Overview
Kalyan Avanti
Kalyan Developers · Near UST-Infosys Campus
Units73
Booked73 of 73
Construction progress100%As of 2023-01-05
Completion2022-03-31Revised · Proposed 2022-03-31
Registered on2021-05-31
Approvals2
Cases1
Complaints1
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Disputes & cases | 1 case · 1 project complaint |
| Technical report | |
| Site & area | 5 site details · 8 unit types |
| Construction & progress | 5 progress details · 6 quarters · 1 extension |
| Developer & finance | |
| Developer | 3 developer details · 2 professional firms |
| The evidence | |
| Sources | 7 documents · 6 source links |
Registration
Registration
| Promoter | Kalyan Developers | |
|---|---|---|
| District | Thiruvananthapuram | |
| Locality | Near UST-Infosys Campus | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/241/2020 | |
| Registered on | 2021-05-31 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Completed | |
| Proposed completion | 2022-03-31 | |
| Revised completion | 2022-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | ZAE/BA/95/16 | 2020-09-02 | 2023-02-09 | Thiruvananthapuram |
| Development Permit | ATR-BA(13790)/2018 | 2018-01-20 | 2021-01-20 | Thiruvananthapuram |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind |
|---|---|---|
| 25/2023 | K-RERA Kerala | Complaint |
Complaints & cases
| Cases | 1 | |
|---|---|---|
| Project complaints | 1 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,240 | |
|---|---|---|
| Built-up (m²) | 8,724.8 | |
| Towers | 0 | |
| Units | 73 | |
| Booked | 73 |
Unit types
| 2BHK | 15 | 15 | Kalyan Avanti |
| 2BHK | 1 | 1 | Kalyan Avanti |
| 2BHK | 14 | 14 | Kalyan Avanti |
| 2BHK | 14 | 14 | Kalyan Avanti |
| 3BHK | 13 | 13 | Kalyan Avanti |
| 3BHK | 13 | 13 | Kalyan Avanti |
| 4BHK | 1 | 1 | Kalyan Avanti |
| 4BHK | 2 | 2 | Kalyan Avanti |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2023-01-05 | |
| Start | 1900-01-01 | |
| Proposed completion | 2022-03-31 | |
| Revised completion | 2022-03-31 |
Quarterly progress
| Quarter |
|---|
| 2022-2023 Q2 |
| 2022-2023 Q3 |
| 2021-2022 Q1 |
| 2021-2022 Q2 |
| 2021-2022 Q4 |
| 2020-2021 Q4 |
Extensions
| Valid to |
|---|
| 2022-03-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Kalyan Developers | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 18 |
Professional firms
| Role | Firm |
|---|---|
| Architect | Ar K C George & Associates |
| Engineer | Associates Structural Consultants |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/complaint-list?ruling_by=all&page=49
- https://rera.kerala.gov.in/projects/112
- https://rera.kerala.gov.in/projects?district=601&page=11
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=4CD2ZBTwa6oSuHhxgWfNY8DVJl2ebEVvfBb4TDpqpyBETzSrjG7kTj2VvebO%2BozkbmXHYE40nN5bk2Un6QVPmHzhIYa3iELOIl%2FPybsFKkSTpq1xa8h%2BAx0BX8shQTKxT40%2Bf4nbqj2dxheEcmqISiroHSTCYEvR2EoB4HsMOqw%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=112&Division=1&UserID=30251&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Extension Certificate · Sign in to download
- Signed project certificate · 2021-05-31
- Extension certificate · 2021-12-30 · Sign in to download
- Declaration by the Promoter - Form No. 6 · 2022-12-16 · Sign in to download
- Occupancy Certificate · 2022-08-31