Overview
Jubilee Juncttion
Jubilee Joy Homes LLP · Sahibzada Ajit Singh Nagar (Mohali)
Units159
Completion2022-03-31Proposed
Valid to2022-03-31
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 23 unit types |
| Construction & progress | 2 progress details · 18 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 79 documents · 32 source links |
Registration
Registration
| Promoter | Jubilee Joy Homes LLP | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PC0095 | |
| Valid to | 2022-03-31 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | Completion Certificate | |
| Proposed completion | 2022-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Legal Documents (Received) | 2019-05-10 |
| Application for renewal of any of the NOCs/ Licenses | Legal Documents (Received) | 2019-04-22 |
| CLU Certificate | ||
| Defense Clearance | Legal Documents (Received) | 2019-04-22 |
| Electric Substation NOC | Legal Documents (Received) | 2019-04-22 |
| License as Promoter from competent Authority | 2018-05-09 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2019-04-08 | |
| NOC from Mining Department | 2019-04-08 | |
| NOC from NHAI/ PWD | Legal Documents (Received) | 2019-04-22 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,21,23,63,211 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 14,811.37 | |
|---|---|---|
| Units | 159 |
Unit types
| Commercial Plot (Plot area provided instead of Carpet area) | 101.28 | 14 | SCO PLOTS |
| Commercial Plot (Plot area provided instead of Carpet area) | 150.66 | 4 | SCO PLOTS |
| Commercial Plot (Plot area provided instead of Carpet area) | 170.54 | 2 | SCO PLOTS |
| Commercial Built-up | 39.3 | 1 | BUILT-UP DSS |
| Commercial Built-up | 40.48 | 3 | BUILT-UP DSS |
| Commercial Built-up | 37.29 | 2 | BUILT-UP DSS |
| Commercial Built-up | 37.39 | 4 | BUILT-UP DSS |
| Commercial Built-up | 57.8 | 21 | BUILT-UP SCO FLOORS |
| Commercial Built-up | 87.26 | 1 | BUILT-UP SCO FLOORS |
| Commercial Built-up | 89.93 | 3 | BUILT-UP SCO FLOORS |
| Commercial Built-up | 90.07 | 7 | BUILT-UP SCO FLOORS |
| Commercial Built-up | 92.2 | 36 | BUILT-UP SCO FLOORS |
| Commercial Built-up | 156.9 | 12 | BUILT-UP SCO FLOORS |
| Commercial Built-up | 56.13 | 3 | BUILT-UP SCO FLOORS |
| Commercial Built-up | 152.87 | 1 | BUILT-UP SCO FLOORS |
| Commercial Built-up | 14.83 | 16 | BUILT-UP DSS FLOORS |
| Commercial Built-up | 21.41 | 2 | BUILT-UP DSS FLOORS |
| Commercial Built-up | 21.89 | 1 | BUILT-UP DSS FLOORS |
| Commercial Built-up | 22.46 | 16 | BUILT-UP DSS FLOORS |
| Commercial Built-up | 13.97 | 2 | BUILT-UP DSS FLOORS |
| Commercial Built-up | 14.12 | 1 | BUILT-UP DSS FLOORS |
| Commercial Plot (Plot area provided instead of Carpet area) | 51.21 | 6 | DSS PLOTS |
| Commercial Plot (Plot area provided instead of Carpet area) | 33.48 | 1 | DSS PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-03-28 | |
|---|---|---|
| Proposed completion | 2022-03-31 |
Quarterly progress
| 2020-Q3 | 2020-12-01 |
| 2020-Q4 | 2021-05-14 |
| 2021-Q1 | 2021-06-14 |
| 2021-Q2 | 2022-03-30 |
| 2021-Q3 | 2022-04-14 |
| 2021-Q4 | 2022-04-15 |
| 2022-Q1 | 2022-05-04 |
| 2022-Q2 | 2022-07-26 |
| 2022-Q3 | 2022-10-18 |
| 2022-Q4 | 2023-01-20 |
| 2023-Q1 | 2023-04-14 |
| 2023-Q2 | 2023-07-14 |
| 2023-Q3 | 2023-10-28 |
| 2023-Q4 | 2024-01-25 |
| 2024-Q1 | 2024-09-12 |
| 2024-Q2 | 2024-09-12 |
| 2024-Q3 | 2024-10-15 |
| 2024-Q4 | 2025-01-23 |
Extensions
| Valid to |
|---|
| 2023-09-29 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Jubilee Joy Homes LLP | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | YES Bank Limited | |
| Other projects in this city pack | 9 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | ABL STRUCTURES CONSULTANTS |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10855&inPromoter_ID=1484&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- CA Certificate (Form 3)
- CA Certificate (Form 3)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2019-05-10
- Amendments or revisions in sanctioned Layout/ Sanction / Building Plan · 2019-04-22
- Application for Occupancy/ Completion/ Phase Completion Certificate · 2019-04-22 · Sign in to download
- Application for renewal of any of the NOCs/ Licenses · 2019-04-22
- Borewell Registration certificate from Central Ground Water Authority · 2019-04-22
- Building Permit Issue from Municipal Authority · 2019-04-22 · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Defense Clearance · 2019-04-22
- Electric Substation NOC · 2019-04-22
- License as Promoter from competent Authority · 2018-05-09
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2019-04-08
- NOC from Mining Department · 2019-04-08
- NOC from NHAI/ PWD · 2019-04-22
- Other Document (Bank authentication for RERA Acc. without cheque) · 2019-04-26 · Sign in to download
- Other Document (Bank authentication for RERA Acc. without cheque) · 2019-04-26 · Sign in to download
- Other Document (Undertaking for RERA Inventory on Point 17) · 2019-04-22 · Sign in to download
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2019-05-10
- Application for renewal of any of the NOCs/ Licenses · 2019-04-22
- CLU Certificate
- Defense Clearance · 2019-04-22
- Electric Substation NOC · 2019-04-22
- License as Promoter from competent Authority · 2018-05-09
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2019-04-08
- NOC from Mining Department · 2019-04-08
- NOC from NHAI/ PWD · 2019-04-22
- Extension order · Sign in to download
- 2020-Q3 · 2020-12-01
- 2020-Q4 · 2021-05-14
- 2021-Q1 · 2021-06-14
- 2021-Q2 · 2022-03-30
- 2021-Q3 · 2022-04-14
- 2021-Q4 · 2022-04-15
- 2022-Q1 · 2022-05-04
- 2022-Q2 · 2022-07-26
- 2022-Q3 · 2022-10-18
- 2022-Q4 · 2023-01-20
- 2023-Q1 · 2023-04-14
- 2023-Q2 · 2023-07-14
- 2023-Q3 · 2023-10-28
- 2023-Q4 · 2024-01-25
- 2024-Q1 · 2024-09-12
- 2024-Q2 · 2024-09-12
- 2024-Q3 · 2024-10-15
- 2024-Q4 · 2025-01-23