Overview
Kashish Maanik Residency
MUSKAN CONSTRUCTIONS PRIVATE LIMITED · Patna
Units27
Booked1 of 27As of 2026-09-30
Construction progress28%As of 2026-09-30
Completion2029-06-10Proposed
Registered on2025-03-10
Valid to2029-06-10
Approvals8
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 1 unit type |
| Construction & progress | 4 progress details · 6 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 18 documents · 12 source links |
Registration
Registration
| Promoter | MUSKAN CONSTRUCTIONS PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP181928060325100629E00 | |
| Registered on | 2025-03-10 | |
| Valid to | 2029-06-10 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2029-06-10 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | 2024-11-06 | Patna Metropolitan Area Authority | |
| Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc. | |||
| Notice of Commencement in form X | |||
| Environment Clearance | N.A | ||
| Fire NOC | 2029-06-10 | Director State Fire Services Bihar | |
| Airport NOC | N.A | ||
| Water Supply Permission | Own Boring | ||
| Other approval | No |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹14,17,80,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,194.61 | |
|---|---|---|
| Built-up (m²) | 2,982.54 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 27 | |
| Booked | 1 | |
| Booked as of | 2026-09-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 27 | Kashish Maanik Residency |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 28% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2024-06-20 | |
| Proposed completion | 2029-06-10 |
Quarterly progress
| 2026-Q3 | 2026-10-27 | 28% | 1 |
| 2026-Q2 | 2026-07-28 | ||
| 2026-Q1 | 2026-04-28 | ||
| 2025-Q4 | 2026-01-27 | ||
| 2025-Q3 | 2025-10-24 | ||
| 2025-Q2 | 2025-07-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MUSKAN CONSTRUCTIONS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 7 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP114201800262-8
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP114201800262&ld=pan&pj=RERAP114201800262-8&f=2026-2027&q=2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP114201800262-8
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-27
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-28
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-28
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-27
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-24
- Q1 (Apr - Jun) / 2025-2026 · 2025-07-15
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Notice of Commencement in form X
- 2026-Q2 · 2026-07-28
- 2026-Q1 · 2026-04-28
- 2025-Q4 · 2026-01-27
- 2025-Q3 · 2025-10-24
- 2025-Q2 · 2025-07-15