Title & ownership
Approvals
| Building plan (BMICAPA) | Sanctioned 18 Apr 2026 · No. BMICAPA/PLAN-01/53/2025-26 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| SEIAA | Filed with the registration |
Disputes & cases
Contract & costs
Valuation
We haven't verified this for this project yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan (BMICAPA) | Sanctioned 18 Apr 2026 | |
| Escrow bank | HDFC · RICHMOND ROAD, BENGALURU |
Data room
93 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. The 1 filed survey number matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 14 Nov 2026. The drawn plot is a whole survey number, not the project's own share of it; it shows where the land is, not the site.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| Aaradhya GardensRegistered · no quarterly update yet | SAI SAMRUDHI CONSTRUCTIONS | Apartment | 992 sqft carpet (as filed) | Dec 2028 |
| Aashirvad Siddhi PriyaFiled as completed · no completion certificate on record | SEENAPPA P | Plot | ~600–1,240 sqft (estimate: filed carpet plus 25%) | Nov 2024 |
| Aashirvad's Panchamukhi ShreyodhamaCompleted (regulator flag) | RAJESHWARI AASHIRVAD INFRA PROJECTS PRIVATE LIMITED | Plot | ~1,650 sqft (estimate: filed carpet plus 25%) | Completed |
| Aditya OrchardLapsed · completion date passed | Mangala Raghavan | Plot | ~1,200–1,800 sqft (estimate: filed carpet plus 25%) | May 2024 |
| Aprameya Brindavanam EliteCompleted (regulator flag) | Aprameya Properties Pvt Ltd | Plot | – | Completed |
| Ashwasurya Atharva RitewayCompleted (regulator flag) | RITEWAY & KUBERA PROMOTERS | Plot | ~1,200–2,400 sqft (estimate: filed carpet plus 25%) | Completed |
| Axis Banyan CountyCompleted (regulator flag) | R.Harish babu | Plot | – | Completed |
| Birla Apple SpireLapsed · completion date passed | Apple spire India LLP | Apartment | 1,667 sqft carpet (as filed) | Sep 2019 |
8 of 121 other projects in Mysore Road, A to Z. Status is taken from each project's own filing.
All 126 projects in Mysore Road → · KNS Infrastructure Private Limited's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Kns Aadrika Phase III in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| KSPCB | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 22 May 2031 |
| Land conversion | Converted 5 Dec 2025 · Deputy Comissioner, Bengaluru Urban District. | |
|---|---|---|
| Survey numbers | 10/1 |
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 11.5 km, Kengeri Yellamma temple | |
|---|---|---|
| Government land in the filed surveys | Not found |
| Nearest storm drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed tank |
As the promoter reported itPossession date in the agreement
| Internal roads | 5% | |
|---|---|---|
| Completion | 16% |
| Possession, agreement | 3 Jun 2031 | |
|---|---|---|
| RERA completion date | 22 May 2031 | |
| Work began, as filed | 18 May 2026 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Structural engineer, quarterly | Form 6 · Jul 2026, Oct 2026 (2 filed) | Clear |
|---|---|---|
| Chartered accountant's certificate, registration | Dated 1 Jun 2026 | |
| Chartered accountant, Form 4 | Dated 13 Oct 2026 |
Land · ₹4.50 Cr 57.9%Development · ₹3.27 Cr 42.1%
| Estimated cost, at registration | ₹7.77 Cr | |
|---|---|---|
| Estimated cost, engineer's certificate | ₹9.94 Cr | |
| Estimated cost, chartered accountant's certificate | ₹34.27 Cr | |
| Cost incurred | ₹5.48 Cr | |
| Cost left | ₹2.29 Cr |
| Plots booked, Form 4 Q2 2026-27 | 22 |
|---|
| Escrow bank | HDFC · RICHMOND ROAD, BENGALURU | |
|---|---|---|
| Designated account, collected | ₹62.8 L in Q2 2026-27 | |
| Designated account, withdrawn | ₹0 in Q2 2026-27 (0% of that quarter's deposits) | |
| Sale proceeds realised, Q2 2026-27 | ₹62,81,020 |
| K-RERA registrations under this promoter | 20 | |
|---|---|---|
| Marked completed | 14 | |
| Past promised date, not completed | 3 | |
| Other phases under this promoter name | 16 | |
| With a filed extension or completion | 13 (13 completed, 0 extended) | |
| Average schedule slip | 26 months |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 23.2 m
Taluk average; not a reading at the site.
| Groundwater | Bengaluru South taluk average, July 2023: 16.9 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 10 CGWB wells in Bengaluru South taluk read in this class | |
| Through the year | January 2025: 2.2 m (5 wells), Pre-monsoon 2025: 1.9 m (10 wells), August 2025: 1.5 m (11 wells), depth below ground of CGWB's monitoring wells in Bengaluru South taluk (the median where there are several) | |
| Water supply, as filed | Local authority (Chikkanahalli Grama Panchyathi) |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 9.5 km, Challaghatta | |
| Metro, under construction | about 23.5 km, Kalena Agrahara |
| Kempegowda Airport | 65.5 | 50.5 |
| MG Road (CBD) | 32.5 | 26.5 |
| Manyata Tech Park | 43 | 32.5 |
| ITPL, Whitefield | 49.5 | 41 |
| Ecospace, Bellandur ORR | 46.5 | 33 |
| Electronic City Ph 1 | 43 | 32.5 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | about 0.5 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | None within 3 km |