DOSLChhattisgarh Workspace

Overview

KANCHAN VIHAR PHASE - I

KANCHAN COMPLEXES PVT LTD · RAIPUR
Units78
Booked78 of 78As of 2025-12-31
Construction progress100%As of 2025-12-31
Completion2025-07-07Revised · Proposed 2019-05-31
Registered on2018-06-26
Approvals4
Cases1

Sections

Property title & search report
Approvals4 approvals
Disputes & cases1 case
Contract & costs2 cost heads · 29 quarters
Technical report
Site & area3 site details · 78 unit types
Construction & progress4 progress details · 29 quarters
Developer & finance
Developer4 developer details
The evidence
Sources117 documents · 10 source links

Registration

Registration

PromoterKANCHAN COMPLEXES PVT LTD
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA260618000340
Registered on2018-06-26
Project typeGroup Housing
Status (as filed)Ongoing
Proposed completion2019-05-31
Revised completion2025-07-07