Overview
LARISSA EN ROUTE
AGK INFRA · Rupnagar (Ropar)
Units61
Completion2030-05-07Proposed
Valid to2030-05-07
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 12 unit types |
| Construction & progress | 2 progress details · 4 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 26 documents · 17 source links |
Registration
Registration
| Promoter | AGK INFRA | |
|---|---|---|
| District | Rupnagar (Ropar) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-RPR70-PC0380 | |
| Valid to | 2030-05-07 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2030-05-07 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Electric Substation NOC | 2025-05-17 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2025-02-28 | |
| NOC from Mining Department | 2025-03-13 | |
| NOC from NHAI/ PWD | 2025-05-19 | |
| Other Document (Affidavit for NOC ) | Legal Documents (Received) | 2025-08-18 |
| Other Document (Forest NOC) | 2025-03-20 | |
| Pollution Clearance from Punjab Pollution Control Board | 2025-08-20 | |
| Pollution Clearance from Punjab Pollution Control Board | 2025-08-16 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹6,23,44,323 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 15,529.812 | |
|---|---|---|
| Units | 61 |
Unit types
| Plot No 1 | 250.838 | 1 | COMMERCIAL |
| Plot No 2 | 301.933 | 1 | COMMERCIAL |
| Plot No 3 to 14 | 107.768 | 12 | COMMERCIAL |
| Plot No 15 to 19 | 40.134 | 5 | COMMERCIAL |
| Plot No 20 to 30 | 89.189 | 11 | COMMERCIAL |
| Plot No 31 | 71.998 | 1 | COMMERCIAL |
| Plot No 32 to 35 | 40.134 | 4 | COMMERCIAL |
| Plot No 36 to 42 | 108.696 | 7 | COMMERCIAL |
| Plot No 43 to 52 | 62.709 | 10 | COMMERCIAL |
| Plot No 53 | 28.219 | 1 | COMMERCIAL |
| Plot No 54 to 56 | 27.868 | 3 | COMMERCIAL |
| Plot No 57 to 61 | 69.674 | 5 | COMMERCIAL |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-05-08 | |
|---|---|---|
| Proposed completion | 2030-05-07 |
Quarterly progress
| 2025-Q4 | 2026-10-15 |
| 2026-Q1 | 2026-10-15 |
| 2026-Q2 | 2026-10-15 |
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AGK INFRA | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12459&inPromoter_ID=3368&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-05-17
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2025-02-28
- NOC from Mining Department · 2025-03-13
- NOC from NHAI/ PWD · 2025-05-19
- Other Document (Architect Certificate for HT and EC) · 2025-08-11 · Sign in to download
- Other Document (Forest NOC) · 2025-03-20
- Pollution Clearance from Punjab Pollution Control Board · 2025-08-20
- Pollution Clearance from Punjab Pollution Control Board · 2025-08-16
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2025-05-17
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2025-02-28
- NOC from Mining Department · 2025-03-13
- NOC from NHAI/ PWD · 2025-05-19
- Other Document (Affidavit for NOC ) · 2025-08-18
- Other Document (Forest NOC) · 2025-03-20
- Pollution Clearance from Punjab Pollution Control Board · 2025-08-20
- Pollution Clearance from Punjab Pollution Control Board · 2025-08-16
- 2025-Q4 · 2026-10-15
- 2026-Q1 · 2026-10-15
- 2026-Q2 · 2026-10-15
- 2026-Q3 · 2026-10-15