Overview
KUNJ VIHAR
ALPANA · Sirmaur
Units60
Registered on2025-12-30
Valid to2029-08-30
Approvals6
Complaints0As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Disputes & cases | 0 project complaints |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 60 unit types |
| Construction & progress | 4 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 30 documents · 22 source links |
Registration
Registration
| Promoter | ALPANA | |
|---|---|---|
| District | Sirmaur | |
| Regulator | Himachal Pradesh Real Estate Regulatory Authority | |
| Registration number | HPRERASIR2025175/P | |
| Registered on | 2025-12-30 | |
| Valid to | 2029-08-30 | |
| Project type | Plotted (Residential) | |
| Status (as filed) | New Project Launch |
Approvals
Is it approved for its use?
Approvals
Approvals
| Plan sanction | 1368 (P) | Special Area Development Authority (SADA) |
| NOC/Consent to Operate from Pollution Control Board | ||
| Sanctioned Letter by TCP/ULB(s)/Local Authority * | ||
| Sanctioned Location Plan * | ||
| Sanctioned Site Plan * | ||
| Sanctioned Building Plan * |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,25,77,000 | |
|---|---|---|
| Construction | ₹1,84,47,000 | |
| Total | ₹4,10,24,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 16,196.12 | |
|---|---|---|
| Units | 60 |
Unit types
| 1 | 1 | SEMI DETACHED |
| 2 | 1 | ROW HOUSE |
| 3 | 1 | SEMI DETACHED |
| 4 | 1 | SEMI DETACHED |
| 5 | 1 | SEMI DETACHED |
| 6 | 1 | SEMI DETACHED |
| 7 | 1 | SEMI DETACHED |
| 8 | 1 | SEMI DETACHED |
| 9 | 1 | SEMI DETACHED |
| 10 | 1 | ROW HOUSE |
| 11 | 1 | SEMI DETACHED |
| 12 | 1 | SEMI DETACHED |
| 13 | 1 | SEMI DETACHED |
| 14 | 1 | SEMI DETACHED |
| 15 | 1 | SEMI DETACHED |
| 16 | 1 | SEMI DETACHED |
| 17 | 1 | SEMI DETACHED |
| 18 | 1 | SEMI DETACHED |
| 19 | 1 | SEMI DETACHED |
| 20 | 1 | SEMI DETACHED |
| 21 | 1 | SEMI DETACHED |
| 22 | 1 | SEMI DETACHED |
| 23 | 1 | SEMI DETACHED |
| 24 | 1 | SEMI DETACHED |
| 25 | 1 | SEMI DETACHED |
| 26 | 1 | SEMI DETACHED |
| 27 | 1 | SEMI DETACHED |
| 28 | 1 | SEMI DETACHED |
| 29 | 1 | SEMI DETACHED |
| 30 | 1 | DETACHED |
| 31 | 1 | ROW HOUSE |
| 32 | 1 | SEMI DETACHED |
| 33 | 1 | SEMI DETACHED |
| 34 | 1 | SEMI DETACHED |
| 35 | 1 | SEMI DETACHED |
| 36 | 1 | SEMI DETACHED |
| 37 | 1 | SEMI DETACHED |
| 38 | 1 | SEMI DETACHED |
| 39 | 1 | SEMI DETACHED |
| 40 | 1 | SEMI DETACHED |
| 41 | 1 | SEMI DETACHED |
| 42 | 1 | ROW SHOP |
| 43 | 1 | ROW SHOP |
| 44 | 1 | ROW SHOP |
| 45 | 1 | ROW SHOP |
| 46 | 1 | ROW SHOP |
| 47 | 1 | SEMI DETACHED |
| 48 | 1 | SEMI DETACHED |
| 49 | 1 | SEMI DETACHED |
| 50 | 1 | SEMI DETACHED |
| 51 | 1 | SEMI DETACHED |
| 52 | 1 | SEMI DETACHED |
| 53 | 1 | SEMI DETACHED |
| 54 | 1 | DETACHED |
| 55 | 1 | SEMI DETACHED |
| 56 | 1 | ROW HOUSE |
| 57 | 1 | SEMI DETACHED |
| 58 | 1 | SEMI DETACHED |
| 59 | 1 | PUBLIC AND SEMI PUBLIC |
| 60 | 1 | PUBLIC AND SEMI PUBLIC |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Quarterly progress
| Quarter |
|---|
| 2025-Q4 |
| 2026-Q1 |
| 2026-Q2 |
| 2026-Q3 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ALPANA | |
|---|---|---|
| Type | Individual | |
| Escrow bank | State Bank of India | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://hprera.nic.in/Complaints/Litigation/Litigation_PreviewPV?qs=f3fIU7vFXK2V506PrdNaRdx6Hzz%2FtJlyNponNspPZxRlyiLzSEmmYhcpNg6VOVQYrto4OTBdBTJYYh6%2FZSKLWmVDZTObuAezNSn6VWsk3duViuDUQy1lJA%3D%3D
- https://hprera.nic.in/Home/PRGrid
- https://hprera.nic.in/Home/ProjectsQPR?FnYr=2025-26
- https://hprera.nic.in/Home/ProjectsQPR?FnYr=2026-27
- https://hprera.nic.in/Project/ProjectRegistration/AssociatedVendors_PreviewPV?qs=f3fIU7vFXK2V506PrdNaRdx6Hzz%2FtJlyNponNspPZxRlyiLzSEmmYhcpNg6VOVQYrto4OTBdBTJYYh6%2FZSKLWmVDZTObuAezNSn6VWsk3duViuDUQy1lJA%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/BankDetails_PreviewPV?qs=f3fIU7vFXK2V506PrdNaRdx6Hzz%2FtJlyNponNspPZxRlyiLzSEmmYhcpNg6VOVQYrto4OTBdBTJYYh6%2FZSKLWmVDZTObuAezNSn6VWsk3duViuDUQy1lJA%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/Documents_PreviewPV?qs=f3fIU7vFXK2V506PrdNaRdx6Hzz%2FtJlyNponNspPZxRlyiLzSEmmYhcpNg6VOVQYrto4OTBdBTJYYh6%2FZSKLWmVDZTObuAezNSn6VWsk3duViuDUQy1lJA%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/InventoryDetails_PreviewPV?qs=f3fIU7vFXK2V506PrdNaRdx6Hzz%2FtJlyNponNspPZxRlyiLzSEmmYhcpNg6VOVQYrto4OTBdBTJYYh6%2FZSKLWmVDZTObuAezNSn6VWsk3duViuDUQy1lJA%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/PastProjectDetails_PreviewPV?qs=f3fIU7vFXK2V506PrdNaRdx6Hzz%2FtJlyNponNspPZxRlyiLzSEmmYhcpNg6VOVQYrto4OTBdBTJYYh6%2FZSKLWmVDZTObuAezNSn6VWsk3duViuDUQy1lJA%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/Payment_PreviewPV?qs=f3fIU7vFXK2V506PrdNaRdx6Hzz%2FtJlyNponNspPZxRlyiLzSEmmYhcpNg6VOVQYrto4OTBdBTJYYh6%2FZSKLWmVDZTObuAezNSn6VWsk3duViuDUQy1lJA%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/ProjectDetails_PreviewPV?qs=f3fIU7vFXK2V506PrdNaRdx6Hzz%2FtJlyNponNspPZxRlyiLzSEmmYhcpNg6VOVQYrto4OTBdBTJYYh6%2FZSKLWmVDZTObuAezNSn6VWsk3duViuDUQy1lJA%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/PromotorDetails_PreviewPV?qs=f3fIU7vFXK2V506PrdNaRdx6Hzz%2FtJlyNponNspPZxRlyiLzSEmmYhcpNg6VOVQYrto4OTBdBTJYYh6%2FZSKLWmVDZTObuAezNSn6VWsk3duViuDUQy1lJA%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/PublicDashboard/GetFilteredProjectsPV?DistrictList%5B0%5D.Selected=false&DistrictList%5B0%5D.Value=18&DistrictList%5B1%5D.Selected=false&DistrictList%5B1%5D.Value=24&DistrictList%5B2%5D.Selected=false&DistrictList%5B2%5D.Value=20&DistrictList%5B3%5D.Selected=false&DistrictList%5B3%5D.Value=23&DistrictList%5B4%5D.Selected=false&DistrictList%5B4%5D.Value=25&DistrictList%5B5%5D.Selected=false&DistrictList%5B5%5D.Value=22&DistrictList%5B6%5D.Selected=false&DistrictList%5B6%5D.Value=26&DistrictList%5B7%5D.Selected=false&DistrictList%5B7%5D.Value=21&DistrictList%5B8%5D.Selected=false&DistrictList%5B8%5D.Value=15&DistrictList%5B9%5D.Selected=false&DistrictList%5B9%5D.Value=17&DistrictList%5B10%5D.Selected=false&DistrictList%5B10%5D.Value=16&DistrictList%5B11%5D.Selected=false&DistrictList%5B11%5D.Value=19&PlottedTypeList%5B0%5D.Selected=false&PlottedTypeList%5B0%5D.Value=P&PlottedTypeList%5B1%5D.Selected=false&PlottedTypeList%5B1%5D.Value=F&PlottedTypeList%5B2%5D.Selected=false&PlottedTypeList%5B2%5D.Value=M&ResidentialTypeList%5B0%5D.Selected=false&ResidentialTypeList%5B0%5D.Value=R&ResidentialTypeList%5B1%5D.Selected=false&ResidentialTypeList%5B1%5D.Value=C&ResidentialTypeList%5B2%5D.Selected=false&ResidentialTypeList%5B2%5D.Value=M&AreaFrom=&AreaUpto=&SearchText=
- Past Project Details document · Sign in to download
- Income Tax Return (ITR) Acknowledgement * · 2025-12-06 · Sign in to download
- Income Tax Return (ITR) Acknowledgement * · 2025-12-06 · Sign in to download
- Income Tax Return (ITR) Acknowledgement * · 2025-12-06 · Sign in to download
- Project Report · 2025-12-29 · Sign in to download
- NOC/Consent to Operate from Pollution Control Board · 2025-12-05
- Value of the Project as per approved valuer empaneled with Income Tax Department * · 2025-12-29 · Sign in to download
- legal report · 2025-08-29 · Sign in to download
- Sanctioned Letter by TCP/ULB(s)/Local Authority * · 2025-08-29
- Sanctioned Location Plan * · 2025-08-29
- Sanctioned Site Plan * · 2025-11-11
- Sanctioned Building Plan * · 2025-11-11
- Project Specifications * · 2025-12-05 · Sign in to download
- Other Civic Ammenties Map · 2025-10-16 · Sign in to download
- Other Civic Ammenties Map-2 · 2025-10-16 · Sign in to download
- Public and Semi Public area is a facility · 2025-10-16 · Sign in to download
- aggriculture certificate · 2025-11-11 · Sign in to download
- ESTIMATE OF CONSTRUCTION WORKS · 2025-12-05 · Sign in to download
- Park · 2025-08-29 · Sign in to download
- road map · 2025-08-29 · Sign in to download
- 200 mtr STP document · 2025-08-29 · Sign in to download
- LETTER TO CHAIRPERSON · 2025-12-05 · Sign in to download
- IT REGISTRATION CERTIFICATE · 2025-12-29
- Consent Letter · Sign in to download
- Certificate · Sign in to download
- Consent Letter · Sign in to download
- Certificate · Sign in to download
- Consent Letter · Sign in to download
- Certificate · Sign in to download
- Account Details Proof · Sign in to download
- NOC/Consent to Operate from Pollution Control Board
- Sanctioned Letter by TCP/ULB(s)/Local Authority *
- Sanctioned Location Plan *
- Sanctioned Site Plan *
- Sanctioned Building Plan *
- 2025-Q4
- 2026-Q1
- 2026-Q2
- 2026-Q3