Overview
Kashyap Sunaina Vihar
Kashyap Green Homes Pvt. Ltd. · Patna
Units38
Completion2019-04-01Proposed
Registered on2018-07-16
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 1 unit type |
| Construction & progress | 2 progress details · 3 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 19 documents · 8 source links |
Registration
Registration
| Promoter | Kashyap Green Homes Pvt. Ltd. | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00132-1/92/R-91/2018 | |
| Registered on | 2018-07-16 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Completed | |
| Proposed completion | 2019-04-01 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,46,40,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,117.13 | |
|---|---|---|
| Built-up (m²) | 7,792.4 | |
| FAR | 2.49 | |
| Towers | 2 | |
| Units | 38 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 38 | Kashyap Sunaina Vihar |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-11-01 | |
|---|---|---|
| Proposed completion | 2019-04-01 |
Quarterly progress
| Quarter | Filed on |
|---|---|
| 2019-Q1 | 2019-02-09 |
| 2018-Q4 | 2019-12-31 |
| 2018-Q3 | 2019-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Kashyap Green Homes Pvt. Ltd. | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 7 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP251201800132-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP251201800132-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q4-Jan to Mar / 2018-2019 · 2019-02-09
- Q3-Oct to Dec / 2018-2019 · 2019-12-31
- Q2-Jul to Sep / 2018-2019 · 2019-12-31
- Notice of Commencement
- 2019-Q1 · 2019-02-09
- 2018-Q4 · 2019-12-31
- 2018-Q3 · 2019-12-31