Overview
JSB SKY POINT
JSB INFRASTRUCTURES · Seujpur Road
Units55
Completion2029-12-31Proposed
Registered on2025-03-20
Valid to2030-07-16
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 3 cost heads · 5 quarters |
| Technical report | |
| Site & area | 2 site details · 7 unit types |
| Construction & progress | 2 progress details · 5 quarters |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 80 documents · 6 source links |
Registration
Registration
| Promoter | JSB INFRASTRUCTURES | |
|---|---|---|
| District | DIBRUGARH | |
| Locality | Seujpur Road | |
| Regulator | RERA Assam | |
| Registration number | RERAA DI 226 OF 2024-2025 | |
| Registered on | 2025-03-20 | |
| Valid to | 2030-07-16 | |
| Status (as filed) | Ongoing Projects | |
| Proposed completion | 2029-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Layout Plan | |||
| Building Plan | |||
| NOC/Building Permit | DIBRUGARH MUNICIPAL CORPORATION | 2025-01-16 | 2027-01-15 |
| I. BUILDING PERMISSION | 2025-01-16 | ||
| II. FIRE SUGGESTION | 2024-12-28 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,43,05,000 | |
|---|---|---|
| Construction | ₹18,43,81,539 | |
| Total | ₹27,01,47,053 |
Quarterly money flows
| 2025-Q2 | ₹3,45,14,032 | ₹2,19,06,179 | ₹62,395 |
| 2025-Q3 | ₹3,91,18,533 | ₹0 | ₹4,68,582 |
| 2025-Q4 | ₹20,65,78,517 | ₹1,97,57,393 | ₹27,817 |
| 2026-Q1 | ₹3,36,96,691 | ₹2,59,48,495 | ₹2,78,135 |
| 2026-Q2 | ₹2,19,49,384 | ₹1,48,59,950 | ₹35,998 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,422.3 | |
|---|---|---|
| Units | 55 |
Unit types
| 2 | 77.23 | 11 |
| 3 | 102.88 | 11 |
| 3 | 105.02 | 11 |
| 3 | 103.62 | 11 |
| 3 | 109.2 | 6 |
| 3 | 110.22 | 1 |
| 4 | 129.18 | 4 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-01-16 | |
|---|---|---|
| Proposed completion | 2029-12-31 |
Quarterly progress
| Quarter |
|---|
| 2025-Q2 |
| 2025-Q3 |
| 2025-Q4 |
| 2026-Q1 |
| 2026-Q2 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | JSB INFRASTRUCTURES | |
|---|---|---|
| Other projects in this city pack | 10 |
Sources
Sources
Source URLs & documents
- https://rera.assam.gov.in/admincontrol/custom_search
- https://rera.assam.gov.in/admincontrol/registered_projects/1
- https://rera.assam.gov.in/assistancecontrol/project_search_public/1
- https://rera.assam.gov.in/view_project/project_preview_open/2230
- https://rera.assam.gov.in/view_project/quaterly_schedule_preview_open/MTY5Mw==
- https://rera.assam.gov.in/view_project/searchprojectDetail/2230
- Registration Certificate
- LETTER OF AUTHORIZATION FOR AUTHORIZED SIGNATORY · 2025-01-08 · Sign in to download
- REGISTRATION CERTIFICATE OF THE ENTITY · 2025-01-11
- Other · 2025-01-11 · Sign in to download
- Other · 2025-01-11 · Sign in to download
- AUDITED BALANCE SHEET OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2025-01-11 · Sign in to download
- PHOTOCOPY OF BANK DRAFT · 2025-01-11 · Sign in to download
- BANK MANAGER'S LETTER MENTIONING THAT THE ACCOUNT HAS BEEN OPENED IN COMPLIANCE WITH THE SECTION 4(2)(L)(D) OF REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016 · 2025-01-20 · Sign in to download
- CASHFLOW STATEMENT · 2025-01-21 · Sign in to download
- LATEST NON ENCUMBRANCE CERTIFICATE · 2025-01-11 · Sign in to download
- TRACE MAP SHOWING NEARBY BY STREAMS, PONDS ETC. · 2025-01-11 · Sign in to download
- FORM B, DULY NOTARIZED · 2025-01-21 · Sign in to download
- FIRE NOC · 2025-01-11
- PLAN OF DEVELOPMENT WORKS · 2025-01-11
- ARCHITECT, STRUCTURAL ENGINEER AND CONTRACTOR DETAILS WITH NAME AND ADDRESS AS THE CASE MAY BE · 2025-01-11 · Sign in to download
- PROJECT COST ESTIMATE · 2025-01-11 · Sign in to download
- NO OBJECTION CERTIFICATE FROM THE COMPETENT AUTHORITY · 2025-01-20 · Sign in to download
- APPROVED DRAWING FROM COMPETENT AUTHORITY · 2025-01-20 · Sign in to download
- LOCATIONAL MAP INCLUDING LATITUDE AND LONGITUDE · 2025-01-20 · Sign in to download
- PROOF CHECKING OF STRUCTURAL DESIGN / VETTING CERTIFICATE · 2025-01-21 · Sign in to download
- COMMENCEMENT CERTIFICATE OF THE PROJECT · 2025-01-21 · Sign in to download
- CARPET AREA AND PARKING AREA DETAILS · 2025-01-22 · Sign in to download
- CA CERTFICATE · 2025-01-11 · Sign in to download
- Other · 2025-01-11 · Sign in to download
- ONGOING PROJECTLIST · 2025-01-11 · Sign in to download
- DECLARARTION ON REAL ESTATE AGENT · 2025-01-11 · Sign in to download
- DECLARATION ON EXTERNAL DEVELOPMENT · 2025-01-11 · Sign in to download
- Other · 2025-01-11 · Sign in to download
- REVENUE RECEIPT · 2025-01-11 · Sign in to download
- COMPLETED PROJECTS · 2025-01-11 · Sign in to download
- COMPLETION CERTIFIFCATES LAST FIVE YEAR · 2025-01-11 · Sign in to download
- DETAILS OF FIRM · 2025-01-11 · Sign in to download
- FINANCIALS OF NIKUNJ HARLALKA · 2025-01-11 · Sign in to download
- TRADE LICENSE · 2025-01-11 · Sign in to download
- Other · 2025-01-11 · Sign in to download
- FINANCIALS OF PUSPA DEVI HARLALKA · 2025-01-11 · Sign in to download
- FINANCIAL OF RAJA GUPTA · 2025-01-11 · Sign in to download
- ELECTRICAL NETWORK DISTRIBUTION 2ND, 8TH 11TH FLOOR PLAN · 2025-01-21
- ELECTRICAL NETWORK DISTRIBUTION 7TH FLOOR PLAN · 2025-01-21
- PLUMBING WATER TANK LOCATION MARKING · 2025-01-21 · Sign in to download
- STRUCTURAL CERTIFICATE (PROOF CHECKING) · 2025-01-21 · Sign in to download
- ELECTRICAL NETWORK DISTRIBUTION 1ST, 4TH AND 10TH FLOOR PLAN · 2025-01-21
- ELECTRICAL NETWORK DISTRIBUTION SITE PLAN · 2025-01-21
- PLUMBING 2ND, 8TH , 11TH FLOOR PLAN · 2025-01-21
- PLUMBING 5TH FLOOR PLAN · 2025-01-21
- PLUMBING 1ST , 10TH , 4TH FLOOR PLAN · 2025-01-21
- PLUMBING 6TH FLOOR PLAN · 2025-01-21
- ELECTRICAL NETWORK DISTRIBUTION 3RD AND 9TH FLOOR PLAN · 2025-01-21
- ELECTRICAL NETWORK DISTRIBUTION 5TH FLOOR PLAN · 2025-01-21
- ELECTRICAL NETWORK DISTRIBUTION 6TH FLOOR PLAN · 2025-01-21
- ELECTRICAL NETWORK DISTRIBUTION GROUND FLOOR PLAN · 2025-01-21
- PLUMBING 3RDAND 9TH FLOOR PLAN · 2025-01-21
- PLUMBING 7TH FLOOR PLAN · 2025-01-21
- PLUMBING SITE PLAN · 2025-01-21
- Project application order/letter · 2025-03-19 · Sign in to download
- CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT · 2026-01-02
- CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. · 2026-01-02
- A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. · 2026-01-02
- A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. · 2026-01-02
- SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. · 2026-01-02
- CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT · 2026-01-09
- CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. · 2026-01-09
- A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. · 2026-01-09
- A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. · 2026-01-09
- SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. · 2026-01-09
- CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT · 2026-04-06
- CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. · 2026-04-06
- A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. · 2026-04-06
- A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. · 2026-04-06
- SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. · 2026-04-06
- CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT · 2026-08-11
- CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. · 2026-08-11
- A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. · 2026-08-11
- A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. · 2026-08-11
- SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. · 2026-08-11
- CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT · 2026-08-13
- CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. · 2026-08-13
- A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. · 2026-08-13
- A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. · 2026-08-13
- SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. · 2026-08-13