Overview
L.I.C.PHASE -II
LAXMI NARAYAN GUPTA · BILASPUR
Units30
Booked21 of 30As of 2026-06-30
Construction progress69%As of 2026-06-30
Completion2026-09-16Revised · Proposed 2022-12-14
Registered on2021-12-15
Cases2
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 2 cases |
| Contract & costs | 2 cost heads · 19 quarters |
| Technical report | |
| Site & area | 3 site details · 30 unit types |
| Construction & progress | 4 progress details · 19 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 74 documents · 8 source links |
Registration
Registration
| Promoter | LAXMI NARAYAN GUPTA | |
|---|---|---|
| District | BILASPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA151221001305 | |
| Registered on | 2021-12-15 | |
| Project type | Plotted Development | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2022-12-14 | |
| Revised completion | 2026-09-16 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXP-2025-03169 | CG RERA | Complaint | Disposed | 2026-01-05 |
| SM-EXP-2024-02292 | CG RERA | Complaint | Disposed | 2024-06-10 |
Complaints & cases
| Cases | 2 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,10,86,000 | |
|---|---|---|
| Construction | ₹70,00,000 |
Quarterly money flows
| 2021-Q4 | ₹0 |
| 2022-Q1 | ₹0 |
| 2022-Q2 | ₹0 |
| 2022-Q3 | ₹0 |
| 2022-Q4 | ₹0 |
| 2023-Q1 | ₹0 |
| 2023-Q2 | ₹0 |
| 2023-Q3 | ₹0 |
| 2023-Q4 | ₹0 |
| 2024-Q1 | ₹0 |
| 2024-Q2 | ₹0 |
| 2024-Q3 | ₹0 |
| 2024-Q4 | ₹0 |
| 2025-Q1 | ₹0 |
| 2025-Q2 | ₹0 |
| 2025-Q3 | ₹0 |
| 2025-Q4 | ₹0 |
| 2026-Q1 | ₹0 |
| 2026-Q2 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 30 | |
|---|---|---|
| Booked | 21 | |
| Booked as of | 2026-06-30 |
Unit types
| LIC CITY PHASE II-1 | 1 | 1 |
| LIC CITY PHASE II-2 | 1 | 0 |
| LIC CITY PHASE II-3 | 1 | 1 |
| LIC CITY PHASE II-4 | 1 | 0 |
| LIC CITY PHASE II-5 | 1 | 0 |
| LIC CITY PHASE II-6 | 1 | 1 |
| LIC CITY PHASE II-7 | 1 | 0 |
| LIC CITY PHASE II-8 | 1 | 1 |
| LIC CITY PHASE II-9 | 1 | 0 |
| LIC CITY PHASE II-10 | 1 | 1 |
| LIC CITY PHASE II-11 | 1 | 0 |
| LIC CITY PHASE II-12 | 1 | 1 |
| LIC CITY PHASE II-13 | 1 | 0 |
| LIC CITY PHASE II-14 | 1 | 1 |
| LIC CITY PHASE II-15 | 1 | 0 |
| LIC CITY PHASE II-16 | 1 | 1 |
| LIC CITY PHASE II-17 | 1 | 1 |
| LIC CITY PHASE II-18 | 1 | 1 |
| LIC CITY PHASE II-19 | 1 | 1 |
| LIC CITY PHASE II-20 | 1 | 1 |
| LIC CITY PHASE II-21 | 1 | 1 |
| LIC CITY PHASE II-22 | 1 | 1 |
| LIC CITY PHASE II-23 | 1 | 1 |
| LIC CITY PHASE II-24 | 1 | 1 |
| LIC CITY PHASE II-25 | 1 | 1 |
| LIC CITY PHASE II-26 | 1 | 1 |
| LIC CITY PHASE II-27 | 1 | 1 |
| LIC CITY PHASE II-28 | 1 | 1 |
| LIC CITY PHASE II-29 | 1 | 1 |
| LIC CITY PHASE II-30 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 69% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2022-12-14 | |
| Revised completion | 2026-09-16 |
Quarterly progress
| 2021-Q4 | 52% |
| 2022-Q1 | 52% |
| 2022-Q2 | 52% |
| 2022-Q3 | 52% |
| 2022-Q4 | 62% |
| 2023-Q1 | 62% |
| 2023-Q2 | 62% |
| 2023-Q3 | 62% |
| 2023-Q4 | 62% |
| 2024-Q1 | 62% |
| 2024-Q2 | 62% |
| 2024-Q3 | 62% |
| 2024-Q4 | 69% |
| 2025-Q1 | 69% |
| 2025-Q2 | 69% |
| 2025-Q3 | 69% |
| 2025-Q4 | 69% |
| 2026-Q1 | 69% |
| 2026-Q2 | 69% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | LAXMI NARAYAN GUPTA | |
|---|---|---|
| Type | Individual | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTE1Mw==
- https://rera.cgstate.gov.in/cause_list.aspx
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-01-05 · Sign in to download
- Final order · 2024-06-10 · Sign in to download
- Interim order · 2025-11-28
- Interim order · 2024-05-08 · Sign in to download
- SM-EXP-2025-03169 · Sign in to download
- SM-EXP-2024-02292 · Sign in to download