M. K. TOWER
RUDRA CONSTRUCTIONS · Patna
Units48
Completion2025-02-28Proposed
Registered on2020-05-06
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 1 unit type |
| Construction & progress | 2 progress details · 12 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 22 documents · 17 source links |
Registration
Registration
| Promoter | RUDRA CONSTRUCTIONS | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP000178-4/1187/R-953/2020 | |
| Registered on | 2020-05-06 | |
| Project type | Mixed Development(residential and commercial) | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2025-02-28 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹8,46,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,163.52 | |
|---|---|---|
| Built-up (m²) | 6,609.66 | |
| FAR | 3.06 | |
| Towers | 1 | |
| Units | 48 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 48 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2020-02-10 | |
|---|---|---|
| Proposed completion | 2025-02-28 |
Quarterly progress
| 2024-Q2 | 2024-07-15 |
| 2024-Q1 | 2024-07-25 |
| 2023-Q4 | 2024-07-25 |
| 2023-Q3 | 2024-07-25 |
| 2023-Q2 | 2024-07-25 |
| 2023-Q1 | 2023-04-15 |
| 2022-Q4 | 2023-04-20 |
| 2022-Q3 | 2022-11-17 |
| 2022-Q2 | 2022-08-30 |
| 2022-Q1 | 2022-05-06 |
| 2021-Q4 | 2022-01-18 |
| 2021-Q3 | 2021-10-12 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RUDRA CONSTRUCTIONS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 7 |
Professional firms
| Role | Firm |
|---|---|
| Architect | A. R. & ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP272201800178-4
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP272201800178-4
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q1-Apr to Jun / 2024-2025 · 2024-07-15
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-15
- Q3-Oct to Dec / 2022-2023 · 2023-04-20
- Q2-Jul to Sep / 2022-2023 · 2022-11-17
- Q1-Apr to Jun / 2022-2023 · 2022-08-30
- Q4-Jan to Mar / 2021-2022 · 2022-05-06
- Q3-Oct to Dec / 2021-2022 · 2022-01-18
- Q2-Jul to Sep / 2021-2022 · 2021-10-12
- Notice of Commencement
- 2024-Q2 · 2024-07-15
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-15
- 2022-Q4 · 2023-04-20
- 2022-Q3 · 2022-11-17
- 2022-Q2 · 2022-08-30
- 2022-Q1 · 2022-05-06
- 2021-Q4 · 2022-01-18
- 2021-Q3 · 2021-10-12