Overview
LILAWATI VILLA
SUMITRA HOMES · Patna
Units13
Booked2 of 13As of 2026-09-30
Construction progress35%As of 2026-09-30
Completion2029-10-27Proposed
Registered on2025-04-18
Valid to2029-10-27
Approvals11
Sections
| Property title & search report | |
|---|---|
| Approvals | 11 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 3 unit types |
| Construction & progress | 4 progress details · 6 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 22 documents · 12 source links |
Registration
Registration
| Promoter | SUMITRA HOMES | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP182228070425271029E00 | |
| Registered on | 2025-04-18 | |
| Valid to | 2029-10-27 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2029-10-27 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | EXECUTIVE OFFICER, DANAPUR | |
| Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc. | ||
| Environmental Clearance Certificate | ||
| NOC From Airport Authority of India | ||
| NOC from Fire Service Authority | ||
| Notice of Commencement in form X | ||
| Environment Clearance | 2025-01-01 | |
| Fire NOC | 2025-01-01 | |
| Airport NOC | 2025-01-01 | |
| Water Supply Permission | 2025-01-01 | |
| Other approval | 2025-01-01 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,00,32,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 613.62 | |
|---|---|---|
| Built-up (m²) | 1,058.03 | |
| FAR | 1.72 | |
| Towers | 1 | |
| Units | 13 | |
| Booked | 2 | |
| Booked as of | 2026-09-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 2 BHK | 3 | LILAWATI VILLA |
| 1 BHK | 1 | LILAWATI VILLA |
| 3 BHK | 9 | LILAWATI VILLA |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 35% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2025-02-15 | |
| Proposed completion | 2029-10-27 |
Quarterly progress
| 2026-Q3 | 2026-10-26 | 35% | 2 |
| 2026-Q2 | 2026-07-26 | ||
| 2026-Q1 | 2026-04-21 | ||
| 2025-Q4 | 2026-01-31 | ||
| 2025-Q3 | 2025-11-01 | ||
| 2025-Q2 | 2025-08-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SUMITRA HOMES | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Union Bank of India | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP01142022203227-2
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP01142022203227&ld=pan&pj=RERAP01142022203227-2&f=2026-2027&q=2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP01142022203227-2
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- A certificate from a Chartered accountant declaring that no advance booking amount has been taken from the customers against the current project duly signed by the promoter and countersigned by CA · Sign in to download
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Environmental Clearance Certificate
- NOC From Airport Authority of India
- NOC from Fire Service Authority
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-26
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-26
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-21
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-31
- Q2 (Jul - Sep) / 2025-2026 · 2025-11-01
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-14
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Notice of Commencement in form X
- 2026-Q2 · 2026-07-26
- 2026-Q1 · 2026-04-21
- 2025-Q4 · 2026-01-31
- 2025-Q3 · 2025-11-01
- 2025-Q2 · 2025-08-14