Overview
Kabilaso Enclave
NEELGEET CONSTRUCTION PVT LTD · Patna
Units46
Completion2022-06-15Proposed
Registered on2019-01-30
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 1 unit type |
| Construction & progress | 2 progress details · 10 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 20 documents · 15 source links |
Registration
Registration
| Promoter | NEELGEET CONSTRUCTION PVT LTD | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00126-1/780/R-379/2019 | |
| Registered on | 2019-01-30 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2022-06-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹75,62,50,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,762.83 | |
|---|---|---|
| Built-up (m²) | 4,866.08 | |
| FAR | 1.76 | |
| Towers | 2 | |
| Units | 46 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 46 | KABILASO ENCLAVE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-12-24 | |
|---|---|---|
| Proposed completion | 2022-06-15 |
Quarterly progress
| 2023-Q3 | 2024-07-25 |
| 2023-Q2 | 2024-07-25 |
| 2023-Q1 | 2023-04-20 |
| 2022-Q4 | 2023-01-21 |
| 2022-Q3 | 2022-10-12 |
| 2022-Q2 | 2022-08-08 |
| 2022-Q1 | 2022-07-02 |
| 2021-Q4 | 2022-07-02 |
| 2021-Q3 | 2021-10-07 |
| 2021-Q2 | 2021-10-07 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | NEELGEET CONSTRUCTION PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | Union Bank of India | |
| Other projects in this city pack | 1 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | Computer Foundation P Ltd |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP231201800126-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP231201800126-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-20
- Q3-Oct to Dec / 2022-2023 · 2023-01-21
- Q2-Jul to Sep / 2022-2023 · 2022-10-12
- Q1-Apr to Jun / 2022-2023 · 2022-08-08
- Q4-Jan to Mar / 2021-2022 · 2022-07-02
- Q3-Oct to Dec / 2021-2022 · 2022-07-02
- Q2-Jul to Sep / 2021-2022 · 2021-10-07
- Q1-Apr to Jun / 2021-2022 · 2021-10-07
- Notice of Commencement
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-20
- 2022-Q4 · 2023-01-21
- 2022-Q3 · 2022-10-12
- 2022-Q2 · 2022-08-08
- 2022-Q1 · 2022-07-02
- 2021-Q4 · 2022-07-02
- 2021-Q3 · 2021-10-07
- 2021-Q2 · 2021-10-07