Overview
KARTA GRIHAM
GRIHAM DEVELOPERS PRIVATE LIMITED · Patna
Units80
Booked35 of 80As of 2025-12-31
Construction progress100%As of 2025-12-31
Completion2023-09-15Proposed
Registered on2019-07-15
Valid to2023-09-15
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 3 unit types |
| Construction & progress | 4 progress details · 27 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 37 documents · 33 source links |
Registration
Registration
| Promoter | GRIHAM DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP01030-2/941/R-696/2019 | |
| Registered on | 2019-07-15 | |
| Valid to | 2023-09-15 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2023-09-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Authority |
|---|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) | |
| Notice of Commencement | |
| Fire NOC | State Fire Officer Bihar Patna |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,60,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,643.49 | |
|---|---|---|
| Built-up (m²) | 8,335.52 | |
| FAR | 2.5 | |
| Towers | 0 | |
| Units | 80 | |
| Booked | 35 | |
| Booked as of | 2025-12-31 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 2 BHK | 23 | KARTA GRIHAM |
| 3 BHK | 53 | KARTA GRIHAM |
| 4 BHK | 4 | KARTA GRIHAM |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-12-31 | |
| Start | 2019-04-15 | |
| Proposed completion | 2023-09-15 |
Quarterly progress
| 2025-Q4 | 2026-01-31 | 100% | 35 |
| 2025-Q3 | 2025-10-30 | ||
| 2025-Q2 | 2025-08-20 | ||
| 2025-Q1 | 2025-04-25 | ||
| 2024-Q4 | 2025-01-16 | ||
| 2024-Q3 | 2024-12-11 | ||
| 2024-Q3 | 2024-10-15 | ||
| 2024-Q2 | 2024-10-15 | ||
| 2024-Q1 | 2024-10-15 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2023-04-15 | ||
| 2022-Q4 | 2023-03-26 | ||
| 2022-Q3 | 2023-03-26 | ||
| 2022-Q2 | 2022-09-18 | ||
| 2022-Q1 | 2022-06-18 | ||
| 2021-Q4 | 2022-02-08 | ||
| 2021-Q3 | 2021-10-25 | ||
| 2021-Q2 | 2021-07-13 | ||
| 2021-Q1 | 2021-07-13 | ||
| 2020-Q4 | 2021-01-23 | ||
| 2020-Q3 | 2021-01-23 | ||
| 2020-Q2 | 2020-10-01 | ||
| 2020-Q1 | 2020-05-20 | ||
| 2019-Q4 | 2020-05-20 | ||
| 2019-Q3 | 2019-12-26 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GRIHAM DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF BIKANER AND JAIPUR | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP2810201801030-2
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP2810201801030&ld=pan&pj=RERAP2810201801030-2&f=2025-2026&q=3
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP2810201801030-2
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-31
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-30
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-20
- Q4-Jan to Mar / 2024-2025 · 2025-04-25
- Q3-Oct to Dec / 2024-2025 · 2025-01-16
- Q2-Jun to Sep / 2024-2025 · 2024-12-11
- Q2-Jul to Sep / 2024-2025 · 2024-10-15
- Q1-Apr to Jun / 2024-2025 · 2024-10-15
- Q4-Jan to Mar / 2023-2024 · 2024-10-15
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-15
- Q3-Oct to Dec / 2022-2023 · 2023-03-26
- Q2-Jul to Sep / 2022-2023 · 2023-03-26
- Q1-Apr to Jun / 2022-2023 · 2022-09-18
- Q4-Jan to Mar / 2021-2022 · 2022-06-18
- Q3-Oct to Dec / 2021-2022 · 2022-02-08
- Q2-Jul to Sep / 2021-2022 · 2021-10-25
- Q1-Apr to Jun / 2021-2022 · 2021-07-13
- Q4-Jan to Mar / 2020-2021 · 2021-07-13
- Q3-Oct to Dec / 2020-2021 · 2021-01-23
- Q2-Jul to Sep / 2020-2021 · 2021-01-23
- Q1-Apr to Jun / 2020-2021 · 2020-10-01
- Q4-Jan to Mar / 2019-2020 · 2020-05-20
- Q3-Oct to Dec / 2019-2020 · 2020-05-20
- Q2-Jul to Sep / 2019-2020 · 2019-12-26
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- 2025-Q3 · 2025-10-30
- 2025-Q2 · 2025-08-20
- 2025-Q1 · 2025-04-25
- 2024-Q4 · 2025-01-16
- 2024-Q3 · 2024-12-11
- 2024-Q3 · 2024-10-15
- 2024-Q2 · 2024-10-15
- 2024-Q1 · 2024-10-15
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-15
- 2022-Q4 · 2023-03-26
- 2022-Q3 · 2023-03-26
- 2022-Q2 · 2022-09-18
- 2022-Q1 · 2022-06-18
- 2021-Q4 · 2022-02-08
- 2021-Q3 · 2021-10-25
- 2021-Q2 · 2021-07-13
- 2021-Q1 · 2021-07-13
- 2020-Q4 · 2021-01-23
- 2020-Q3 · 2021-01-23
- 2020-Q2 · 2020-10-01
- 2020-Q1 · 2020-05-20
- 2019-Q4 · 2020-05-20
- 2019-Q3 · 2019-12-26