Overview
Knowledge Based IT Park.
Malhotra Developers and Colonisers · Ludhiana
Units121
Completion2023-09-15Proposed
Valid to2022-07-29
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 2 unit types |
| Construction & progress | 2 progress details · 35 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 14 documents · 40 source links |
Registration
Registration
| Promoter | Malhotra Developers and Colonisers | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH44-PI0001 | |
| Valid to | 2022-07-29 | |
| Project type | (1) Industrial (Building/Tower Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2023-09-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Date |
|---|---|
| CLU Certificate | |
| License to develop colony or society from Competent Authority | |
| Other Document (License) | 2009-10-14 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹10,72,05,356 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 93,846.6 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 121 | |
| Units | 121 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| IT TOWERS | 8,625 | 2 | KNOWLEDGE BASED IT PARK |
| INDUSTRIAL PLOTS | 500 | 119 | KNOWLEDGE BASED IT PARK |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2010-04-19 | |
|---|---|---|
| Proposed completion | 2023-09-15 |
Quarterly progress
| 2018-Q1 | 2021-03-22 |
| 2018-Q2 | 2021-03-22 |
| 2018-Q3 | 2021-03-22 |
| 2018-Q4 | 2021-03-22 |
| 2019-Q1 | 2021-03-22 |
| 2019-Q2 | 2021-03-22 |
| 2019-Q3 | 2021-03-22 |
| 2019-Q4 | 2021-03-22 |
| 2020-Q1 | 2021-03-22 |
| 2020-Q2 | 2021-03-22 |
| 2020-Q3 | 2021-03-22 |
| 2020-Q4 | 2021-03-22 |
| 2021-Q1 | 2023-03-03 |
| 2021-Q2 | 2023-03-03 |
| 2021-Q3 | 2023-03-03 |
| 2021-Q4 | 2023-03-03 |
| 2022-Q1 | 2023-03-03 |
| 2022-Q2 | 2023-03-03 |
| 2022-Q3 | 2023-03-03 |
| 2022-Q4 | 2023-03-03 |
| 2023-Q1 | 2023-06-14 |
| 2023-Q2 | 2023-10-09 |
| 2023-Q3 | 2023-10-09 |
| 2023-Q4 | 2024-01-29 |
| 2024-Q1 | 2024-05-24 |
| 2024-Q2 | 2024-08-28 |
| 2024-Q3 | 2025-01-04 |
| 2024-Q4 | 2025-02-03 |
| 2025-Q1 | 2025-04-18 |
| 2025-Q2 | 2025-07-04 |
| 2025-Q3 | 2025-10-13 |
| 2025-Q4 | 2026-02-09 |
| 2026-Q1 | 2026-04-15 |
| 2026-Q2 | 2026-07-09 |
| 2026-Q3 | 2026-10-10 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Malhotra Developers and Colonisers | |
|---|---|---|
| Type | Company | |
| Escrow bank | Allahabad Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10515&inPromoter_ID=1421&inPromoterType=2
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- License to develop colony or society from Competent Authority
- Other Document (Letter Of Intent) · 2008-02-15 · Sign in to download
- Other Document (License) · 2009-10-14
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- License to develop colony or society from Competent Authority
- Other Document (License) · 2009-10-14
- 2018-Q1 · 2021-03-22
- 2018-Q2 · 2021-03-22
- 2018-Q3 · 2021-03-22
- 2018-Q4 · 2021-03-22
- 2019-Q1 · 2021-03-22
- 2019-Q2 · 2021-03-22
- 2019-Q3 · 2021-03-22
- 2019-Q4 · 2021-03-22
- 2020-Q1 · 2021-03-22
- 2020-Q2 · 2021-03-22
- 2020-Q3 · 2021-03-22
- 2020-Q4 · 2021-03-22
- 2021-Q1 · 2023-03-03
- 2021-Q2 · 2023-03-03
- 2021-Q3 · 2023-03-03
- 2021-Q4 · 2023-03-03
- 2022-Q1 · 2023-03-03
- 2022-Q2 · 2023-03-03
- 2022-Q3 · 2023-03-03
- 2022-Q4 · 2023-03-03
- 2023-Q1 · 2023-06-14
- 2023-Q2 · 2023-10-09
- 2023-Q3 · 2023-10-09
- 2023-Q4 · 2024-01-29
- 2024-Q1 · 2024-05-24
- 2024-Q2 · 2024-08-28
- 2024-Q3 · 2025-01-04
- 2024-Q4 · 2025-02-03
- 2025-Q1 · 2025-04-18
- 2025-Q2 · 2025-07-04
- 2025-Q3 · 2025-10-13
- 2025-Q4 · 2026-02-09
- 2026-Q1 · 2026-04-15
- 2026-Q2 · 2026-07-09
- 2026-Q3 · 2026-10-10