DOSLKarnataka Workspace

Overview

LTG Ascent Phase - 1

LTG Infrastructure Limited · Ramanagara
Completion2023-02-25Proposed
Registered on2020-10-01
Valid to2023-02-25
Approvals7
Complaints0

Sections

Property title & search report
Approvals7 approvals
Disputes & cases0 project complaints · 0 promoter complaints
Contract & costs3 cost heads
Technical report
Site & area1 site detail
Construction & progress2 progress details
Developer & finance
Developer4 developer details
The evidence
Sources88 documents · 10 source links

Registration

Registration

PromoterLTG Infrastructure Limited
DistrictRamanagara
RegulatorK-RERA
Registration numberPRM/KA/RERA/1270/302/PR/201001/003618
Registered on2020-10-01
Valid to2023-02-25
Project typePlotted Development
Status (as filed)APPROVED
Proposed completion2023-02-25