Overview
M2K HARMONY
ELITE HOMES PRIVATE LIMITED · Rewari
Units107
Completion2023-03-31Proposed
Valid to2024-10-31
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 17 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 21 documents · 2 source links |
Registration
Registration
| Promoter | ELITE HOMES PRIVATE LIMITED | |
|---|---|---|
| District | Rewari | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-RWR-227-2021 | |
| Valid to | 2024-10-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2023-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 23 OF 2020 | Town & Country Planning Department | |
| Layout Plan | 2020-09-03 | ||
| Building Plan | |||
| I. LAYOUT PLAN | 2020-09-03 | ||
| II. NOC FROM FOREST DEPARTMENT | 2015-03-11 | ||
| III. LICENCE UNDER DDJAY-2016 | 2020-08-31 | ||
| IV. APPROVAL OF ELECTRIFICATION PLAN FROM DHBVN | 2020-10-14 | ||
| V. APPROVAL OF SERVICE ESTIMATE FROM DTCP/ HUDA/ HSVP | 2020-10-13 | ||
| VI. DEMARCATION PLAN FROM DTCP | 2020-10-21 | ||
| VII. NOC FROM HARYANA POLLUTION CONTROL BOARD |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,16,10,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹9,39,55,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 20,917.156 | |
|---|---|---|
| Units | 107 |
Unit types
| Plot | 1 | |
| Plot | 3 | |
| Plot | 3 | |
| Plot | 7 | |
| Plot | 8 | |
| Plot | 5 | |
| Plot | 5 | |
| Plot | 17 | |
| Plot | 16 | |
| Plot | 1 | |
| Plot | 7 | |
| Plot | 12 | |
| Plot | 2 | |
| Plot | 7 | |
| Plot | 7 | |
| Apartment/Shops/Other Buildings | 49.186 | 1 |
| Apartment/Shops/Other Buildings | 48.703 | 5 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2020-12-01 | |
|---|---|---|
| Proposed completion | 2023-03-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ELITE HOMES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | IDBI BANK | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/view_project/project_preview_open/1470
- Registration Certificate
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2020-10-22 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2020-10-23
- STREET LIGHTING PLAN · 2020-11-02
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2020-10-23
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2020-10-23
- ZONING PLAN · 2020-10-23
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2020-11-02
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2020-11-02 · Sign in to download
- DEMARCATION PLAN · 2020-11-02
- ELECTRICITY SUPPLY PLAN · 2020-11-02
- ROAD & PAVEMENT PLAN · 2020-11-02
- SEWERAGE AND GARBAGE DISPOSAL PLAN · 2020-11-02
- STORM WATER DRAINAGE PLAN · 2020-11-02
- WATER SUPPLY PLAN · 2020-11-02
- SCO LAYOUT PLAN ON COMMERCIAL PLOT · 2020-11-03
- RC Uploaded · 2023-07-24 · Sign in to download
- Corrigendum Issued · 2023-08-11 · Sign in to download
- First Extension · 2023-10-18 · Sign in to download
- Extension uploaded. · 2025-07-29 · Sign in to download
- Completion certificate · 2026-02-20 · Sign in to download