Villa |
| 2 BHK | 3 | Jagdish Villa |
| 3 BHK | 3 | Jagdish Villa |
| 1 BHK | 1 | Jagdish Villa |
| 1 BHK | 1 | Jagdish Villa |
| 1 BHK | 1 | Jagdish Villa |
| 2 BHK | 1 | Jagdish Villa |
| 3 BHK | 1 | Jagdish Villa |
| 3 BHK | 3 | Jagdish Villa |
| 2 BHK | 3 | Jagdish Villa |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 37% | |
|---|---|---|
| As of | 2026-06-30 | |
| Start | 2024-10-30 | |
| Proposed completion | 2029-09-15 |
Quarterly progress
| 2026-Q2 | 2026-07-29 | 37% | 2 |
| 2026-Q1 | 2026-04-16 | ||
| 2025-Q4 | 2026-01-24 | ||
| 2025-Q3 | 2025-10-26 | ||
| 2025-Q2 | 2025-08-17 | ||
| 2025-Q1 | 2025-04-13 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MANDVI BUILDCON PVT.LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP31201800103-3
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP31201800103&ld=pan&pj=RERAP31201800103-3&f=2026-2027&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP31201800103-3
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-29
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-16
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-24
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-26
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-17
- Q4-Jan to Mar / 2024-2025 · 2025-04-13
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Notice of Commencement in form X
- 2026-Q1 · 2026-04-16
- 2025-Q4 · 2026-01-24
- 2025-Q3 · 2025-10-26
- 2025-Q2 · 2025-08-17
- 2025-Q1 · 2025-04-13