DOSLBihar Workspace

Overview

KAUSHLYA GREEN

NISHANJALI HOMES PVT .LTD · Patna
Units24
Booked12 of 24As of 2025-12-31
Construction progress96%As of 2025-12-31
Completion2026-02-15Proposed
Registered on2022-04-20
Valid to2026-02-15
Approvals7

Sections

Property title & search report
Approvals7 approvals
Contract & costs1 cost head
Technical report
Site & area7 site details · 2 unit types
Construction & progress4 progress details · 15 quarters
Developer & finance
Developer4 developer details
The evidence
Sources28 documents · 21 source links

Registration

Registration

PromoterNISHANJALI HOMES PVT .LTD
DistrictPatna
RegulatorRERA Bihar
Registration numberBRERAP81735-1/02/R-1291/2022
Registered on2022-04-20
Valid to2026-02-15
Project typeResidential/Group Housing
Status (as filed)New Project Launch
Proposed completion2026-02-15