Overview

LOTUS TOWER PHASE I

A. DHEBAR BUILDCON · RAIPUR
Units256
Booked203 of 256As of 2021-06-30
Construction progress100%As of 2021-06-30
Completion2021-11-28Revised · Proposed 2020-03-31
Registered on2018-06-28
Approvals4
Cases2

Sections

Property title & search report
Approvals4 approvals
Disputes & cases2 cases
Contract & costs2 cost heads · 12 quarters
Technical report
Site & area3 site details · 1 unit type
Construction & progress4 progress details · 12 quarters
Developer & finance
Developer4 developer details
The evidence
Sources54 documents · 11 source links

Registration

Registration

PromoterA. DHEBAR BUILDCON
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA280618000378
Registered on2018-06-28
Project typeGroup Housing
Status (as filed)Ongoing
Proposed completion2020-03-31
Revised completion2021-11-28