Are there court cases or buyer complaints on this project?
Locked
Cases on the land
Cases on the builder
RERA complaints
Builder's other projects
Filed onCase no.Filed atWhat it's aboutStatus
₹ ••,•••
•• %
•• ••• ••••
Contract & costs
What does a buyer commit to?
We haven't verified this for this project yet.
Sign in first, then it is one click.
Not verified yet: Forfeiture, agreement; Forfeiture, allotment letter; Transfer fee; Maintenance included; Agreement and allotment letter; Payment plan; Agreement for sale.
Valuation
What is it worth?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
This project
Unit sizes
Floor plans, brochure
No floor plans on file
Unsold stock
K-RERA inventory
Sold, Q2 2026-27
6 / 24
Unsold, Q2 2026-27
18
Location & risks
What is the location like?
Groundwater, taluk average22.7 m below groundBengaluru North taluk, July 2023
Water supply, as filedLocal authorityDeclared by the promoter
Metro, operational480 mCubbon Park
Construction & progress
How is it being built, and when will it be ready?
Review1 to review · 1 clear
Completion96%As of Q2 2026-27, promoter's return
Progress
Completion, as the promoter reported it
Developer
Can the developer deliver?
Review1 to review · 1 clear
Receivable, sold flats₹8.36 CrAs of Q1 2026-27
Cost left₹5.58 CrAs of Q1 2026-27
Sold6 / 24As of Q2 2026-27
Sold in Q2 2026-270✓ClearClear
Funding
Estimated cost
Loan & collateral
Can it be financed?
Conditions
Collateral checks
Escrow bank
HDFC · Miller road
Stage
Progress as reported, by quarter
Data room
Documents filed for this project
Locked
87 documents filed with K-RERA for this project
DocumentFolderPagesFiled
₹ ••,•••
•• %
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Unlock this full report
₹99 for this report opens Disputes & cases and Documents for this project, yours to read for good.
Unlock this full report₹99 for this report · opens Disputes & cases and DocumentsUnlock
Survey plots · KGIS cadastral
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Legacy Cataleya in the interactive atlas
Survey sketch filed with K-RERA
No survey sketch is listed on this phase's K-RERA filing
Land record
Survey plots · KGIS cadastral
Imagery: Esri, Vantor, Earthstar Geographics
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
Not verified yet: Title opinion; Records searched to; Charges on the land; Landowner share of sales; How the land reached this project; Court-case search; High Court order; Charges; Schedule in the EC vs KGIS neighbours; Sketch, sanction and mutation vs KGIS map; Area on the KGIS map; The RTC of each filed survey; Share of sales revenue; Joint development agreement.
RERA
K-RERA
RERA extensions
Granted · Approved 19 Dec 2022
RERA completion date
30 Sep 2026
Registration certificates
PRM/KA/RERA/1251/309/PR/171016/000867
EX/PRM/KA/RERA/1251/309/PR/221219/000867
Not verified yet: Building plan, Land conversion, Validity, Environmental clearance, Pollution board (CFE), Conversion order.
•••••
₹ •.•• Cr
•• of ••
Unlock this full report
₹99 for this report opens Disputes & cases and Documents for this project, yours to read for good.
Not verified yet: Recent price, super built-up; Recent price, carpet; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Unit mix filed; Unit types; Transactions in this project; Central Bengaluru, past year; Bengaluru, past year; Central Bengaluru since 2022; This project vs Central Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Bengaluru median yield.
Land · ₹10.11 Cr 15.8%Development · ₹53.89 Cr 84.2%
Cost left vs buyer dues
Form 4
Estimated cost, at registration
₹64.00 Cr
Estimated cost, Form 4 Q1 2026-27
₹74.00 Cr
Cost incurred
₹68.42 Cr (92.5% of the Form 4 Q1 2026-27 estimate)
Cost left
₹5.58 Cr
Receivable, sold flats
₹8.36 Cr
Sales
Sold vs unsold, Q2 2026-27
Sold (6) 25%Unsold (18) 75%
Sold per quarter
K-RERA inventory
Sold, Q3 2025-26
6 / 24 · 18 available
Sold, Q4 2025-26
6 / 24 · 18 available
Sold, Q1 2026-27
6 / 24 · 18 available
Sold, Q2 2026-27
6 / 24 · 18 available
Unsold, Q2 2026-27
18
Sold in Q4 2025-26
0
Sold in Q1 2026-27
0
Sold in Q2 2026-27
0
4BHK, sold
6 / 24
Compliance
Escrow, Q2 2026-27
Escrow and filings
Escrow bank
HDFC · Miller road
Designated account, collected
₹0 in Q2 2026-27
Designated account, withdrawn
₹0 in Q2 2026-27
Amount withdrawable, Form 4
₹47,36,00,000
Net amount withdrawable, Form 4
₹34,51,69,237
Escrow account to date, Q2 2026-27
₹12.84 Cr deposited from sales, ₹12.84 Cr withdrawn
Track record
Average schedule slip
DOSL builder track
K-RERA registrations under this promoter
11
Marked completed
1
Past promised date, not completed
7
!Review
Other phases under this promoter name
10
With a filed extension or completion
5 (1 completed, 4 extended)
Average schedule slip
36 months
Not verified yet: Collected from buyers; Land cost revision; Unregistered agreements, over 10% paid.
Site photos, Q1 2026-27
Not verified yet: Value; Max loan; Borrower margin; Developer's project loan; Example unit; Calculation; Records searched to; Building plan; Unregistered agreements, over 10% paid; Sale deed in favour of.
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
Bengaluru North taluk average, July 2023: 22.7 m below ground
What it means
20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 7 CGWB wells in Bengaluru North taluk read in this class
Through the year
January 2025: 2.6 m (5 wells), Pre-monsoon 2025: 2.9 m (7 wells), August 2025: 3.2 m (7 wells), depth below ground of CGWB's monitoring wells in Bengaluru North taluk (the median where there are several)
Water supply, as filed
Local authority
Nearest city water main
70 m
Distances
Within 3 km
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.