Overview
M/S SHIVNATH APARTMENTS
SHIVNATH APARTMENTS · RAIPUR
Units22
Booked0 of 22As of 2024-12-31
Construction progress100%As of 2024-12-31
Completion2025-11-09Proposed
Registered on2022-03-07
Cases1
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 12 quarters |
| Technical report | |
| Site & area | 3 site details · 22 unit types |
| Construction & progress | 3 progress details · 12 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 62 documents · 6 source links |
Registration
Registration
| Promoter | SHIVNATH APARTMENTS | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA070322001353 | |
| Registered on | 2022-03-07 | |
| Project type | Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2025-11-09 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| M-PRO-2025-02906 | CG RERA | Complaint | Disposed | 2025-07-21 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,88,10,000 | |
|---|---|---|
| Construction | ₹4,47,65,000 |
Quarterly money flows
| 2022-Q1 | ₹0 |
| 2022-Q2 | ₹0 |
| 2022-Q3 | ₹0 |
| 2022-Q4 | ₹4,32,000 |
| 2023-Q1 | ₹1,06,000 |
| 2023-Q2 | ₹5,05,000 |
| 2023-Q3 | ₹2,05,000 |
| 2023-Q4 | ₹1,300 |
| 2024-Q1 | ₹97,96,000 |
| 2024-Q2 | ₹1,46,26,000 |
| 2024-Q3 | ₹30,000 |
| 2024-Q4 | ₹30,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 22 | |
|---|---|---|
| Booked | 0 | |
| Booked as of | 2024-12-31 |
Unit types
| 3BHK | 162.5 | 1 | 0 |
| 3BHK | 162.5 | 1 | 0 |
| 3BHK | 104.83 | 1 | 0 |
| 3BHK | 104.63 | 1 | 0 |
| 3BHK | 102.1 | 1 | 0 |
| 3BHK | 102.3 | 1 | 0 |
| 3BHK | 104.83 | 1 | 0 |
| 3BHK | 104.63 | 1 | 0 |
| 3BHK | 102.1 | 1 | 0 |
| 3BHK | 102.3 | 1 | 0 |
| 3BHK | 104.83 | 1 | 0 |
| 3BHK | 104.63 | 1 | 0 |
| 3BHK | 102.1 | 1 | 0 |
| 3BHK | 102.3 | 1 | 0 |
| 3BHK | 104.83 | 1 | 0 |
| 3BHK | 101.63 | 1 | 0 |
| 3BHK | 102.1 | 1 | 0 |
| 3BHK | 102.3 | 1 | 0 |
| 3BHK | 104.83 | 1 | 0 |
| 3BHK | 101.63 | 1 | 0 |
| 3BHK | 102.1 | 1 | 0 |
| 3BHK | 102.3 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2024-12-31 | |
| Proposed completion | 2025-11-09 |
Quarterly progress
| 2022-Q1 | 32% |
| 2022-Q2 | 32% |
| 2022-Q3 | 32% |
| 2022-Q4 | 56% |
| 2023-Q1 | 67% |
| 2023-Q2 | 86% |
| 2023-Q3 | 90% |
| 2023-Q4 | 95% |
| 2024-Q1 | 95% |
| 2024-Q2 | 99% |
| 2024-Q3 | 99% |
| 2024-Q4 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHIVNATH APARTMENTS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTY2MQ==
- https://rera.cgstate.gov.in/cause_list.aspx
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Final order · 2025-07-21 · Sign in to download
- M-PRO-2025-02906 · Sign in to download