Overview
Lake Street
Gulab Valley Developers Pvt. Ltd. · Ludhiana
Units69
Completion2028-02-06Proposed
Valid to2028-02-06
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 51 unit types |
| Construction & progress | 2 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 25 documents · 20 source links |
Registration
Registration
| Promoter | Gulab Valley Developers Pvt. Ltd. | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH45-PC0202 | |
| Valid to | 2028-02-06 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2028-02-06 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Electric Substation NOC | 2023-06-15 | |
| License as Promoter from competent Authority | 2022-05-06 | |
| License to develop colony or society from Competent Authority | ||
| Other Document (Drainage NOC Attached ) | Permissions (Received) | 2023-08-21 |
| Other Document (Forest NOC) | 2023-08-02 | |
| Other Document (Sewerage Connection Approval) | 2023-02-27 | |
| Pollution Clearance from Punjab Pollution Control Board | Permissions (Received) | 2023-09-12 |
| Consent details of actual owner of Land |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹24,78,35,766 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 34,706.025 | |
|---|---|---|
| Units | 69 |
Unit types
| SCO 2 | 869.572 | 1 | SCO PLOT |
| SCO 3 | 869.572 | 1 | SCO PLOT |
| SCO 4 | 869.572 | 1 | SCO PLOT |
| SCO 5 | 869.572 | 1 | SCO PLOT |
| SCO 6 | 869.572 | 1 | SCO PLOT |
| SCO 7 | 869.572 | 1 | SCO PLOT |
| SCO 8 | 4,013.41 | 1 | SCO PLOT |
| SCO 9 | 4,013.41 | 1 | SCO PLOT |
| SCO 10 | 4,013.41 | 1 | SCO PLOT |
| SCO 11 | 4,013.41 | 1 | SCO PLOT |
| SCO 12 | 4,013.41 | 1 | SCO PLOT |
| SCO 13 | 4,013.41 | 1 | SCO PLOT |
| SCO 14 | 4,013.41 | 1 | SCO PLOT |
| SCO 15 | 4,013.41 | 1 | SCO PLOT |
| SCO 16 | 4,013.41 | 1 | SCO PLOT |
| SCO 17 | 4,013.41 | 1 | SCO PLOT |
| SCO 18 | 4,013.41 | 1 | SCO PLOT |
| SCO 19 | 4,013.41 | 1 | SCO PLOT |
| SCO 20 | 4,013.41 | 1 | SCO PLOT |
| SCO 21 | 4,013.41 | 1 | SCO PLOT |
| SCO 22 | 4,013.41 | 1 | SCO PLOT |
| SCO 23 | 4,013.41 | 1 | SCO PLOT |
| SCO 24 | 4,013.41 | 1 | SCO PLOT |
| SCO 25 | 4,013.41 | 1 | SCO PLOT |
| SCO 26 | 4,013.41 | 1 | SCO PLOT |
| SCO 27 | 4,013.41 | 1 | SCO PLOT |
| SCO 28 | 4,013.41 | 1 | SCO PLOT |
| SCO 29 | 4,013.41 | 1 | SCO PLOT |
| SCO 30 | 4,013.41 | 1 | SCO PLOT |
| SCO 31 | 4,013.41 | 1 | SCO PLOT |
| SCO 33 | 2,739.152 | 1 | SCO PLOT |
| SCO 34 | 2,739.152 | 1 | SCO PLOT |
| SCO 35 | 2,739.152 | 1 | SCO PLOT |
| SCO 36 | 2,739.152 | 1 | SCO PLOT |
| SCO 38 | 2,739.152 | 1 | SCO PLOT |
| SCO 39 | 2,739.152 | 1 | SCO PLOT |
| SCO 40 | 2,739.152 | 1 | SCO PLOT |
| SCO 41 | 2,739.152 | 1 | SCO PLOT |
| SCO 42 | 2,739.152 | 1 | SCO PLOT |
| SCO 43 | 2,739.152 | 1 | SCO PLOT |
| SCO 1 | 413.64 | 1 | SCO PLOT |
| SCO 32 | 1,371.249 | 1 | SCO PLOT |
| SCO 54 To 57 | 144.92 | 4 | SCO PLOT |
| Food Court 58 | 185.8 | 1 | SCO PLOT |
| SCO 59 To 62 | 111.48 | 4 | SCO PLOT |
| SCO 63 To 64 | 144.92 | 2 | SCO PLOT |
| SCO 65 To 66 | 232.25 | 2 | SCO PLOT |
| SCO 67 To 68 | 167.22 | 2 | SCO PLOT |
| Food Court 69 | 148.64 | 1 | SCO PLOT |
| SCO 44 To 53 | 130.436 | 10 | SCO PLOT |
| SCO 37 | 130.436 | 1 | SCO PLOT |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-02-07 | |
|---|---|---|
| Proposed completion | 2028-02-06 |
Quarterly progress
| 2024-Q2 | 2024-10-10 |
| 2024-Q3 | 2024-10-10 |
| 2024-Q4 | 2025-01-17 |
| 2025-Q1 | 2025-04-15 |
| 2025-Q2 | 2025-07-15 |
| 2025-Q3 | 2025-10-15 |
| 2025-Q4 | 2026-01-15 |
| 2026-Q1 | 2026-04-14 |
| 2026-Q2 | 2026-07-11 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Gulab Valley Developers Pvt. Ltd. | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11665&inPromoter_ID=2550&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2023-06-15
- License as Promoter from competent Authority · 2022-05-06
- License to develop colony or society from Competent Authority
- Other Document (Drainage NOC Attached ) · 2023-08-21
- Other Document (Forest NOC) · 2023-08-02
- Other Document (PPCB corrigendum) · 2023-09-13 · Sign in to download
- Other Document (Sewerage Connection Approval) · 2023-02-27
- Pollution Clearance from Punjab Pollution Control Board · 2023-09-12
- Consent details of actual owner of Land
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2023-06-15
- License as Promoter from competent Authority · 2022-05-06
- License to develop colony or society from Competent Authority
- Other Document (Drainage NOC Attached ) · 2023-08-21
- Other Document (Forest NOC) · 2023-08-02
- Other Document (Sewerage Connection Approval) · 2023-02-27
- Pollution Clearance from Punjab Pollution Control Board · 2023-09-12
- Consent details of actual owner of Land
- 2024-Q2 · 2024-10-10
- 2024-Q3 · 2024-10-10
- 2024-Q4 · 2025-01-17
- 2025-Q1 · 2025-04-15
- 2025-Q2 · 2025-07-15
- 2025-Q3 · 2025-10-15
- 2025-Q4 · 2026-01-15
- 2026-Q1 · 2026-04-14
- 2026-Q2 · 2026-07-11