Overview
Overview
Overview
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | 1 | 1 | – | Red flag |
| Disputes & cases | – | – | – | – |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | ||
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
Disputes & cases
Builder: SURAKSHA THE BANK RETIREES COMMUNITY LIVING
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Not checked. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Not checked. | |||||||
| Pending 2 | ||||||
|---|---|---|---|---|---|---|
| 13 Jul 2026 | 95/2026 | K-RERA Kerala Kerala | NELLANAD | Not stated | complaint | Pending, Low: Not decided yet. |
| 19 Jun 2026 | 65/2026 | K-RERA Kerala Kerala | NELLANAD | Not stated | complaint | Pending, Low: Not decided yet. |
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| Not checked. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
Source: K-RERA Kerala project page and the documents filed there, as read by us.
| – |
| – |
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
| Area on the KGIS map | Not verified yet | |
|---|---|---|
| Land area of this registration | 11,615 sq m | |
| Building plan (NELLANAD GRAMAPANCHAYATH) | Sanctioned 18 May 2023 · No. A3-BA(173393)/2023 | |
|---|---|---|
| Power NOC (BESCOM) | Not verified yet | |
| Fire NOC | Not verified yet | |
| Environmental clearance | Not verified yet | |
| Airport height NOC | Not verified yet | |
| Pollution board (CFE) | Not verified yet | |
| Clearances pending | 2, in the latest update | Review |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 2 | |
| RERA completion date | 17 Sep 2028 |
3BHK 100%
| Type | Flats | Carpet, as filed (sq ft) |
|---|---|---|
| 3BHK | 26 | Not filed |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | Not verified yet | |
| RERA completion date | 17 Sep 2028 | |
| Work began, as filed | 18 May 2023 | |
Booked 100%
| Registered units | 26 | |
|---|---|---|
| Booked | 26 | |
| Not booked | 0 |
| Escrow bank | FEDERAL BANK | |
|---|---|---|
| Designated account, collected | Not verified yet | |
| Designated account, withdrawn | Not verified yet | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 2 | |
| Developer's project loan | Not verified yet | |
|---|---|---|
| Records searched to | Not verified yet | |
| Building plan | Sanctioned 18 May 2023 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| Sale deed in favour of | Not verified yet | |
| Escrow bank | FEDERAL BANK | |