KAMALA CASTLE

SAI VARSHITH CONSTRUCTIONS · KARMANGHAT
Units15
Booked1 of 15
Construction progress48.5%
Completion2023-11-16Revised · Proposed 2023-11-16
Registered on2018-11-30
Valid to2023-11-16
Approvals1

Sections

Property title & search report
Approvals1 approval
Technical report
Site & area5 site details · 10 unit types
Construction & progress3 progress details
Developer & finance
Developer3 developer details
The evidence
Sources9 documents · 3 source links

Registration

Registration

PromoterSAI VARSHITH CONSTRUCTIONS
DistrictRanga Reddy
LocalityKARMANGHAT
RegulatorTelangana RERA
Registration numberP02400000060
Registered on2018-11-30
Valid to2023-11-16
Project typeResidential
Status (as filed)On-Going Project
Proposed completion2023-11-16