Overview
KONARK GIRIRAJ
KONARK BUILDER · SURGUJA
Units25
Booked17 of 25As of 2022-09-30
Construction progress100%As of 2022-09-30
Completion2023-09-29Revised · Proposed 2021-03-31
Registered on2018-06-07
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 2 cost heads · 17 quarters |
| Technical report | |
| Site & area | 3 site details · 4 unit types |
| Construction & progress | 4 progress details · 17 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 102 documents · 4 source links |
Registration
Registration
| Promoter | KONARK BUILDER | |
|---|---|---|
| District | SURGUJA | |
| Regulator | CG RERA | |
| Registration number | PCGRERA070618000076 | |
| Registered on | 2018-06-07 | |
| Project type | Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2021-03-31 | |
| Revised completion | 2023-09-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,38,31,782 | |
|---|---|---|
| Construction | ₹5,60,77,134 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹0 |
| 2019-Q1 | ₹27,82,252 |
| 2019-Q2 | ₹19,42,234.5 |
| 2019-Q3 | ₹20,23,778 |
| 2019-Q4 | ₹5,760.5 |
| 2020-Q1 | ₹5,742.5 |
| 2020-Q2 | ₹5,724 |
| 2020-Q3 | ₹5,106 |
| 2020-Q4 | ₹5,088 |
| 2021-Q1 | ₹5,073.5 |
| 2021-Q2 | ₹8,05,058.5 |
| 2021-Q3 | ₹33,70,043.5 |
| 2021-Q4 | ₹3,22,028.5 |
| 2022-Q1 | ₹7,013 |
| 2022-Q2 | ₹5,86,998.5 |
| 2022-Q3 | ₹26,31,983.5 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 25 | |
|---|---|---|
| Booked | 17 | |
| Booked as of | 2022-09-30 |
Unit types
| 4BHK | 136 | 17 | 12 |
| 4BHK | 100 | 3 | 2 |
| 3BHK | 27 | 3 | 2 |
| 2BHK | 20 | 2 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2022-09-30 | |
| Proposed completion | 2021-03-31 | |
| Revised completion | 2023-09-29 |
Quarterly progress
| 2018-Q3 | 0% |
| 2018-Q4 | 10% |
| 2019-Q1 | 10% |
| 2019-Q2 | 25% |
| 2019-Q3 | 30% |
| 2019-Q4 | 21% |
| 2020-Q1 | 33% |
| 2020-Q2 | 28% |
| 2020-Q3 | 23% |
| 2020-Q4 | 35% |
| 2021-Q1 | 35% |
| 2021-Q2 | 36% |
| 2021-Q3 | 51% |
| 2021-Q4 | 52% |
| 2022-Q1 | 100% |
| 2022-Q2 | 100% |
| 2022-Q3 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | KONARK BUILDER | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Chhattisgarh Rajya Gramin Bank | |
| Other projects in this city pack | 7 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=NjQ=
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Approval Letter of Town And Country Planning