Overview
KINGS RESIDENCY-A
REMARK CHEMICALS LLP · Jaipur
Units72
Booked40 of 72As of 2024-06-30
Completion2027-07-31Revised · Proposed 2023-10-26
Registered on2023-11-05
Valid to2027-07-31
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 34 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 56 documents · 6 source links |
Registration
Registration
| Promoter | REMARK CHEMICALS LLP | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2023/2793 | |
| Registered on | 2023-11-05 | |
| Valid to | 2027-07-31 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2023-10-26 | |
| Revised completion | 2027-07-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹9,03,34,260 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹12,83,34,260 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2024-Q2 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 15,655 | |
|---|---|---|
| Built-up (m²) | 9,190.6 | |
| Towers | 72 | |
| Units | 72 | |
| Booked | 40 | |
| Booked as of | 2024-06-30 |
Unit types
| 1 | 1 | 0 |
| 2 to 3 | 2 | 0 |
| 4 | 1 | 0 |
| 5 | 1 | 0 |
| 6 TO 19 | 14 | 0 |
| 20 | 1 | 0 |
| 21 | 1 | 0 |
| 22 TO 27 | 6 | 0 |
| 28 | 1 | 0 |
| 29 | 1 | 0 |
| 30 | 1 | 0 |
| 31 | 1 | 0 |
| 32 | 1 | 0 |
| 33 | 1 | 0 |
| 34 | 1 | 0 |
| 35 | 1 | 0 |
| 36 | 1 | 0 |
| 37 | 1 | 0 |
| 38 | 1 | 0 |
| 39 | 1 | 0 |
| 40 TO 44 | 5 | 0 |
| 45 | 1 | 0 |
| 46 | 1 | 0 |
| 47 TO 55 | 9 | 0 |
| 56 | 1 | 0 |
| 57 | 1 | 0 |
| 58 TO 63 | 6 | 0 |
| 64 TO 66 | 3 | 0 |
| 67 | 1 | 0 |
| 68 | 1 | 0 |
| 69 | 1 | 0 |
| 70 | 1 | 0 |
| 71 | 1 | 0 |
| C-1 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-10-26 | |
|---|---|---|
| Proposed completion | 2023-10-26 | |
| Revised completion | 2027-07-31 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2024-Q2 | 2024-07-31 | 40 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | REMARK CHEMICALS LLP | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | AU Small Finance Bank | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=3IlQPmjmnYXzmbsvY1KPag
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/3IlQPmjmnYXzmbsvY1KPag
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=3IlQPmjmnYXzmbsvY1KPag%3D%3D&QuarterIdEnc=RXQtwfTEmtE0gcDePQWEOA%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=0IQ5LZHzHAA%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan · 2023-10-23
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- SitePlanPath · 2023-10-23
- LayoutPlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- SitePlanPath · 2023-10-23
- Site_Plan_Doc_Sanctioned
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2024-07-29 · Sign in to download
- R2_UploadDoc · 2024-07-30 · Sign in to download
- R3_UploadedPath · 2024-07-31 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download