Overview
KRISHNA VIHAR
BHOOMI COLONIZERS AND DEVELOPERS · DURG
Units72
Booked19 of 72As of 2026-06-30
Construction progress67%As of 2026-06-30
Completion2028-06-01Revised · Proposed 2028-02-01
Registered on2023-04-11
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 2 cost heads · 13 quarters |
| Technical report | |
| Site & area | 3 site details · 72 unit types |
| Construction & progress | 4 progress details · 13 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 88 documents · 6 source links |
Registration
Registration
| Promoter | BHOOMI COLONIZERS AND DEVELOPERS | |
|---|---|---|
| District | DURG | |
| Regulator | CG RERA | |
| Registration number | PCGRERA110423001625 | |
| Registered on | 2023-04-11 | |
| Project type | Mixed Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2028-02-01 | |
| Revised completion | 2028-06-01 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,60,19,000 | |
|---|---|---|
| Construction | ₹5,21,95,000 |
Quarterly money flows
| 2023-Q2 | ₹0 |
| 2023-Q3 | ₹2,79,485 |
| 2023-Q4 | ₹2,78,970 |
| 2024-Q1 | ₹2,78,455 |
| 2024-Q2 | ₹31,21,855 |
| 2024-Q3 | ₹6,63,855 |
| 2024-Q4 | ₹6,63,855 |
| 2025-Q1 | ₹20,98,316 |
| 2025-Q2 | ₹26.89 |
| 2025-Q3 | ₹15.82 |
| 2025-Q4 | ₹28,15,233 |
| 2026-Q1 | ₹10,85,229.85 |
| 2026-Q2 | ₹43,429.85 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 72 | |
|---|---|---|
| Booked | 19 | |
| Booked as of | 2026-06-30 |
Unit types
| GENERAL-1 | 1 | 0 |
| GENERAL-2 | 1 | 0 |
| GENERAL-3 | 1 | 0 |
| GENERAL-4 | 1 | 0 |
| GENERAL-5 | 1 | 1 |
| GENERAL-6 | 1 | 1 |
| GENERAL-7 | 1 | 0 |
| GENERAL-8 | 1 | 1 |
| GENERAL-9 | 1 | 0 |
| GENERAL-10 | 1 | 0 |
| GENERAL-11 | 1 | 0 |
| GENERAL-12 | 1 | 0 |
| GENERAL-13 | 1 | 0 |
| GENERAL-14 | 1 | 0 |
| GENERAL-15 | 1 | 0 |
| GENERAL-16 | 1 | 0 |
| GENERAL-17 | 1 | 0 |
| GENERAL-18 | 1 | 0 |
| GENERAL-19 | 1 | 0 |
| GENERAL-20 | 1 | 0 |
| GENERAL-21 | 1 | 0 |
| GENERAL-22 | 1 | 0 |
| GENERAL-23 | 1 | 1 |
| GENERAL-24 | 1 | 1 |
| GENERAL-25 | 1 | 1 |
| GENERAL-26 | 1 | 1 |
| GENERAL-27 | 1 | 1 |
| GENERAL-28 | 1 | 1 |
| GENERAL-29 | 1 | 1 |
| GENERAL-30 | 1 | 0 |
| GENERAL-31 | 1 | 1 |
| GENERAL-32 | 1 | 1 |
| GENERAL-33 | 1 | 1 |
| GENERAL-34 | 1 | 1 |
| GENERAL-35 | 1 | 1 |
| GENERAL-36 | 1 | 0 |
| GENERAL-37 | 1 | 0 |
| GENERAL-38 | 1 | 0 |
| GENERAL-39 | 1 | 0 |
| GENERAL-40 | 1 | 0 |
| GENERAL-41 | 1 | 0 |
| GENERAL-42 | 1 | 0 |
| GENERAL-43 | 1 | 0 |
| LIG-44 | 1 | 0 |
| LIG-45 | 1 | 0 |
| LIG-46 | 1 | 0 |
| LIG-47 | 1 | 0 |
| LIG-48 | 1 | 0 |
| LIG-49 | 1 | 0 |
| LIG-50 | 1 | 0 |
| LIG-51 | 1 | 0 |
| GENERAL-52 | 1 | 0 |
| GENERAL-53 | 1 | 0 |
| GENERAL-54 | 1 | 1 |
| GENERAL-55 | 1 | 1 |
| GENERAL-56 | 1 | 0 |
| GENERAL-57 | 1 | 0 |
| GENERAL-58 | 1 | 0 |
| GENERAL-59 | 1 | 0 |
| GENERAL-60 | 1 | 0 |
| GENERAL-61 | 1 | 0 |
| GENERAL-62 | 1 | 0 |
| GENERAL-63 | 1 | 0 |
| GENERAL-64 | 1 | 0 |
| GENERAL-65 | 1 | 1 |
| GENERAL-66 | 1 | 0 |
| GENERAL-67 | 1 | 1 |
| GENERAL-68 | 1 | 0 |
| GENERAL-69 | 1 | 0 |
| GENERAL-70 | 1 | 0 |
| GENERAL-71 | 1 | 0 |
| GENERAL-72 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 67% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2028-02-01 | |
| Revised completion | 2028-06-01 |
Quarterly progress
| 2023-Q2 | 0% |
| 2023-Q3 | 0% |
| 2023-Q4 | 0% |
| 2024-Q1 | 15% |
| 2024-Q2 | 22% |
| 2024-Q3 | 43% |
| 2024-Q4 | 46% |
| 2025-Q1 | 48% |
| 2025-Q2 | 52% |
| 2025-Q3 | 52% |
| 2025-Q4 | 67% |
| 2026-Q1 | 67% |
| 2026-Q2 | 67% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BHOOMI COLONIZERS AND DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTk4NQ==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities