Overview
KALAKRITI'S LALBAGH
KALAKRITI CONSTRUCTION · Patna
Units38
Booked0 of 38As of 2025-06-30
Construction progress95%As of 2025-06-30
Completion2021-07-03Proposed
Registered on2018-09-19
Valid to2021-07-03
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 2 unit types |
| Construction & progress | 4 progress details · 27 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 42 documents · 31 source links |
Registration
Registration
| Promoter | KALAKRITI CONSTRUCTION | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00359-1/371/R-175/2018 | |
| Registered on | 2018-09-19 | |
| Valid to | 2021-07-03 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2021-07-03 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Environment Clearance | 2025-01-01 |
| Fire NOC | 2025-01-01 |
| Airport NOC | 2025-01-01 |
| Water Supply Permission | 2025-01-01 |
| Other approval | 2025-01-01 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹5,67,47,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,938.36 | |
|---|---|---|
| Built-up (m²) | 3,705.36 | |
| FAR | 1.91 | |
| Towers | 2 | |
| Units | 38 | |
| Booked | 0 | |
| Booked as of | 2025-06-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 2 BHK | 22 | KLAKRITI'S LALBAGH |
| 3 BHK | 16 | KLAKRITI'S LALBAGH |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 95% | |
|---|---|---|
| As of | 2025-06-30 | |
| Start | 2018-07-03 | |
| Proposed completion | 2021-07-03 |
Quarterly progress
| 2025-Q2 | 2025-08-19 | 95% | 0 |
| 2025-Q1 | 2025-04-15 | ||
| 2024-Q4 | 2025-01-15 | ||
| 2024-Q3 | 2024-10-29 | ||
| 2024-Q2 | 2024-07-14 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2024-07-25 | ||
| 2022-Q4 | 2024-07-25 | ||
| 2022-Q3 | 2024-07-25 | ||
| 2022-Q2 | 2024-07-25 | ||
| 2022-Q1 | 2024-07-25 | ||
| 2021-Q4 | 2024-07-25 | ||
| 2021-Q3 | 2024-07-25 | ||
| 2021-Q2 | 2024-07-25 | ||
| 2021-Q1 | 2024-07-25 | ||
| 2020-Q4 | 2024-07-25 | ||
| 2020-Q3 | 2024-07-25 | ||
| 2020-Q2 | 2024-07-25 | ||
| 2020-Q1 | 2024-07-25 | ||
| 2019-Q4 | 2024-07-25 | ||
| 2019-Q3 | 2024-07-25 | ||
| 2019-Q2 | 2024-07-25 | ||
| 2019-Q1 | 2024-07-25 | ||
| 2018-Q4 | 2024-07-25 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | KALAKRITI CONSTRUCTION | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP15201800359-1
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP15201800359&ld=pan&pj=RERAP15201800359-1&f=2025-2026&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP15201800359-1
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-19
- Q4-Jan to Mar / 2024-2025 · 2025-04-15
- Q3-Oct to Dec / 2024-2025 · 2025-01-15
- Q2-Jun to Sep / 2024-2025 · 2024-10-29
- Q1-Apr to Jun / 2024-2025 · 2024-07-14
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2024-07-25
- Q3-Oct to Dec / 2022-2023 · 2024-07-25
- Q2-Jul to Sep / 2022-2023 · 2024-07-25
- Q1-Apr to Jun / 2022-2023 · 2024-07-25
- Q4-Jan to Mar / 2021-2022 · 2024-07-25
- Q3-Oct to Dec / 2021-2022 · 2024-07-25
- Q2-Jul to Sep / 2021-2022 · 2024-07-25
- Q1-Apr to Jun / 2021-2022 · 2024-07-25
- Q4-Jan to Mar / 2020-2021 · 2024-07-25
- Q3-Oct to Dec / 2020-2021 · 2024-07-25
- Q2-Jul to Sep / 2020-2021 · 2024-07-25
- Q1-Apr to Jun / 2020-2021 · 2024-07-25
- Q4-Jan to Mar / 2019-2020 · 2024-07-25
- Q3-Oct to Dec / 2019-2020 · 2024-07-25
- Q2-Jul to Sep / 2019-2020 · 2024-07-25
- Q1-Apr to Jun / 2019-2020 · 2024-07-25
- Q4-Jan to Mar / 2018-2019 · 2024-07-25
- Q3-Oct to Dec / 2018-2019 · 2024-07-25
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- 2025-Q1 · 2025-04-15
- 2024-Q4 · 2025-01-15
- 2024-Q3 · 2024-10-29
- 2024-Q2 · 2024-07-14
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2024-07-25
- 2022-Q4 · 2024-07-25
- 2022-Q3 · 2024-07-25
- 2022-Q2 · 2024-07-25
- 2022-Q1 · 2024-07-25
- 2021-Q4 · 2024-07-25
- 2021-Q3 · 2024-07-25
- 2021-Q2 · 2024-07-25
- 2021-Q1 · 2024-07-25
- 2020-Q4 · 2024-07-25
- 2020-Q3 · 2024-07-25
- 2020-Q2 · 2024-07-25
- 2020-Q1 · 2024-07-25
- 2019-Q4 · 2024-07-25
- 2019-Q3 · 2024-07-25
- 2019-Q2 · 2024-07-25
- 2019-Q1 · 2024-07-25
- 2018-Q4 · 2024-07-25