Overview
LOTUS TOWER PHASE II
A. DHEBAR BUILDCON · RAIPUR
Units1,032
Booked177 of 1,032As of 2023-12-31
Construction progress20%As of 2023-12-31
Completion2025-12-30Revised · Proposed 2025-03-31
Registered on2018-06-28
Approvals3
Cases5
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 5 cases |
| Contract & costs | 2 cost heads · 22 quarters |
| Technical report | |
| Site & area | 3 site details · 1 unit type |
| Construction & progress | 4 progress details · 22 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 105 documents · 13 source links |
Registration
Registration
| Promoter | A. DHEBAR BUILDCON | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA280618000377 | |
| Registered on | 2018-06-28 | |
| Project type | Group Housing | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2025-03-31 | |
| Revised completion | 2025-12-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| M-PRO-2026-03549 | CG RERA | Complaint | Disposed | 2026-07-13 |
| M-COM-2019-00423 | CG RERA | Complaint | Disposed | 2022-10-28 |
| M-PRO-2019-00831 | CG RERA | Complaint | Disposed | 2020-02-13 |
| M-PRO-2018-00153 | CG RERA | Complaint | Disposed | 2019-03-07 |
| M-PRO-2018-00152 | CG RERA | Complaint | Disposed | 2019-02-23 |
Complaints & cases
| Cases | 5 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹12,55,46,000 | |
|---|---|---|
| Construction | ₹85,09,89,000 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹0 |
| 2019-Q1 | ₹0 |
| 2019-Q2 | ₹0 |
| 2019-Q3 | ₹0 |
| 2019-Q4 | ₹0 |
| 2020-Q1 | ₹0 |
| 2020-Q2 | ₹0 |
| 2020-Q3 | ₹0 |
| 2020-Q4 | ₹0 |
| 2021-Q1 | ₹0 |
| 2021-Q2 | ₹0 |
| 2021-Q3 | ₹0 |
| 2021-Q4 | ₹0 |
| 2022-Q1 | ₹13,302 |
| 2022-Q2 | ₹14,152 |
| 2022-Q3 | ₹14,152 |
| 2022-Q4 | ₹14,152 |
| 2023-Q1 | ₹14,072 |
| 2023-Q2 | ₹14,072 |
| 2023-Q3 | ₹14,072 |
| 2023-Q4 | ₹14,072 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 1,032 | |
|---|---|---|
| Booked | 177 | |
| Booked as of | 2023-12-31 |
Unit types
| Type | Carpet (m²) | Units | Booked |
|---|---|---|---|
| 2BHK | 78,618 | 1,032 | 177 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 20% | |
|---|---|---|
| As of | 2023-12-31 | |
| Proposed completion | 2025-03-31 | |
| Revised completion | 2025-12-30 |
Quarterly progress
| 2018-Q3 | 18% |
| 2018-Q4 | 18% |
| 2019-Q1 | 20% |
| 2019-Q2 | 20% |
| 2019-Q3 | 20% |
| 2019-Q4 | 20% |
| 2020-Q1 | 20% |
| 2020-Q2 | 20% |
| 2020-Q3 | 20% |
| 2020-Q4 | 20% |
| 2021-Q1 | 20% |
| 2021-Q2 | 20% |
| 2021-Q3 | 20% |
| 2021-Q4 | 20% |
| 2022-Q1 | 20% |
| 2022-Q2 | 20% |
| 2022-Q3 | 20% |
| 2022-Q4 | 20% |
| 2023-Q1 | 20% |
| 2023-Q2 | 20% |
| 2023-Q3 | 20% |
| 2023-Q4 | 20% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | A. DHEBAR BUILDCON | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | YES Bank | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=NDY0
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-07-13 · Sign in to download
- Final order · 2022-10-28 · Sign in to download
- Final order · 2020-02-13 · Sign in to download
- Final order · 2019-03-07 · Sign in to download
- Final order · 2019-02-23 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities
- M-PRO-2026-03549 · Sign in to download
- M-COM-2019-00423 · Sign in to download
- M-PRO-2019-00831 · Sign in to download
- M-PRO-2018-00153 · Sign in to download
- M-PRO-2018-00152 · Sign in to download