Overview
KRISHNA VILLAS
Shreshth Realtechnologies Private Limited · Village Siroli
Units20
Booked17 of 20As of 2025-09-30
Completion2025-02-15Revised · Proposed 2023-02-15
Registered on2023-02-25
Valid to2026-02-13
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 13 unit types |
| Construction & progress | 3 progress details · 1 quarter · 2 extensions |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 38 documents · 8 source links |
Registration
Registration
| Promoter | Shreshth Realtechnologies Private Limited | |
|---|---|---|
| District | Jaipur | |
| Locality | Village Siroli | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2023/2408 | |
| Registered on | 2023-02-25 | |
| Valid to | 2026-02-13 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2023-02-15 | |
| Revised completion | 2025-02-15 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,90,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹2,40,00,000 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2025-Q3 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,977.88 | |
|---|---|---|
| Built-up (m²) | 2,486.76 | |
| Towers | 20 | |
| Units | 20 | |
| Booked | 17 | |
| Booked as of | 2025-09-30 |
Unit types
| Plot No. 1-8 | 8 | 0 |
| Plot No. 9 | 1 | 0 |
| Plot no. 10 | 1 | 0 |
| Plot No. 11 | 1 | 0 |
| Plot No. 12 | 1 | 0 |
| Plot No. 13 | 1 | 0 |
| Plot No. 14 | 1 | 0 |
| Plot No. 15 | 1 | 0 |
| Plot No. 16 | 1 | 0 |
| Plot No. 17 | 1 | 0 |
| Plot No. 18 | 1 | 0 |
| Plot No. 19 | 1 | 0 |
| Plot No. 20 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-02-15 | |
|---|---|---|
| Proposed completion | 2023-02-15 | |
| Revised completion | 2025-02-15 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2025-Q3 | 2025-11-11 | 17 |
Extensions
| Valid to |
|---|
| 2026-02-13 |
| 2025-07-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Shreshth Realtechnologies Private Limited | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | HDFC Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=bf3lf9nGV2vkjDZtFAmHKQ
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/bf3lf9nGV2vkjDZtFAmHKQ
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=bf3lf9nGV2vkjDZtFAmHKQ%3D%3D&QuarterIdEnc=s291bsdE%2FxcYMFPaLLqdrQ%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=xi2MYaFOEOs%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan · 2023-02-03
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- FormFUploadedPathString · Sign in to download
- FormFUploadedPathString · Sign in to download
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- SitePlanPath · 2023-02-03
- LayoutPlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- SitePlanPath · 2023-02-03
- Site_Plan_Doc_Sanctioned
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2025-10-08 · Sign in to download
- R2_UploadDoc · 2025-10-09 · Sign in to download
- R3_UploadedPath · 2025-11-07 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download
- Extension order · Sign in to download
- Extension order · Sign in to download