KAVERI SANGAM

A SHRIDHAR INFRACON LLP · Ahmedabad
Units224
Booked210 of 224
Construction progress100%As of 2018-02-03
Completion2017-12-31Proposed
Registered on2017-09-01
Valid to2017-12-31
Approvals4

Sections

Property title & search report
Approvals4 approvals · 1 occupancy certificate
Contract & costs3 cost heads
Technical report
Site & area4 site details · 4 unit types
Construction & progress4 progress details · 2 quarters
Developer & finance
Developer4 developer details
The evidence
Sources34 documents · 31 source links

Registration

Registration

PromoterA SHRIDHAR INFRACON LLP
DistrictAhmedabad
RegulatorGujRERA
Registration numberPR/GJ/AHMEDABAD/DASKROI/AUDA/MAA00044/010917
Registered on2017-09-01
Valid to2017-12-31
Project typeMixed Development
Status (as filed)Public completed project list
Proposed completion2017-12-31