Overview
M3M INTERNATIONAL FINANCIAL CENTER INCLUDING PHASE I & II
GENTLE REALTORS PRIVATE LIMITED · Gurugram
Completion2024-12-31Revised · Proposed 2024-12-31
Registered on2022-05-23
Valid to2024-12-31
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 1 unit type |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 45 documents · 2 source links |
Registration
Registration
| Promoter | GENTLE REALTORS PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/564/296/2022/39 DATED 23.05.2022 | |
| Registered on | 2022-05-23 | |
| Valid to | 2024-12-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2024-12-31 | |
| Revised completion | 2024-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 165 of 2008 dated 8.09.2008 | Town & Country Planning Department | |
| Layout Plan | 2021-03-22 | ||
| Building Plan | 2021-03-22 | ||
| I. LICENCE | 2008-09-08 | ||
| II. ZONING PLAN | 2013-10-31 | ||
| III. SERVICE PLAN ESTIMATES | 2021-04-09 | ||
| IV. ENVIRONMENT CLEARANCE | 2018-04-04 | ||
| V. ARAVALI | 2014-05-13 | ||
| VI. NOC FOR HEIGHT CLEARANCE | 2017-11-03 | ||
| VII. BUILDING PLAN APPROVAL | 2021-03-22 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,26,16,70,000 | |
|---|---|---|
| Construction | ₹2,85,95,40,000 | |
| Total | ₹5,32,24,30,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 3.62 |
|---|
Unit types
| Type |
|---|
| 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-05-04 | |
|---|---|---|
| Proposed completion | 2024-12-31 | |
| Revised completion | 2024-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GENTLE REALTORS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI BANK LIMITED | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1544
- Registration Certificate · 2022-05-23
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2021-02-03
- LC- IV · 2021-02-03 · Sign in to download
- LOI · 2021-02-03 · Sign in to download
- ENVIRONMENT CLEARANCE · 2021-02-03
- ZONING PLAN · 2021-02-03
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2021-02-03
- LICENCE RENEWAL · 2021-02-03
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2021-02-18 · Sign in to download
- BOARD RESOLUTIONS · 2021-02-18 · Sign in to download
- NEC · 2021-02-18 · Sign in to download
- SERVICE PLAN APPLICATION · 2021-02-18
- DEMARCATION PLAN · 2021-02-18
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2021-02-18
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2021-02-18
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2021-02-18
- 165 OF 2008- LC-IV · 2021-03-30 · Sign in to download
- REVISED ZONING UNDER TOD_FINAL · 2021-03-30 · Sign in to download
- BR III -REVISED GENTLE-22.03.2021 · 2021-03-30 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2021-03-30 · Sign in to download
- GENTLE_DEMARCATION SUPERIMPOSED ON SITE PLAN-MODEL · 2021-03-30
- SITE PLAN2 18-02-2021-MODEL_FOR PARKING · 2021-03-30
- 12TH, 12-A FLOOR & TERRACE PLAN-TOWER-2 (PHASE-II) · 2021-03-30
- 23RD SERVICE FLOOR CARPET AREA DIAGRAM WITH DETAIL-TOWER 1 · 2021-03-30 · Sign in to download
- 38TH TO 43RD FLOOR CARPET AREA DIAGRAM WITH DETAIL · 2021-03-30 · Sign in to download
- 39TH FLOOR PLAN TOWER-1 (PHASE III) · 2021-03-30
- 40TH, 41ST, 41A, 42ND & 42A FLOOR AREA DIAGRAM WITH DETAIL · 2021-03-30 · Sign in to download
- 41A FLOOR PLAN-TOWER 1 (PHASE-III) · 2021-03-30
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2022-04-08 · Sign in to download
- SERVICE PLAN ROAD · 2022-04-08
- SERVICE PLAN WATER · 2022-04-08
- SERVICE PLAN SEWER · 2022-04-08
- SERVICE PLAN STORM WATER · 2022-04-08
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2022-05-17 · Sign in to download
- GENTLE REVISED FIRE APPROVAL · 2022-05-17
- REP II IFC · 2022-05-17 · Sign in to download
- TOWER-1 40TH, 41ST & 42ND FLOOR CARPET AREA DIAGRAM WITH DETAIL · 2022-05-17 · Sign in to download
- TOWER-1 (PHASE II)TYPICAL FLOOR PLAN · 2022-05-17
- TOWER 1 (23RD FLOOR) 26TH, 30TH, 34TH 38TH FLOOR · 2022-05-17 · Sign in to download
- 43RD FLOOR PLAN-TOWER 1 (PHASE-III) · 2022-05-17
- 43 FLOOR AREA DIAGRAM WITH DETAIL · 2022-05-17 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2022-05-19 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download