Overview
KASTURI BAROG THE LUXURY RESIDENCES
MONICA SAMEER JAGTAP · Solan
Units16
Registered on2025-11-04
Valid to2030-07-04
Approvals9
Complaints0As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Disputes & cases | 0 project complaints |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 16 unit types |
| Construction & progress | 3 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 24 documents · 24 source links |
Registration
Registration
| Promoter | MONICA SAMEER JAGTAP | |
|---|---|---|
| District | Solan | |
| Regulator | Himachal Pradesh Real Estate Regulatory Authority | |
| Registration number | HPRERASOL2025171/P | |
| Registered on | 2025-11-04 | |
| Valid to | 2030-07-04 | |
| Project type | Development / Construction (Residential) | |
| Status (as filed) | New Project Launch |
Approvals
Is it approved for its use?
Approvals
Approvals
| Plan sanction | Special Area Development Authority (SADA) |
| Structural Stability Certificate | |
| ELECTRICITY BOARD NOC | |
| IPH NOC/ affidavit | |
| Tcp approval map and letter | |
| Sanctioned Letter by TCP/ULB(s)/Local Authority * | |
| Sanctioned Location Plan * | |
| Sanctioned Site Plan * | |
| Sanctioned Building Plan * |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹40,00,000 | |
|---|---|---|
| Construction | ₹8,69,09,000 | |
| Total | ₹9,09,09,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,058 | |
|---|---|---|
| Built-up (m²) | 1,607.1 | |
| Units | 16 |
Unit types
| 2 BHK | 87.25 | 1 | A-BLOCK |
| Studio Apartment | 31.65 | 1 | A-BLOCK |
| 2 BHK | 90.45 | 1 | A-BLOCK |
| 2 BHK | 87.25 | 1 | A-BLOCK |
| Studio Apartment | 31.65 | 1 | A-BLOCK |
| 2 BHK | 90.45 | 1 | A-BLOCK |
| 2 BHK | 87.25 | 1 | A-BLOCK |
| Studio Apartment | 31.65 | 1 | A-BLOCK |
| 2 BHK | 90.45 | 1 | A-BLOCK |
| 2 BHK | 87.25 | 1 | A-BLOCK |
| Studio Apartment | 31.65 | 1 | A-BLOCK |
| 2 BHK | 87.25 | 1 | A-BLOCK |
| 3 BHK | 143.38 | 1 | A-BLOCK |
| Studio Apartment | 39.28 | 1 | A-BLOCK |
| 3 BHK | 149.16 | 1 | A-BLOCK |
| Studio Apartment | 31.3 | 1 | A-BLOCK |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Quarterly progress
| Quarter |
|---|
| 2025-Q4 |
| 2026-Q1 |
| 2026-Q2 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MONICA SAMEER JAGTAP | |
|---|---|---|
| Type | Individual | |
| Escrow bank | Union bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://hprera.nic.in/Complaints/Litigation/Litigation_PreviewPV?qs=f3fIU7vFXK1qeVYzd9qDCIjy%2Bg4H0DPsmZSVqoE0MfxfY20P6%2BbArsKtdCL6zNaJU2QZQol8IjnA%2BvAUn%2B%2BLwP6OtHnFJvd8kLsxSxrAAlpkAwvx7QoWkg%3D%3D
- https://hprera.nic.in/Home/PRGrid
- https://hprera.nic.in/Home/ProjectsQPR?FnYr=2025-26
- https://hprera.nic.in/Home/ProjectsQPR?FnYr=2026-27
- https://hprera.nic.in/Project/ProjectRegistration/AssociatedVendors_PreviewPV?qs=f3fIU7vFXK1qeVYzd9qDCIjy%2Bg4H0DPsmZSVqoE0MfxfY20P6%2BbArsKtdCL6zNaJU2QZQol8IjnA%2BvAUn%2B%2BLwP6OtHnFJvd8kLsxSxrAAlpkAwvx7QoWkg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/BankDetails_PreviewPV?qs=f3fIU7vFXK1qeVYzd9qDCIjy%2Bg4H0DPsmZSVqoE0MfxfY20P6%2BbArsKtdCL6zNaJU2QZQol8IjnA%2BvAUn%2B%2BLwP6OtHnFJvd8kLsxSxrAAlpkAwvx7QoWkg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/Documents_PreviewPV?qs=f3fIU7vFXK1qeVYzd9qDCIjy%2Bg4H0DPsmZSVqoE0MfxfY20P6%2BbArsKtdCL6zNaJU2QZQol8IjnA%2BvAUn%2B%2BLwP6OtHnFJvd8kLsxSxrAAlpkAwvx7QoWkg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/InventoryDetails_PreviewPV?qs=f3fIU7vFXK1qeVYzd9qDCIjy%2Bg4H0DPsmZSVqoE0MfxfY20P6%2BbArsKtdCL6zNaJU2QZQol8IjnA%2BvAUn%2B%2BLwP6OtHnFJvd8kLsxSxrAAlpkAwvx7QoWkg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/PastProjectDetails_PreviewPV?qs=f3fIU7vFXK1qeVYzd9qDCIjy%2Bg4H0DPsmZSVqoE0MfxfY20P6%2BbArsKtdCL6zNaJU2QZQol8IjnA%2BvAUn%2B%2BLwP6OtHnFJvd8kLsxSxrAAlpkAwvx7QoWkg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/Payment_PreviewPV?qs=f3fIU7vFXK1qeVYzd9qDCIjy%2Bg4H0DPsmZSVqoE0MfxfY20P6%2BbArsKtdCL6zNaJU2QZQol8IjnA%2BvAUn%2B%2BLwP6OtHnFJvd8kLsxSxrAAlpkAwvx7QoWkg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/ProjectDetails_PreviewPV?qs=f3fIU7vFXK1qeVYzd9qDCIjy%2Bg4H0DPsmZSVqoE0MfxfY20P6%2BbArsKtdCL6zNaJU2QZQol8IjnA%2BvAUn%2B%2BLwP6OtHnFJvd8kLsxSxrAAlpkAwvx7QoWkg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/PromotorDetails_PreviewPV?qs=f3fIU7vFXK1qeVYzd9qDCIjy%2Bg4H0DPsmZSVqoE0MfxfY20P6%2BbArsKtdCL6zNaJU2QZQol8IjnA%2BvAUn%2B%2BLwP6OtHnFJvd8kLsxSxrAAlpkAwvx7QoWkg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/PublicDashboard/GetFilteredProjectsPV?DistrictList%5B0%5D.Selected=false&DistrictList%5B0%5D.Value=18&DistrictList%5B1%5D.Selected=false&DistrictList%5B1%5D.Value=24&DistrictList%5B2%5D.Selected=false&DistrictList%5B2%5D.Value=20&DistrictList%5B3%5D.Selected=false&DistrictList%5B3%5D.Value=23&DistrictList%5B4%5D.Selected=false&DistrictList%5B4%5D.Value=25&DistrictList%5B5%5D.Selected=false&DistrictList%5B5%5D.Value=22&DistrictList%5B6%5D.Selected=false&DistrictList%5B6%5D.Value=26&DistrictList%5B7%5D.Selected=false&DistrictList%5B7%5D.Value=21&DistrictList%5B8%5D.Selected=false&DistrictList%5B8%5D.Value=15&DistrictList%5B9%5D.Selected=false&DistrictList%5B9%5D.Value=17&DistrictList%5B10%5D.Selected=false&DistrictList%5B10%5D.Value=16&DistrictList%5B11%5D.Selected=false&DistrictList%5B11%5D.Value=19&PlottedTypeList%5B0%5D.Selected=false&PlottedTypeList%5B0%5D.Value=P&PlottedTypeList%5B1%5D.Selected=false&PlottedTypeList%5B1%5D.Value=F&PlottedTypeList%5B2%5D.Selected=false&PlottedTypeList%5B2%5D.Value=M&ResidentialTypeList%5B0%5D.Selected=false&ResidentialTypeList%5B0%5D.Value=R&ResidentialTypeList%5B1%5D.Selected=false&ResidentialTypeList%5B1%5D.Value=C&ResidentialTypeList%5B2%5D.Selected=false&ResidentialTypeList%5B2%5D.Value=M&AreaFrom=&AreaUpto=&SearchText=
- MONICA Gender : · Sign in to download
- Past Project Details document · Sign in to download
- Income Tax Return (ITR) Acknowledgement * · 2025-07-15 · Sign in to download
- Income Tax Return (ITR) Acknowledgement * · 2025-07-15 · Sign in to download
- Income Tax Return (ITR) Acknowledgement * · 2025-07-15 · Sign in to download
- Project Report · 2025-10-05 · Sign in to download
- Structural Stability Certificate · 2025-08-24
- ELECTRICITY BOARD NOC · 2025-08-23
- ground water aplication · 2025-10-05 · Sign in to download
- Brif history of project · 2025-10-05 · Sign in to download
- court judgment · 2025-10-05 · Sign in to download
- Tcp approval map and letter · 2025-10-05
- Sanctioned Letter by TCP/ULB(s)/Local Authority * · 2025-02-06
- Sanctioned Location Plan * · 2025-02-06
- Sanctioned Site Plan * · 2025-02-06
- Sanctioned Building Plan * · 2025-02-06
- Project Specifications * · 2025-08-24 · Sign in to download
- Consent Letter · Sign in to download
- Certificate · Sign in to download
- Consent Letter · Sign in to download
- Certificate · Sign in to download
- Consent Letter · Sign in to download
- Certificate · Sign in to download
- Account Details Proof · Sign in to download
- Structural Stability Certificate
- ELECTRICITY BOARD NOC
- IPH NOC/ affidavit
- Tcp approval map and letter
- Sanctioned Letter by TCP/ULB(s)/Local Authority *
- Sanctioned Location Plan *
- Sanctioned Site Plan *
- Sanctioned Building Plan *
- 2025-Q4
- 2026-Q1
- 2026-Q2