DOSLChhattisgarh Workspace

Overview

LAXMI EMPIRE BLOCK-A-II PHASE-I

LAXMI BUILDERS · DURG
Units48
Booked0 of 48As of 2023-09-30
Construction progress0%As of 2023-09-30
Completion2024-12-30Revised · Proposed 2024-03-31
Registered on2019-05-08
Approvals3

Sections

Property title & search report
Approvals3 approvals
Disputes & cases1 registration detail
Contract & costs2 cost heads · 18 quarters
Technical report
Site & area3 site details · 1 unit type
Construction & progress4 progress details · 18 quarters
Developer & finance
Developer4 developer details
The evidence
Sources69 documents · 4 source links

Registration

Registration

PromoterLAXMI BUILDERS
DistrictDURG
RegulatorCG RERA
Registration numberPCGRERA080519000969
Registered on2019-05-08
Project typeGroup Housing
Status (as filed)New
Proposed completion2024-03-31
Revised completion2024-12-30