Overview
KIRAN SERINITY
NEWARK CONSTRUCTIONS · AT ROAD
Units54
Completion2030-10-31Proposed
Registered on2026-05-06
Valid to2031-05-05
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 10 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 28 documents · 5 source links |
Registration
Registration
| Promoter | NEWARK CONSTRUCTIONS | |
|---|---|---|
| District | JORHAT | |
| Locality | AT ROAD | |
| Regulator | RERA Assam | |
| Registration number | RERAA JO 210 OF 2026-2027 | |
| Registered on | 2026-05-06 | |
| Valid to | 2031-05-05 | |
| Status (as filed) | Ongoing Projects | |
| Proposed completion | 2030-10-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Layout Plan | ||
| Building Plan | ||
| NOC/Building Permit | Jorhat Municipal Board JMB/Bldg.Per/Ward No.12 12025/194 dtd. 4-03-2025 | 2025-03-04 |
| I. JORHAT MUNICIPAL BOARD NOC NO. MB/BLDG.PER/WARD NO/12/2025/194 | 2025-03-04 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 | |
|---|---|---|
| Construction | ₹14,82,22,000 | |
| Total | ₹19,67,98,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,786 | |
|---|---|---|
| Units | 54 |
Unit types
| 2 | 76.4 | 6 |
| 2 | 88.3 | 6 |
| 4 | 107 | 7 |
| 3 | 90.3 | 12 |
| 3 | 80.5 | 5 |
| 3 | 91.7 | 3 |
| 2 | 66 | 3 |
| 3 | 78.5 | 3 |
| 3 | 85.1 | 3 |
| 2 | 76.2 | 6 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-11-01 | |
|---|---|---|
| Proposed completion | 2030-10-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | NEWARK CONSTRUCTIONS | |
|---|---|---|
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.assam.gov.in/admincontrol/custom_search
- https://rera.assam.gov.in/admincontrol/registered_projects/1
- https://rera.assam.gov.in/assistancecontrol/project_search_public/1
- https://rera.assam.gov.in/view_project/project_preview_open/2457
- https://rera.assam.gov.in/view_project/searchprojectDetail/2457
- Registration Certificate
- NO OBJECTION CERTIFICATE FROM THE COMPETENT AUTHORITY · 2025-09-13 · Sign in to download
- LOCATIONAL MAP INCLUDING LATITUDE AND LONGITUDE · 2025-09-13 · Sign in to download
- ARCHITECT, STRUCTURAL ENGINEER AND CONTRACTOR DETAILS WITH NAME AND ADDRESS AS THE CASE MAY BE · 2025-09-13 · Sign in to download
- HEIGHT CLEARANCE FROM AIRPORT AUTHORITY OF INDIA · 2025-09-14
- FIRE NOC · 2025-09-14
- PLANNING PERMIT FROM COMPETENT AUTHORITY · 2025-09-14
- CARPET AREA AND PARKING AREA DETAILS · 2025-09-15 · Sign in to download
- COMMENCEMENT CERTIFICATE OF THE PROJECT · 2025-09-25 · Sign in to download
- PROJECT COST ESTIMATE · 2025-09-25 · Sign in to download
- APPROVED DRAWING FROM COMPETENT AUTHORITY · 2025-09-25 · Sign in to download
- LETTER OF AUTHORIZATION FOR AUTHORIZED SIGNATORY · 2025-09-14 · Sign in to download
- REGISTRATION CERTIFICATE OF THE ENTITY · 2025-09-14
- Other · 2025-09-14 · Sign in to download
- Other · 2025-09-14 · Sign in to download
- AUDITED BALANCE SHEET OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2025-09-14 · Sign in to download
- INCOME TAX RETURN OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2025-09-14 · Sign in to download
- BANK MANAGER'S LETTER MENTIONING THAT THE ACCOUNT HAS BEEN OPENED IN COMPLIANCE WITH THE SECTION 4(2)(L)(D) OF REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016 · 2025-09-14 · Sign in to download
- CASHFLOW STATEMENT · 2025-09-25 · Sign in to download
- POWER OF ATTORNEY · 2025-09-14 · Sign in to download
- LATEST NON ENCUMBRANCE CERTIFICATE · 2025-09-14 · Sign in to download
- TRACE MAP SHOWING NEARBY BY STREAMS, PONDS ETC. · 2025-09-14 · Sign in to download
- POWER OF ATTORNEY -2 · 2025-09-14 · Sign in to download
- APPROVED PLAN-2 · 2025-09-25
- APPROVED PLAN-2 · 2025-09-25
- APPROVED PLAN-3 · 2025-09-25
- FORM B, DULY NOTARIZED · 2025-09-14 · Sign in to download