Overview
KRISHNA KUNJ ENCLAVE
RAMESTH INFRASTRUCTURE PVT. LTD. · Patna
Units28
Completion2022-04-15Proposed
Registered on2019-06-13
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 6 unit types |
| Construction & progress | 2 progress details · 14 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 25 documents · 20 source links |
Registration
Registration
| Promoter | RAMESTH INFRASTRUCTURE PVT. LTD. | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP92143-1/980/R-662/2019 | |
| Registered on | 2019-06-13 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2022-04-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹6,67,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,753.43 | |
|---|---|---|
| Built-up (m²) | 2,663.03 | |
| FAR | 1.65 | |
| Towers | 3 | |
| Units | 28 |
Unit types
| 2 BHK | 4 | KRISHNA KUNJ ENCLAVE |
| 2 BHK | 4 | KRISHNA KUNJ ENCLAVE |
| 2 BHK | 4 | KRISHNA KUNJ ENCLAVE |
| 2 BHK | 4 | KRISHNA KUNJ ENCLAVE |
| 3 BHK | 8 | KRISHNA KUNJ ENCLAVE |
| Convenience Store | 4 | KRISHNA KUNJ ENCLAVE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-04-16 | |
|---|---|---|
| Proposed completion | 2022-04-15 |
Quarterly progress
| 2022-Q4 | 2023-03-25 |
| 2022-Q3 | 2022-10-13 |
| 2022-Q2 | 2022-09-06 |
| 2022-Q1 | 2022-04-15 |
| 2021-Q4 | 2022-02-08 |
| 2021-Q3 | 2021-10-19 |
| 2021-Q2 | 2021-07-20 |
| 2021-Q1 | 2021-04-20 |
| 2020-Q4 | 2021-01-22 |
| 2020-Q3 | 2020-10-09 |
| 2020-Q2 | 2020-10-09 |
| 2020-Q1 | 2020-04-15 |
| 2019-Q4 | 2020-01-16 |
| 2019-Q3 | 2019-09-12 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RAMESTH INFRASTRUCTURE PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP04102019192143-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP04102019192143-1
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q3-Oct to Dec / 2022-2023 · 2023-03-25
- Q2-Jul to Sep / 2022-2023 · 2022-10-13
- Q1-Apr to Jun / 2022-2023 · 2022-09-06
- Q4-Jan to Mar / 2021-2022 · 2022-04-15
- Q3-Oct to Dec / 2021-2022 · 2022-02-08
- Q2-Jul to Sep / 2021-2022 · 2021-10-19
- Q1-Apr to Jun / 2021-2022 · 2021-07-20
- Q4-Jan to Mar / 2020-2021 · 2021-04-20
- Q3-Oct to Dec / 2020-2021 · 2021-01-22
- Q2-Jul to Sep / 2020-2021 · 2020-10-09
- Q1-Apr to Jun / 2020-2021 · 2020-10-09
- Q4-Jan to Mar / 2019-2020 · 2020-04-15
- Q3-Oct to Dec / 2019-2020 · 2020-01-16
- Q2-Jul to Sep / 2019-2020 · 2019-09-12
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- 2022-Q4 · 2023-03-25
- 2022-Q3 · 2022-10-13
- 2022-Q2 · 2022-09-06
- 2022-Q1 · 2022-04-15
- 2021-Q4 · 2022-02-08
- 2021-Q3 · 2021-10-19
- 2021-Q2 · 2021-07-20
- 2021-Q1 · 2021-04-20
- 2020-Q4 · 2021-01-22
- 2020-Q3 · 2020-10-09
- 2020-Q2 · 2020-10-09
- 2020-Q1 · 2020-04-15
- 2019-Q4 · 2020-01-16
- 2019-Q3 · 2019-09-12