Overview
LOTUS ABODE
NUTAN CONSTRUCTION · Patna
Units202
Completion2021-06-30Proposed
Registered on2018-04-18
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 9 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details · 3 professional firms |
| The evidence | |
| Sources | 17 documents · 6 source links |
Registration
Registration
| Promoter | NUTAN CONSTRUCTION | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00041-1/17/R-04/18 | |
| Registered on | 2018-04-18 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Completed | |
| Proposed completion | 2021-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹18,16,20,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 9,130 | |
|---|---|---|
| Built-up (m²) | 0 | |
| FAR | 2.5 | |
| Towers | 2 | |
| Units | 202 |
Unit types
| 2 BHK | 22 | LOTUS ABODE |
| 2 BHK | 22 | LOTUS ABODE |
| 2 BHK | 22 | LOTUS ABODE |
| 3.5 BHK | 44 | LOTUS ABODE |
| 3.5 BHK | 22 | LOTUS ABODE |
| 3 BHK | 22 | LOTUS ABODE |
| 3.5 BHK | 22 | LOTUS ABODE |
| Penthouse | 4 | LOTUS ABODE |
| 3 BHK | 22 | LOTUS ABODE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-06-01 | |
|---|---|---|
| Proposed completion | 2021-06-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | NUTAN CONSTRUCTION | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Union Bank of India | |
| Other projects in this city pack | 9 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | COMPUTER FOUNDATION PVT. LTD |
| Architect | FROM SPACE N DESIGN ARCHITECTS |
| Contractor | NAINGRAM MULTIWINGS PVT LTD OPC |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP2711201700041-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP2711201700041-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement